Kennedy Space Center Small Task Order Construction Contract
Ended Master IDIQ Awarded
- Federal agency
-
Kennedy Space Center
- Awardees
- 5
- Task orders
- 152
- Obligated
- $92,217,821
Vehicle facts
- Opportunity
-
- Small Task Order Construction Contract (STOCC) Pre-Solicitation · 80KSC020R0028 · Posted Jun 12, 2020
- Agency
-
- Kennedy Space Center National Aeronautics and Space Administration
- Combined task order value
- $94,821,618 Current and potential, with all options
- Last date to order 100% complete
- Shared ceiling 61% used
- $150,000,000.00
IDV award and task order details come from SAM.gov/FPDS.
About this vehicle
NASA Kennedy Space Center awarded this Master IDIQ for construction services on June 11, 2021, with a shared ceiling of $150 million and a five-year ordering period that closed on June 10, 2026. The vehicle is set aside for competitive 8(a) construction firms located in or with a bona fide place of business in Florida; competition is restricted to 8(a) firms meeting the NAICS 236220 size standard of $39.5 million.
Ordering has closed. The vehicle executed 150 task orders over its five-year life, with activity peaking at 41 orders in 2022, declining to 18 in 2026 before the ordering window expired. The combined potential value of awarded task orders reached $90.9 million, with $88.7 million obligated—98 percent of the combined ceiling. Only one customer agency placed orders under this vehicle: NASA Kennedy Space Center, which issued all 150 delivery orders.
Wright Bros LLC leads by potential value at $39.4 million across 42 orders, followed by Aleut Construction LLC at $25.9 million across 47 orders and SES Civil And Environmental LLC at $22.1 million across 36 orders. These three primes account for roughly 87 percent of combined potential value; Vanguard Pacific LLC and Blue Tarpon Construction LLC hold the remainder.
The actual set-aside mix diverged sharply from the vehicle's competitive 8(a) designation. Approximately 79 percent of orders—118 of 150—carried no set-aside designation, awarded competitively or potentially to non-8(a) firms. The remaining 21 percent, 32 orders, were designated competitive 8(a). Task orders ranged from less than $25,000 to $3.9 million, with recent awards including a stormwater system replacement at the Vehicle Assembly Building for $1.6 million, a Launch Abort System Hangar Phase 2 for $3.7 million, and a Safety and Reliability Phase 6 project for $3.5 million. All work was performed at Kennedy Space Center in Florida, covering carpentry, roofing, electrical, HVAC, plumbing, demolition, concrete work, masonry, road repair, excavation, fire protection, and design-build components to address urgent projects.
Description
Provides construction services over a 5-year period consisting of a variety of trades, such as carpentry/wall construction, roofing, interior and exterior electrical, mechanical/HVAC, plumbing, sheet metal, painting, demolition, concrete (flatwork and structures), masonry, welding, road repair, excavation, fire protection, earthwork, site improvements, etc. The need also includes a design build component to address urgent projects.
IDV awards
Latest task orders
Show 15 more
Latest 25 of 152 listed here. See the rest on GovTribe.
Top awardees by obligations
| Rank | Awardee | Obligated | Share |
|---|---|---|---|
| 1 | Wright Bros LLC | $38,784,048 | 42% |
| 2 | Aleut Construction LLC | $27,812,919 | 30% |
| 3 | SES Civil And Environmental LLC | $22,136,957 | 24% |
| 4 | Vanguard Pacific LLC | $3,160,287 | 3% |
| 5 | Blue Tarpon Construction LLC | $241,946 | <1% |
| 6 | Call Associates, Inc. | $81,665 | <1% |
Top funding agencies by obligations
| Rank | Funding agency | Obligated | Share |
|---|---|---|---|
| 1 | National Aeronautics and Space Administration | $92,217,821 | 100% |
Obligations by fiscal year
| Fiscal year | Obligated |
|---|---|
| FY2026 | $21,432,046 |
| FY2025 | $17,168,007 |
| FY2024 | $15,655,617 |
| FY2023 | $15,609,916 |
| FY2022 | $19,601,394 |
| FY2021 | $2,800,841 |
Quick answers
What is the Kennedy Space Center Small Task Order Construction Contract contract vehicle?
Kennedy Space Center Small Task Order Construction Contract is an indefinite delivery, indefinite quantity (IDIQ) contract vehicle run by Kennedy Space Center (National Aeronautics and Space Administration), awarded on June 11, 2021.
Which companies hold Kennedy Space Center Small Task Order Construction Contract?
5 companies hold Kennedy Space Center Small Task Order Construction Contract's IDV awards, one each. The latest went to Aleut Construction LLC on June 11, 2021. The awardees whose task orders obligated the most are Wright Bros LLC, Aleut Construction LLC and SES Civil And Environmental LLC.
How much has been spent through Kennedy Space Center Small Task Order Construction Contract?
152 task orders have been placed under Kennedy Space Center Small Task Order Construction Contract, obligating $92,217,821. Their combined current value, with exercised options, is $94,821,618.
What is the shared ceiling of Kennedy Space Center Small Task Order Construction Contract?
Kennedy Space Center Small Task Order Construction Contract's shared ceiling is $150,000,000; its task orders have used 61% of it.
Which agencies use Kennedy Space Center Small Task Order Construction Contract the most?
The departments whose task orders under Kennedy Space Center Small Task Order Construction Contract obligated the most are National Aeronautics and Space Administration ($92,217,821).
How much was obligated through Kennedy Space Center Small Task Order Construction Contract in fiscal year 2025?
Task orders under Kennedy Space Center Small Task Order Construction Contract obligated $17,168,007 in fiscal year 2025.
On GovTribe
See this vehicle's full record
- Every IDV award and task order
- Funding by agency, awardee, NAICS and set-aside
- Teaming partners on this vehicle
- Ask GovTribe AI about this vehicle