The GSA northwest/arctic region (R10) is issuing this indefinite delivery, indefinite quantity (IDIQ) contract to support recurring construction services needed at federally owned and controlled…

Ended Awarded Last action

Contract number
GS10P16LTD7009
Awardee
Awarding agency
Task orders
8 $7,866,607 obligated

Award facts

Combined order value
  • $7,866,607 Current, with exercised options
  • $7,866,877 Potential, with all options
Last date to order 100% complete
IDV ceiling 20% used
$40,000,000.00
Maximum order
$5,000,000.00
Award type
Multiple award
Who can order
Only the awarding agency
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 13 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Legislative mandates

Award details come from SAM.gov/FPDS.

Description

The GSA northwest/arctic region (R10) is issuing this indefinite delivery, indefinite quantity (IDIQ) contract to support recurring construction services needed at federally owned and controlled facilities located in easter washington, eastern oregon and idaho. The name of this program is the southeast service center (sesc) - spokane multiple award task order contract (MATOC). Copies of the agreement, scope of services, and ordering procedures are available by email to

Task orders

Transactions

Action Obligated Date
Supplemental Agreement for work within scope PS06 $0
Supplemental Agreement for work within scope PS05 · Modification to update terms and conditions and to extend the ordering period of the IDIQ. $0
Exercise an Option PA04 · Exercise option to increase the CMV from $30M by $10M to $40M in accordance with section I.C. Of the agreement $0
Supplemental Agreement for work within scope PS03 · Southeast service center construction MATOC IDIQ, spokane, WA PS03 implementation of ndaa section 889 part b $0
Supplemental Agreement for work within scope PS02 · 889 RPA (BOT) modification $0
Other Administrative Action PA01 · Modification DE-obligates minimum guarantee in the amount of $2,500.00 IAW section 1.c of the agreement. Minimum guarantee has been fulfilled by issuance of… -$2,500
Original award $2,500

