00 11 16 Invitation to Bid.pdf
PDF 130 KB Posted
- Attached to
- Cottages on Maynard
- Solicitation number
- PE-60752-NONST-2025-000000001
- Issued by
- Barrow County, Georgia
About this file
This document is an Invitation to Bid issued by the Winder Housing Authority for the construction of the Cottages at Maynard, an affordable housing development. The work consists of furnishing all materials and equipment and performing all labor necessary to construct the new cottages located at Maynard Street. The sealed bids will be received until 2:00 P.M. on Thursday, December 12, 2024, at which time they will be publicly opened and read aloud. A mandatory pre-bid meeting will be held on Thursday, November 21, 2024, at 2:00 P.M. Contractors are responsible for traffic control and erosion control per Barrow County requirements. Plans, specifications, and contract documents are available for review at the Winder Housing Authority office and may be obtained from the architect.
Payment of the contract amount will be made on a periodic basis based on work accomplished, products furnished, and products stored on the site. A 5% bid bond will be required, and the bidder shall hold a current and valid Contractor License issued by the Georgia State Construction Industry Licensing Board. The Winder Housing Authority reserves the right to reject any or all bids, waive any technicalities and informalities, and re-advertise, as well as award the contract in whole or in part.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Winder Housing Authority – Cottages at Maynard 00 11 16 - Page 1 Project Number FSF Architecture - 2310 Invitation to Bid
Winder Housing Authority 163 M.L.K. J.R. Drive
Winder, GA 30680
Sealed Proposals for construction of the Cottages at Maynard, an affordable housing-development will be received at the Winder Housing Authority, 163 M.L.K. J.R. Drive
Winder, GA 30680, Attention: Michelle Yawn, Executive Director, until 2:00 P.M. legal prevailing time on Thursday, December 12, 2024 at which time and place they will be publicly opened and read aloud. No bid may be withdrawn after the closing time for the receipt of bids for a period of sixty (60) calendar days.
All bids must be on the required bid form found in the specifications.
Mandatory Pre-Bid Meeting will be held at Winder Housing Authority, 163 M.L.K. J.R. Drive
Winder, GA 30680, at 2:00 P.M., legal prevailing time on Thursday, November 21, 2024.
The work to be done consists of furnishing all materials and equipment and performing all labor necessary to construct the new Cottages located at Maynard Street. The work shall be installed as detailed on the construction drawings and specified herein and all incidental work required for a complete and functional building. Contractors are responsible for traffic control and erosion control per Barrow County requirements.
Plans, Specifications and Contract Documents are available for review at the Winder Housing
Authority office at 163 M.L.K. J.R. Drive Winder, GA 30680 during regular business hours.
Complete bid documents are on file and may be obtained from Foreman Seeley Fountain
Architecture, 3091 Governors Lake Drive, Peachtree Corners, Georgia 30071, (phone 770-729-
8433). Contractors and Vendors who register with the Architect may receive digital files of the bid documents for no cost. Contact Takiyah Braxton (braxton@FSFarchitecture.com ).
Payment of the Contract Amount will be made on a periodic basis on applications for payment from the Contractor and approved by the Owner / Project Manager / Architect based on work accomplished, products furnished and products stored on the site. Progress payment requests shall be submitted by the Contractor no later than the twenty-fifth (25th) day of each month during the term of the Contract, and payment shall be made by the Winder Housing Authority within thirty (30) days after receipt of approved progress payment requests, less retainage and other deductions provided in the Contract Documents.
00 11 16 - Page 2 Winder Housing Authority – Cottages at Maynard Invitation to Bid Project Number FSF Architecture - 2310
Bonds: A five percent (5%) bid bond will be required.
License: The Bidder shall hold a current and valid Contractor License issued by the Georgia
State Construction Industry Licensing Board.
Owner’s Right: The Winder Housing Authority reserves the right to reject any or all bids, to waive any technicalities and informalities and re-advertise. The Winder Housing Authority further reserves the right to award this contract in whole or in part.
Winder Housing Authority
By: Michelle Yawn
Executive Director