Kauai Program of Bridge Construction MATOC 2017-2022

Ended Master IDIQ Awarded

Federal agency
Awardees
3
Task orders
4
Obligated
$71,821,115

Vehicle facts

Opportunity
  • DTFH6817D, DTFH6816R00003 Solicitation numbers
Agency
Combined task order value
$71,821,115 Current and potential, with all options
Last date to order 100% complete
Shared ceiling 96% used
$75,000,000.00

IDV award and task order details come from SAM.gov/FPDS.

About this vehicle

The Federal Highway Administration's Central Federal Lands Highway Division awarded this Master IDIQ in partnership with the Hawaii Department of Transportation to execute a program of bridge construction and related infrastructure work on Kauai; ordering closed on March 1, 2022, and the vehicle is no longer active.

The MATOC issued four delivery orders between February 2017 and March 2019, all firm-fixed-price construction contracts under an unrestricted, competitive vehicle structure. Work included permanent bridge replacement (Hanapepe River Bridge, Kapaa Stream Bridge), temporary detour bridge construction, and bridge rehabilitation across multiple state transportation projects. All four orders have reached completion or final modification, with the most recent award—a $25.2 million Kapaa Stream Bridge and Mailihuna intersection project to W.W. Clyde & Co.—closed in March 2019. The vehicle obligated its full combined potential value of $71.8 million across the four orders, leaving no remaining capacity.

Competition concentrated heavily on two local or regional general contractors: W.W. Clyde & Co. received two orders worth $41.5 million combined (57.8% of total value), and Hawaiian Dredging Construction Company, Inc. received two orders worth $30.3 million combined (42.2%). All ordering activity served a single customer—the Federal Highway Administration itself—making this a purpose-built vehicle for a defined capital program rather than a open-ended procurement platform.

Task-order values ranged from approximately $3.9 million to $37.6 million, with typical durations of 12–18 months from award to substantial completion. The vehicle's firm-fixed-price structure and geographic scope to Kauai made it unsuitable for firms without Hawaii-based or regional heavy-civil-construction capacity. Because ordering authority expired more than four years ago and all potential value has been obligated, this vehicle presents no pursuit opportunity; it serves as a reference case for how FHWA structures multimodal bridge-replacement programs under MATOC authority.

Description

The Central Federal Lands Highway Division (CFL) of the Federal Highway Administration in partnership with the Hawaii Department of Transportation has awarded a Multiple Award Task Order Contract (MATOC) for a Kauai Program of Bridge construction.

IDV awards

Latest task orders

Top awardees by obligations

Rank Awardee Obligated Share
1 W.w. Clyde & CO. $41,490,340 58%
2 Hawaiian Dredging Construction Company, Inc. $30,330,776 42%

Top funding agencies by obligations

Rank Funding agency Obligated Share
1 Department of Transportation $71,821,115 100%

Obligations by fiscal year

Fiscal year Obligated
FY2024 -$54,445
FY2022 $433,301
FY2021 $1,876,735
FY2020 $840,085
FY2019 $24,748,239
FY2018 $35,214,371
FY2017 $8,140,096

Quick answers

What is the Kauai Program of Bridge Construction MATOC 2017-2022 contract vehicle?

Kauai Program of Bridge Construction MATOC 2017-2022 is an indefinite delivery, indefinite quantity (IDIQ) contract vehicle run by Federal Highway Administration (Department of Transportation), awarded on February 7, 2017.

Which companies hold Kauai Program of Bridge Construction MATOC 2017-2022?

3 companies hold Kauai Program of Bridge Construction MATOC 2017-2022's IDV awards, one each. The latest went to Goodfellow Bros, LLC on March 2, 2017. The awardees whose task orders obligated the most are W.w. Clyde & CO. and Hawaiian Dredging Construction Company, Inc.

How much has been spent through Kauai Program of Bridge Construction MATOC 2017-2022?

4 task orders have been placed under Kauai Program of Bridge Construction MATOC 2017-2022, obligating $71,821,115.

What is the shared ceiling of Kauai Program of Bridge Construction MATOC 2017-2022?

Kauai Program of Bridge Construction MATOC 2017-2022's shared ceiling is $75,000,000; its task orders have used 96% of it.

Which agencies use Kauai Program of Bridge Construction MATOC 2017-2022 the most?

The departments whose task orders under Kauai Program of Bridge Construction MATOC 2017-2022 obligated the most are Department of Transportation ($71,821,115).

On GovTribe

See this vehicle's full record

  • Every IDV award and task order
  • Funding by agency, awardee, NAICS and set-aside
  • Teaming partners on this vehicle
  • Ask GovTribe AI about this vehicle