Design Bid Build Marine Based Construction for LRD River Districts
Active Master IDIQ Awarded
- Federal agency
-
US Army Corps of Engineers
- Awardees
- 4
- Task orders
- 14
- Obligated
- $46,567,008
Vehicle facts
- Opportunity
-
- IDC Design Bid Build Marine-Based LRD River Districts Pre-Solicitation · W9123722R0004 · Posted Feb 17, 2022
- Agency
-
- US Army Corps of Engineers Department of the Army, Department of Defense
- Combined task order value
-
- $46,665,308 Current, with exercised options
- $46,903,018 Potential, with all options
- Last date to order 81% complete
- Shared ceiling 62% used
- $75,000,000.00
IDV award and task order details come from SAM.gov/FPDS.
About this vehicle
The U.S. Army Corps of Engineers awarded a Master IDIQ on September 27, 2022 for design bid build marine-based construction services to government installations within the Huntington and Pittsburgh River Districts of the Great Lakes and Ohio River Division, with ordering authority extending through September 26, 2027. The vehicle carries a shared ceiling of $75 million and was established as an unrestricted five-award IDIQ with a one-year base period and four one-year option periods.
Ordering remains active with approximately 14 months of authority remaining. The vehicle has obligated $32.6 million of its $32.9 million combined task-order potential value across 13 task orders awarded since September 2022, with recent ordering momentum declining to a single order in 2025 after peaks of five orders in 2024 and four in 2022. C.J. Mahan Construction Company, LLC dominates the vehicle, holding seven orders valued at $21 million combined potential value, roughly 64 percent of all awards. Brayman Construction Corp holds the remaining material share with four orders totaling $11.9 million; two smaller firms each hold a single $20,000 guaranteed-minimum order.
Scope centers on locks and dams maintenance, repair, and rehabilitation across the navigable inland waterway system. Recent large orders include emergency miter gate sill repairs at Captain Anthony Meldahl Lock and Dam ($7.95 million), lock chamber dewatering work at an unspecified location ($5.98 million obligated against a $6.12 million ceiling), and miter gate removal and repair at Green River ($5.22 million ceiling). Smaller orders address mooring cell removal, anchor point buoy replacement, and towboat rental services. All work requires firm fixed-price contracting. Contractors must demonstrate capability to mobilize crews to multiple job sites concurrently, maintain emergency 24-hour response readiness, and provide multimillion-dollar bonding capacity.
All 13 task orders are unrestricted with no set-aside designations. Customer concentration is split between the Army Corps of Engineers (nine orders, $12.6 million combined potential) and the Louisville Engineering District (four orders, $20.4 million combined potential). Performance spans the Huntington, Louisville, Nashville, and Pittsburgh districts.
Description
The primary objective of this IDIQ is to provide site survey, work plan(s) and/or specifications, construction, maintenance, repair, and/or rehabilitation (MRR) services to Government installations and facilities located within the geographical boundaries of the Rivers Districts (Huntington and Pittsburgh) locations of the Great Lakes and Ohio River Division, U.S. Army Corps of Engineers.
IDV awards
Latest task orders
Show all 14
Top awardees by obligations
| Rank | Awardee | Obligated | Share |
|---|---|---|---|
| 1 | Brayman Construction Corp | $25,795,226 | 55% |
| 2 | C.j. Mahan Construction Company, LLC | $20,731,782 | 45% |
| 3 | Amherst Madison, Inc. | $20,000 | <1% |
| 4 | Aleut Flood Management, LLC | $20,000 | <1% |
Top funding agencies by obligations
| Rank | Funding agency | Obligated | Share |
|---|---|---|---|
| 1 | Department of the Army | $46,567,008 | 100% |
Obligations by fiscal year
| Fiscal year | Obligated |
|---|---|
| FY2026 | $14,671,601 |
| FY2025 | $10,110,434 |
| FY2024 | $13,540,224 |
| FY2023 | $8,164,750 |
| FY2022 | $80,000 |
Quick answers
What is the Design Bid Build Marine Based Construction for LRD River Districts contract vehicle?
Design Bid Build Marine Based Construction for LRD River Districts is an indefinite delivery, indefinite quantity (IDIQ) contract vehicle run by US Army Corps of Engineers (Department of the Army), awarded on September 27, 2022.
Which companies hold Design Bid Build Marine Based Construction for LRD River Districts?
4 companies hold Design Bid Build Marine Based Construction for LRD River Districts's IDV awards, one each. The latest went to Brayman Construction Corp on September 27, 2022. The awardees whose task orders obligated the most are Brayman Construction Corp, C.j. Mahan Construction Company, LLC and Amherst Madison, Inc.
How much has been spent through Design Bid Build Marine Based Construction for LRD River Districts?
14 task orders have been placed under Design Bid Build Marine Based Construction for LRD River Districts, obligating $46,567,008. Their combined current value, with exercised options, is $46,665,308.
What is the shared ceiling of Design Bid Build Marine Based Construction for LRD River Districts?
Design Bid Build Marine Based Construction for LRD River Districts's shared ceiling is $75,000,000; its task orders have used 62% of it.
Which agencies use Design Bid Build Marine Based Construction for LRD River Districts the most?
The departments whose task orders under Design Bid Build Marine Based Construction for LRD River Districts obligated the most are Department of the Army ($46,567,008).
How much was obligated through Design Bid Build Marine Based Construction for LRD River Districts in fiscal year 2025?
Task orders under Design Bid Build Marine Based Construction for LRD River Districts obligated $10,110,434 in fiscal year 2025.
On GovTribe
See this vehicle's full record
- Every IDV award and task order
- Funding by agency, awardee, NAICS and set-aside
- Teaming partners on this vehicle
- Ask GovTribe AI about this vehicle