USACE Jacksonville Environmental Remediation 2016-2021
Ended Master IDIQ Awarded
- Federal agency
-
ENDIST Jacksonville
- Awardees
- 9
- Task orders
- 47
- Obligated
- $112,341,344
Vehicle facts
- Opportunity
-
- W912EP15R0018, W912EP15R0011 Solicitation numbers
- Agency
-
- ENDIST Jacksonville US Army Corps of Engineers, Department of Defense
- Combined task order value
-
- $112,447,130 Current, with exercised options
- $113,647,885 Potential, with all options
- Last date to order 100% complete
- Shared ceiling 47% used
- $238,000,000.00
IDV award and task order details come from SAM.gov/FPDS.
About this vehicle
The U.S. Army Corps of Engineers Jacksonville District awarded this Master IDIQ for environmental remediation services on May 15, 2016, with ordering closed as of October 20, 2021. The vehicle is no longer active; new orders cannot be placed. Nine prime contractors shared 47 task orders worth a combined $114.5 million in potential value, of which $105.5 million (92%) has been obligated. Competition is heavily concentrated: Bhate Zapata, LLC dominates by potential value at $73.8 million across 13 orders, nearly 65% of the vehicle's total contracting. Bay West LLC holds the second-largest stake at $24 million across 2 orders. The remaining seven contractors divide the balance, with Aerostar SES LLC placing the most awards (15 orders) but capturing only $2.3 million in potential value. Ordering activity peaked in 2020 with 19 awards, then contracted sharply; the vehicle issued 8 final awards in 2021 before closing the window.
Task orders span environmental restoration at military installations (PFAS remediation, optimized remediation contracts at Air Force bases including Shaw, Robins, Moody, and Eglin), groundwater monitoring, remedial investigation and feasibility studies, abatement and demolition, wetland delineation, and well abandonment. Individual orders ranged widely in scope and dollar value—from minimum guarantees of $2,500 to multi-million-dollar regional contracts. Notable mega-orders include a small-business set-aside for Robins Air Force Base Optimized Remediation at $30.7 million ceiling (obligated $27.6 million), and Shaw Air Force Base Optimized Remediation at $24 million (obligated). The vehicle structure included two subcategories: HUBZone Track and Small Business Track, though actual awards show a mixed set-aside distribution—51% unrestricted, 38% small-business set-aside, and 11% HUBZone.
Customer funding split primarily between the Army Corps of Engineers components and the Air Force. The Corps' Jacksonville and Savannah engineering districts and the broader Department of the Army issued the majority of awards; Air Force Materiel Command's Installation and Mission Support Center Civil Engineer Center placed four orders valued at $38.6 million combined. Most work performed in Florida and the southeastern United States, consistent with the South Atlantic Division scope.
Description
Regional Environmental Acquisition Tool, Environmental Remediation Services, U. S. Army Corps of Engineers, South Atlantic Division
IDV awards
Latest task orders
Show 15 more
Latest 25 of 47 listed here. See the rest on GovTribe.
Pools and SINs
| Pool or SIN | IDV awards | Ceiling | Obligated |
|---|---|---|---|
| Small Business Track | 5 | $188,000,000 | $110,813,508 |
| HUBZone Track | 4 | $50,000,000 | $1,527,836 |
Top awardees by obligations
| Rank | Awardee | Obligated | Share |
|---|---|---|---|
| 1 | Bhate Zapata, LLC | $72,089,484 | 64% |
| 2 | Bay West LLC | $23,571,904 | 21% |
| 3 | Tepa EC, LLC | $8,328,798 | 7% |
| 4 | 3E-Qri Sbjv, LLC | $4,557,124 | 4% |
| 5 | Aerostar SES LLC | $2,266,199 | 2% |
| 6 | FPM Remediations, Inc. | $1,001,654 | 1% |
| 7 | G & RK Consulting Associates LLC | $450,311 | <1% |
| 8 | Energy And Environment, LLC | $75,870 | <1% |
Top funding agencies by obligations
| Rank | Funding agency | Obligated | Share |
|---|---|---|---|
| 1 | Department of the Army | $93,240,791 | 83% |
| 2 | Air Force | $19,024,683 | 17% |
| 3 | Environmental Protection Agency | $75,870 | <1% |
Obligations by fiscal year
| Fiscal year | Obligated |
|---|---|
| FY2026 | $6,903,303 |
| FY2025 | $6,462,145 |
| FY2024 | $8,490,168 |
| FY2023 | $21,153,327 |
| FY2022 | $8,505,529 |
| FY2021 | $7,189,059 |
| FY2020 | $41,825,620 |
| FY2019 | $1,249,005 |
| FY2018 | $10,543,188 |
| FY2017 | $7,500 |
| FY2016 | $12,500 |
Show all 11
Quick answers
What is the USACE Jacksonville Environmental Remediation 2016-2021 contract vehicle?
USACE Jacksonville Environmental Remediation 2016-2021 is an indefinite delivery, indefinite quantity (IDIQ) contract vehicle run by ENDIST Jacksonville (US Army Corps of Engineers), awarded on May 15, 2016.
Which companies hold USACE Jacksonville Environmental Remediation 2016-2021?
9 companies hold USACE Jacksonville Environmental Remediation 2016-2021's IDV awards, one each. The latest went to G & RK Consulting Associates LLC on October 21, 2016. The awardees whose task orders obligated the most are Bhate Zapata, LLC, Bay West LLC and Tepa EC, LLC.
How much has been spent through USACE Jacksonville Environmental Remediation 2016-2021?
47 task orders have been placed under USACE Jacksonville Environmental Remediation 2016-2021, obligating $112,341,344. Their combined current value, with exercised options, is $112,447,130.
What is the shared ceiling of USACE Jacksonville Environmental Remediation 2016-2021?
USACE Jacksonville Environmental Remediation 2016-2021's shared ceiling is $238,000,000; its task orders have used 47% of it.
Which agencies use USACE Jacksonville Environmental Remediation 2016-2021 the most?
The departments whose task orders under USACE Jacksonville Environmental Remediation 2016-2021 obligated the most are Department of the Army ($93,240,791), Air Force ($19,024,683) and Environmental Protection Agency ($75,870).
How much was obligated through USACE Jacksonville Environmental Remediation 2016-2021 in fiscal year 2025?
Task orders under USACE Jacksonville Environmental Remediation 2016-2021 obligated $6,462,145 in fiscal year 2025.
What pools does USACE Jacksonville Environmental Remediation 2016-2021 have?
USACE Jacksonville Environmental Remediation 2016-2021 has 2 pools, lots and SINs, including Small Business Track and HUBZone Track.
On GovTribe
See this vehicle's full record
- Every IDV award and task order
- Funding by agency, awardee, NAICS and set-aside
- Teaming partners on this vehicle
- Ask GovTribe AI about this vehicle