00 9111_ Addendum 01 Project 23106.pdf
PDF 29 KB Posted
- Attached to
- Greene Co. MS Bus Loop
- Solicitation number
- PE-66610-NONST-2024-000000002
- Issued by
- Greene County, Georgia
About this file
This document is an Addendum to a Request for Proposal (RFP) for the Greene County MS Bus Loop project. The Addendum is issued by Gardner Spencer Smith Tench & Jarbeau, P.C., the project architect, and is intended for all prospective bidders. The Addendum modifies the Proposal Documents dated February 6, 2024 and includes changes to the Bid Documents, specifically Section 00 9111 ADDENDUM. The Addendum provides clarification on the allowed work days and hours, the project's classified status, responsibility for testing and proof rolling costs, the ability to block off the work area, and the access point for bringing materials onto the site. It also clarifies that saw cutting of pavement and subsequent concrete curb and gutter work adjacent to the baseball field is not required.
The Addendum does not contain any information on pricing terms, set asides, incumbents, funding requirements and sources, or other financial details. It focuses solely on providing clarification and modifications to the RFP documents.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 00 9111
ADDENDUM
1.01 GENERAL
A. The following sets forth the format for issued Addenda.
ADDENDUM NO 01 dated February 27, 2024.
RE: Request for Proposal (RFP); Greene County MS Bus Loop
FROM: Gardner Spencer Smith Tench & Jarbeau, P.C.
Tower Place Building 3340 Peachtree Road NE Suite 1800
Atlanta, GA 30326
Architect's Stamp & Signature
TO: ALL PROSPECTIVE BIDDERS:
B. This Addendum forms a part of the Contract Documents and modifies the Proposal Documents February 6, 2024 as noted below. Acknowledge' receipt of the Addendum in the space provided on Bid Form. Failure to do so may result in the proposal being deemed non-responsive.
C. The Addendum consists of 2 pages, and the attached drawing(s) and specification(s) with the revised date of 02/27/24.
1. CHANGES TO PROPOSAL REQUIREMENTS TABLE OF CONTENTS: None.
2. CHANGES TO PRIOR ADDENDUM: None.
3. CHANGES TO BID DOCUMENTS:
Section 00 9111 ADDENDUM Delete Section 00 9111 ADDENDUM dated 02/06/24 in its entirety.
Add Section 00 9111 ADDENDUM dated 02/27/24 herein attached.
4. CHANGES TO CONDITIONS OF THE CONTRACT: None.
5. CHANGES TO SPECIFICATIONS: None.
6. CHANGES TO DRAWINGS: None.
7. OTHER CHANGES AS SET FORTH:
A. Mandatory Sign-in Sheet(s).
B. Question: What are the days of the week and hours of the week we are allowed to work?
Answer: Start May 25th 2024 and work Monday through Saturday from 8am-6pm.
C. Question: Will the contractor be taking the project as unclassified?
Answer: The project is classified to the extent that they are to provide Unit Cost for the items specified in Section 01 2200 – Unit Prices.
D. Question: Who's responsible for any testing or proof roll cost?
Answer: The School System will be responsible for the cost associated with testing, either before or after proof rolling is performed. The Contractor is responsible for providing the equipment and personnel to perform the proof rolling.
E. Question: Will we be able to block off the entire work area?
Answer: Yes, from May 25, 2024 through June 24, 2024.
F. Question: Where will we be able to bring material into the site?
Answer: From Hwy 44 (South Main Street) through the existing Middle School bus loop.
G. Question: Is the saw cutting of pavement and subsequent concrete curb and gutter work adjacent to the baseball field required?
Answer: No.
8. Clarification or any other notice of a change in the Proposal Documents will be issued only by the OWNER Contracts Department and only in the form of a written Addendum, transmitted by fax, e-mail or Owner’s Procurement Web Site. It is the responsibility of each Offeror to check and verify status. Any other purported Addenda are void and unenforceable.
END OF DOCUMENT