This is a bid tabulation document for the "Fixing Our Streets Street Lighting Infill Project," Bid No. 00002459, managed by Briana Orr for an Oregon state or local government entity. The project encompasses two distinct locations: T01029 at Killingsworth/42nd-Portland Highway and T01052 at Capital Highway/49th Avenue in the Garden Home-Stephenson area. The scope of work includes street lighting infrastructure installation with standard construction components including mobilization, traffic control, pollution control, tree preservation, lighting poles, pole arms, luminaires, and electrical switching, conduit, and wiring. The bid was opened on December 19, 2024, with no additional information provided regarding site visits, bidder conferences, or award dates.
The engineer's estimate for the total project was $1,000,000. Global Electric, Inc., holding Contractor Board License No. 156838, submitted the sole bid with a total project cost of $919,500.00, consisting of $420,000.00 for the T01029 location and $499,500.00 for the T01052 location, representing a savings of approximately $80,500 against the engineer's estimate. The bidder provided bid surety and met bonding requirements. No information is provided regarding set-asides, incumbents, funding sources, or contract term and renewal options.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid No: 00002459 Project Name: Fixing Our Streets Street Lighting Infill Project Date Bid Opened: 12/19/2024 Project Manager: Briana Orr Engineers Estimate: $1,000,000
Item Spec Est.
No Description Reference Quant Units Unit Price Extended
T01029 - Killingswort: 42nd-Portland Hwy
1 MOBILIZATION 0210 1 LS $20,000.00 $20,000.00
TEMPORARY PROTECTION AND
DIRECTION OF TRAFFIC 0221 1 LS $22,500.00 $22,500.00
3 POLLUTION CONTROL PLAN 0290 1 LS $2,000.00 $2,000.00
4 TREE PRESERVATION AND PRUNING 0325 1 LS $7,500.00 $7,500.00
5 LIGHTING POLES 0970 1 LS $10,000.00 $10,000.00
6 LIGHTING POLE ARMS 0970 1 LS $15,000.00 $15,000.00
7 LUMINAIRES 0970 1 LS $55,000.00 $55,000.00
8 SWITCHING, CONDUIT AND WIRING 0970 1 LS $288,000.00 $288,000.00
Subtotal T01029 $420,000.00 T01052 - Capital Hwy/49th Ave: Garden Home-Stephenson
9 MOBILIZATION 0210 1 LS $20,000.00 $20,000.00
TEMPORARY PROTECTION AND
DIRECTION OF TRAFFIC 0221 1 LS $45,000.00 $45,000.00
11 POLLUTION CONTROL PLAN 0290 1 LS $2,000.00 $2,000.00
12 TREE PRESERVATION AND PRUNING 0325 1 LS $7,500.00 $7,500.00
13 LIGHTING POLES 0970 1 LS $80,000.00 $80,000.00
14 LIGHTING POLE ARMS 0970 1 LS $80,000.00 $80,000.00
15 LUMINAIRES 0970 1 LS $50,000.00 $50,000.00
16 SWITCHING, CONDUIT AND WIRING 0970 1 LS $215,000.00 $215,000.00
Subtotal T01052 $499,500.00
Total $919,500.00
Bid Surety Yes BB