Missouri River BSNP MATOC
Active Master IDIQ Awarded
- Federal agency
-
ENDIST Omaha
- Awardees
- 4
- Task orders
- 7
- Obligated
- $42,527,953
Vehicle facts
- Opportunity
-
- Bank Stabilization and Navigation Project (BSNP) to repair and maintain navigation channels on Missouri River Pre-Solicitation · W9128F23R0023 · Posted Mar 20, 2023
- Agency
-
- ENDIST Omaha US Army Corps of Engineers, Department of Defense
- Combined task order value
- $42,527,953 Current and potential, with all options
- Last date to order 65% complete
- Shared ceiling 87% used
- $49,000,000.00
IDV award and task order details come from SAM.gov/FPDS.
About this vehicle
The Department of the Army Corps of Engineers Engineering District Omaha established a Total Small Business Master IDIQ on July 21, 2023, to repair and maintain navigation channels on the Missouri River under the Bank Stabilization and Navigation Project (BSNP), with ordering authority extending through July 20, 2028. The vehicle carries a shared ceiling of $49 million and remains active with approximately two years and three days of ordering authority remaining.
All seven task orders awarded to date have obligated the full $42.5 million combined potential value, indicating complete execution against current commitments. Western Contracting Corp dominates the portfolio, holding four orders valued at $38.2 million combined (90% of obligated value), with W A Ellis Construction CO. holding one order for $4.3 million. Two additional small-business firms hold minimal awards: Dubuque Barge And Fleeting Service Co and Bloomsdale Excavating Company, each with orders near $3 thousand. Ordering activity was concentrated in the vehicle's launch quarter (July through September 2023); no awards have been made since September 21, 2023.
The set-aside mix diverges from the vehicle's original small-business intent: six of seven orders (86%) carry no set-aside designation, with only one order designated Total Small Business. Orders are typically firm-fixed-price delivery orders with values ranging from $2,500 minimum guarantees to approximately $15 million per task order. Task-order durations span from immediate performance through mid-2025, with three minimum-guarantee orders extending through the vehicle's termination date in 2028. All task orders fund Department of the Army Corps of Engineers Engineering District Omaha or parent Corps of Engineers accounts.
Work performed includes excavation, stone placement, and construction of revetments, dikes, chevrons, and related features supporting navigation channel repair on the Missouri River. Access occurs via floating plant and land routes. NAICS 237310 and PSC codes C and D apply. Despite the vehicle's $49 million ceiling and small-business set-aside structure, current utilization suggests limited ongoing competition: no new orders have been issued since the initial award period, and Western Contracting Corp's market concentration indicates a narrow competitive base for future work under the remaining $6.5 million available ceiling.
IDV awards
Latest task orders
Top awardees by obligations
| Rank | Awardee | Obligated | Share |
|---|---|---|---|
| 1 | Western Contracting Corp | $38,200,590 | 90% |
| 2 | W A Ellis Construction CO. | $4,322,363 | 10% |
| 3 | Dubuque Barge And Fleeting Service Co | $2,500 | <1% |
| 4 | Bloomsdale Excavating Company, Incorporated | $2,500 | <1% |
"Minimum guarantee only" marks awardees whose obligations here are just the minimum order their contract guarantees.
Top funding agencies by obligations
| Rank | Funding agency | Obligated | Share |
|---|---|---|---|
| 1 | Department of the Army | $42,527,953 | 100% |
Obligations by fiscal year
| Fiscal year | Obligated |
|---|---|
| FY2026 | $30,755 |
| FY2025 | $502,534 |
| FY2024 | $19,082,505 |
| FY2023 | $22,912,159 |
Quick answers
What is the Missouri River BSNP MATOC contract vehicle?
Missouri River BSNP MATOC is an indefinite delivery, indefinite quantity (IDIQ) contract vehicle run by ENDIST Omaha (US Army Corps of Engineers), awarded on July 21, 2023.
Which companies hold Missouri River BSNP MATOC?
4 companies hold Missouri River BSNP MATOC's IDV awards, one each. The latest went to Bloomsdale Excavating Company, Incorporated on July 21, 2023. The awardees whose task orders obligated the most are Western Contracting Corp, W A Ellis Construction CO. and Dubuque Barge And Fleeting Service Co.
How much has been spent through Missouri River BSNP MATOC?
7 task orders have been placed under Missouri River BSNP MATOC, obligating $42,527,953.
What is the shared ceiling of Missouri River BSNP MATOC?
Missouri River BSNP MATOC's shared ceiling is $49,000,000; its task orders have used 87% of it.
Which agencies use Missouri River BSNP MATOC the most?
The departments whose task orders under Missouri River BSNP MATOC obligated the most are Department of the Army ($42,527,953).
How much was obligated through Missouri River BSNP MATOC in fiscal year 2025?
Task orders under Missouri River BSNP MATOC obligated $502,534 in fiscal year 2025.
On GovTribe
See this vehicle's full record
- Every IDV award and task order
- Funding by agency, awardee, NAICS and set-aside
- Teaming partners on this vehicle
- Ask GovTribe AI about this vehicle