Indefinite Delivery Contract W912HN10D0070
Award Date 9/30/10
Last Date to Order 9/29/15
Federal Agency
Ultimate Awardee
Not listed PSC Category
Not listed Federal Contract Vehicle
- Not listed
Pricing Type
Order Dependent (IDV only)
Legislative Mandate
Davis Bacon Act
National Interest Action
None
Award Type
Single
Primary Consortia Member
Not listed Similar IDVs
- Archer Western Federal JV was awarded a multiple-award Indefinite Delivery Contract valued at $249 million by the U.S. Army Corps of Engineers Engineering District Savannah on January 7, 2019, with an ultimate completion date of October 6, 2024. This contract, designated as the Georgia/South Carolina Military Construction Task Order Contract (GA/SC MATOC), was awarded without set-asides through full and open competition and establishes a vehicle for delivering general and design-build...
- The Department of the Army European Command (DOD-Army) awarded an Indefinite Delivery/Indefinite Quantity (IDIQ) Multiple Award Task Order Contract (MATOC) to Lcons LLC, a for-profit organization based in Georgia. The MATOC has a $25 million ceiling value and a period of performance from January 2023 through July 2028. The MATOC will be used to procure design-bid-build and design-build construction services in Georgia and Armenia, including general building renovation, vertical construction,...
- The U.S. Army Corps of Engineers, Omaha District awarded a $240M Indefinite Delivery/Indefinite Quantity (IDIQ) Multiple Award Task Order Contract (MATOC) for environmental remediation services and munitions response work. The MATOC is an unrestricted procurement with no set-asides, and up to 10 prime contractors were awarded 3-year base contracts with a 2-year option. The contract supports the Corps' Northwest Division and existing customers within its geographic boundaries. Task orders will be...
- This Multiple Award Indefinite Delivery Construction Task Order Contract (MATOC) was awarded on July 17, 2007, to N-Powell Company, Inc., a minority-owned, small disadvantaged business, under a competitive 8(a) set-aside. The contract has a ceiling value of $170,087,500 and an ultimate completion date of July 16, 2012. The primary funding agency is the Defense Department's Northeast Region, with additional task orders funded by specialized commands including the Research Development and...
- This indefinite delivery contract, awarded by the U.S. Army Space and Missile Defense Command on June 22, 2015, established a single-award vehicle with a ceiling value of $89.4 million for Georgia TECH Applied Research Corp (GTARC) to provide core competencies in defense research, engineering, science, and technology development. GTARC, a non-profit research organization affiliated with the Georgia Institute of Technology, serves as the prime contractor with all performance locations in Atlanta,...
- The Rapid Disaster Infrastructure HUBZone Multiple Award Task Order Contract (MATOC) is a $99 million indefinite delivery vehicle awarded by the U.S. Army Corps of Engineers Omaha District on June 16, 2021, with performance extending through June 15, 2029. The contract is exclusively set aside for Historically Underutilized Business Zone (HUBZone) certified small businesses and represents a multiple award vehicle designed to provide flexible contracting capabilities for disaster response...
- Top Gun Contracting Inc., a woman-owned small business based in Warner Robins, Georgia, holds a $40 million multiple-award Indefinite Delivery/Indefinite Quantity (IDIQ) contract awarded by the Air Force Materiel Command on August 23, 2021, with performance extending through July 31, 2026. The contract was established under a Total Small Business set-aside and covers comprehensive paving repair, maintenance, and minor construction work for miscellaneous surface areas at Robins Air Force Base and...
- K&C Contractors, Inc., a Native American-owned, minority-owned small disadvantaged business based in Maxton, North Carolina, holds a multiple award indefinite delivery contract (MATOC) valued at $7.2 million with the U.S. Army Installation Management Command Southeast Region. The contract, awarded on December 1, 2022, and extending through February 1, 2028, establishes a vehicle for the procurement of minor construction and specialty trade services at Army installations throughout the...
- The U.S. Army Corps of Engineers Engineering District Savannah awarded an Indefinite Delivery Contract (IDC) to M.A. Mortenson Company, doing business as Mortenson Construction, for unspecified services under the Georgia/South Carolina Unrestricted Design-Build Construction Multiple Award Task Order Contract (GA/SC Unrestricted Design-Build Construction MATOC). The $249 million IDC has a period of performance through October 2024 and was established to support the Corps' civil works program in...
- David Taylor Construction, Inc. was awarded a single-award, indefinite delivery contract by the United States Marine Corps on September 29, 2020. The contract has a potential value of $4,000,000 and a period of performance through September 27, 2025. Under the contract vehicle, three task orders have been awarded to David Taylor Construction. The first, awarded on August 23, 2021 for $79,310.52, calls for the contractor to provide a turnstile cover at the Marine Corps' Production Plant Albany...
- W912HN10D0070Indefinite Delivery Contract
- 10Federal Contract Awards
GEORGIA MATOC, RP09-3 BASE YEAR
Posted 9/30/10
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| P00005 | Other Administrative Action | $0 | 7/28/17 | |
| P00004 | Other Administrative Action | $0 | 9/5/14 | |
| P00003 | Exercise an Option | $0 | 9/3/14 | |
| P00002 | Exercise an Option | $0 | 9/24/13 | |
| P00001 | Other Administrative Action | $0 | 4/12/12 |
Name | Description | Awardee | Potential Value | AwardDate | CompletionDate | Updated At |
|---|---|---|---|---|---|---|
Delivery Order W912HN10D0070-DW02 | Tyler Construction Group, Inc. | $1.6m | 9/28/13 | 9/23/14 | 2/28/14 | |
Delivery Order W912HN10D0070-DQ02 | Tyler Construction Group, Inc. | $510.6k | 9/24/12 | 6/22/13 | 9/25/12 | |
Delivery Order W912HN10D0070-0003 | Tyler Construction Group, Inc. | $4.7m | 9/29/13 | 4/16/16 | 7/19/16 | |
Delivery Order W912HN10D0070-0002 | Tyler Construction Group, Inc. | $1.7m | 6/5/13 | 4/3/14 | 11/6/14 | |
Delivery Order W912HN10D0070-DW03 | Tyler Construction Group, Inc. | $2.1m | 9/28/13 | 12/31/15 | 11/4/16 |
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
GEORGIA GENERAL CONSTRUCTION MATOC | W912HN-09-R-0018 | Department of the Army Corps of Engineers Engineering District Savannah | Award Notice 1/1 | 6/11/09, 3:07 PM |