Subawards

Subcontractor Amount Awarded
Air TECH Abatement Technologies, Inc. INSTALL FALL PROTECTION SYSTEM ON THE THOMAS FOLEY COURTHOUSE AND UNITED STATES POST OFFICE LOCATED IN SPOKANE, WASHINGTON. Lead Abatement $77,006
Marlin Windows, Inc. DESIGN BUILD SERVICES TO SUPPORT THE VBA'S INITIAL OCCUPANCY (I.E, NEW OFFICE SPACE BUILD-OUT) ON THE 5TH FLOOR OF THE THOMAS S. FOLEY COURTHOUSE IN SPOKANE,… $39,852
Advanced Fireproofing & Insulation, CO. INSTALL FALL PROTECTION SYSTEM ON THE THOMAS FOLEY COURTHOUSE AND UNITED STATES POST OFFICE LOCATED IN SPOKANE, WASHINGTON. Fire Proofing $39,900
MK Fall Protection Inc. INSTALL FALL PROTECTION SYSTEM ON THE THOMAS FOLEY COURTHOUSE AND UNITED STATES POST OFFICE LOCATED IN SPOKANE, WASHINGTON. Fall Protection System $317,239
Sturm Heating & Air Conditioning, LLC Design build services to support the VBA's initial occupancy (i.e, new office space build-out) on the 5TH floor of the thomas s. Foley courthouse in spokane,… $199,938
Krueger Sheet Metal CO. INSTALL FALL PROTECTION SYSTEM ON THE THOMAS FOLEY COURTHOUSE AND UNITED STATES POST OFFICE LOCATED IN SPOKANE, WASHINGTON. Structural Steel $415,909
Specialty Environmental Group, LLC DESIGN BUILD SERVICES TO SUPPORT THE VBA'S INITIAL OCCUPANCY (I.E, NEW OFFICE SPACE BUILD-OUT) ON THE 5TH FLOOR OF THE THOMAS S. FOLEY COURTHOUSE IN SPOKANE,… $98,382
Peterson Electric, Inc. DESIGN BUILD SERVICES TO SUPPORT THE VBA'S INITIAL OCCUPANCY (I.E, NEW OFFICE SPACE BUILD-OUT) ON THE 5TH FLOOR OF THE THOMAS S. FOLEY COURTHOUSE IN SPOKANE,… $409,375
Modern Dry Wall, Inc. DESIGN BUILD SERVICES TO SUPPORT THE VBA'S INITIAL OCCUPANCY (I.E, NEW OFFICE SPACE BUILD-OUT) ON THE 5TH FLOOR OF THE THOMAS S. FOLEY COURTHOUSE IN SPOKANE,… $95,945
Modern Dry Wall, Inc. INSTALL FALL PROTECTION SYSTEM ON THE THOMAS FOLEY COURTHOUSE AND UNITED STATES POST OFFICE LOCATED IN SPOKANE, WASHINGTON. Patch Ceiling Area $231,762
CTA Inc. DESIGN BUILD SERVICES TO SUPPORT THE VBA'S INITIAL OCCUPANCY (I.E, NEW OFFICE SPACE BUILD-OUT) ON THE 5TH FLOOR OF THE THOMAS S. FOLEY COURTHOUSE IN SPOKANE,… $36,000
Advanced Fireproofing & Insulation, CO. DESIGN BUILD SERVICES TO SUPPORT THE VBA'S INITIAL OCCUPANCY (I.E, NEW OFFICE SPACE BUILD-OUT) ON THE 5TH FLOOR OF THE THOMAS S. FOLEY COURTHOUSE IN SPOKANE,… $43,900
Bullet Guard Corporation UPGRADE TO FIRE ALARM AND SECURITY SYSTEM AT OROVILLE LPOE IN OKANOGAN COUNTY, WA. POP IS 270 DAYS ENDING ON APRIL 13, 2020. Bullet Resistant Products $138,279
Western States Fire Protection Company UPGRADE TO FIRE ALARM AND SECURITY SYSTEM AT OROVILLE LPOE IN OKANOGAN COUNTY, WA. POP IS 270 DAYS ENDING ON APRIL 13, 2020. Fire Alarm $338,721
Western States Fire Protection Company UPGRADE TO FIRE ALARM AND SECURITY SYSTEM AT OROVILLE LPOE IN OKANOGAN COUNTY, WA. POP IS 270 DAYS ENDING ON APRIL 13, 2020. Fire Sprinkler $74,946
IRS Environmental Of Washington, Inc. INSTALL FALL PROTECTION SYSTEM ON THE THOMAS FOLEY COURTHOUSE AND UNITED STATES POST OFFICE LOCATED IN SPOKANE, WASHINGTON. Asbestos Abatement $152,649
Access Unlimited & Security Inc. UPGRADE TO FIRE ALARM AND SECURITY SYSTEM AT OROVILLE LPOE IN OKANOGAN COUNTY, WA. POP IS 270 DAYS ENDING ON APRIL 13, 2020. Security System $526,342
Apex Construction Service, LLC CONSTRUCTION CONTRACT FOR REPLACEMENT OF HIGH-LOW INSPECTION BOOTHS AT EASTPORT LAND PORT OF ENTRY IN BOUNDARY COUNTY, IDAHO. Labor/Equipment for booths $46,060
RON Stadley UPGRADE TO FIRE ALARM AND SECURITY SYSTEM AT OROVILLE LPOE IN OKANOGAN COUNTY, WA. POP IS 270 DAYS ENDING ON APRIL 13, 2020. Electrical Work $741,120
Perimeter Security Group, LLC UPGRADE TO FIRE ALARM AND SECURITY SYSTEM AT OROVILLE LPOE IN OKANOGAN COUNTY, WA. POP IS 270 DAYS ENDING ON APRIL 13, 2020. Fencing & Gates $145,323
Subcontractor not on record CONSTRUCTION CONTRACT FOR REPLACEMENT OF HIGH-LOW INSPECTION BOOTHS AT EASTPORT LAND PORT OF ENTRY IN BOUNDARY COUNTY, IDAHO. Electrical & Communication $110,842
Jay Henges Enterprises Inc. CONSTRUCTION CONTRACT FOR REPLACEMENT OF HIGH-LOW INSPECTION BOOTHS AT EASTPORT LAND PORT OF ENTRY IN BOUNDARY COUNTY, IDAHO. Durasteel Building $298,434
Subcontractor not on record REPLACE ROOF, YAKIMA, WA CH (WA0053ZZ) Design/Build Roofing Systems $249,940
Show all 23

Quick answers

Who was awarded contract GS10P16LTD7009?

GS10P16LTD7009 was awarded to RJS Construction Inc. by Region 10 (Public Buildings Service) on December 1, 2016.

How much is contract GS10P16LTD7009 worth?

Orders under GS10P16LTD7009 have obligated $7,866,607. Their combined potential value, with all options, is $7,866,877. GS10P16LTD7009's own ceiling is $40,000,000. A single order can be worth up to $5,000,000.

How many orders have been placed under contract GS10P16LTD7009?

8 orders have been placed under GS10P16LTD7009, the latest on May 2, 2022.

Who can order from contract GS10P16LTD7009?

GS10P16LTD7009 is a multiple award indefinite delivery contract. Only the awarding agency can place orders on it.

Is contract GS10P16LTD7009 part of a contract vehicle?

Yes. GS10P16LTD7009 is part of GSA PBS Region 10 Construction 2016-2021.

Was contract GS10P16LTD7009 competed?

The extent of competition for GS10P16LTD7009 was full and open competition after exclusion of sources. The government received 13 offers. It was set aside: Total Small Business.

On GovTribe

See this IDV's full record

  • Every order and transaction
  • The awardee's other awards and teaming partners
  • Similar IDVs and recompete opportunities
  • Ask GovTribe AI about this IDV