Combined order value
  • $5,193,613 Current, with exercised options
  • $5,197,464 Potential, with all options
Last date to order 100% complete
IDV ceiling 15% used
$34,143,310.95
Award type
Single award
Who can order
Only the awarding agency
Set-aside
Competitive 8(a)
Competition
Full and Open Competition after exclusion of sources · 6 offers Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Legislative mandates

Award details come from SAM.gov/FPDS.

Description

Operations & mechanical maintenance and vertical transportation equipment (VTE) maintenance services for the SAN diego federal buildings and courthouses. 24 month base period with, 4 each, 24 month option periods.

Task orders

Task order Ordering agency Obligated Awarded
Provide and install 69 stainless steel kick plates for various U.S. District courts located at the carter & keep… 47PK0922F0001 Region 9 (PBS) $11,221
Schwartz ADA bathroom accessibility 47PK0921F0105 Region 9 (PBS) $9,166
Weinberger misc project 47PK0921F0107 Region 9 (PBS) $9,758
Ckch elevator inspection 47PK0921F0104 Region 9 (PBS) $11,599
Weinberger exit signs replacement 47PK0921F0103 Region 9 (PBS) $49,607
Provide electrical repairs in the 6TH floor pretrial offices for usdc located at 333 W. Broadway, SAN diego CA 92101. 47PK0921F0087 Region 9 (PBS) $3,480
47PK0921F0075 Region 9 (PBS) $81,975
Refuel generators at carter keep courthouse and the edward J schwartz courthouse and federal building located at 880… 47PK0921F0070 Region 9 (PBS) $12,332
Provide all labor, supervision, materials, and equipment necessary to perform soil sampling and permanent closure in… 47PK0921F0036 Region 9 (PBS) $25,764
47PK0921F0015 Region 9 (PBS) $1,097
Run electrical wiring on the 4TH and 11TH floor. Carpet tiles will be installed as needed on the old locations. Work to… 47PK0921F0012 Region 9 (PBS) $17,018
Repair electrical deficiencies found at the schwartz usch located at 221 west broadway, SAN diego, CA 92101. 47PK0921F0005 Region 9 (PBS) $13,498
Repair damaged gate at the SAN ysidro lpoe parking structure located at 720 E SAN ysidro blvd., SAN diego, CA 92173 47PK0920F0103 Region 9 (PBS) $6,482
Remove existing failed mini ductless a/C unit in ceiling grid from control room and install one (1) new mini ductless… 47PK0920F0101 Region 9 (PBS) $10,850
Advanced metering project and the schwartz federal building. 47PK0220F0059 Region 9 (PBS) $8,658
Refuel generator tanks at carter keep courthouse, weinberger courthouse, schwartz courthouse in SD california 47PK0920F0097 Region 9 (PBS) $9,642
Provide and install a boiler room gas shut off button for the carter and keep courthouse, schwartz federal office… 47PK0920F0092 Region 9 (PBS) $16,856
Provide all labor, supervision, materials, and equipment necessary to provide labor, material and permits to repair 2… 47PK0920F0087 Region 9 (PBS) $7,608
Run new communication cables to multiple floors to support new lutron lighting system upgrades located at 333 west… 47PK0920F0079 Region 9 (PBS) $10,959
See sustainability clause 47PK0920F0083 Region 9 (PBS) $18,610
FOB schwartz signage repairs 47PK0920F0063 Region 9 (PBS) $4,881
Weinberger BRG doors and windows 47PK0720F0029 Region 9 (PBS) $42,326
See sustainability clause 47PK0920F0055 Region 9 (PBS) $8,639
See sustainability clause 47PK0920F0049 Region 9 (PBS) $12,712
See sustainability clause 47PK0920F0048 Region 9 (PBS) $15,594
See sustainability clause 47PK0920F0047 Region 9 (PBS) $5,509
Cooling tower retro fit at existing cooling tower catwalk area. 47PK0920F0043 Region 9 (PBS) $30,666
See sustainability clause 47PK0920F0032 Region 9 (PBS) $9,298
See sustainability clause 47PK0920F0027 Region 9 (PBS) $6,376
See sustainability clause 47PK0920F0018 Region 9 (PBS) $6,515
See sustainability clause 47PK0920F0011 Region 9 (PBS) $8,141
Ckch sump pump replacement 47PK0620F0017 Region 9 (PBS) $13,210
See sustainability clause 47PK0920F0008 Region 9 (PBS) $11,394
Weinberger courthouse flag pole fall protection device 47PK0620F0018 Region 9 (PBS) $8,614
See sustainability clause 47PK0920F0010 Region 9 (PBS) $10,349
See sustainability clause 47PK0920F0009 Region 9 (PBS) $9,144
Schwartz broken glass replacement 47PK0620F0014 Region 9 (PBS) $6,852
Carter & keep underground storage tank line leak detector 47PK0620F0009 Region 9 (PBS) $34,084
Meets clause requirements 47PK0920F0006 Region 9 (PBS) $19,959
See sustainability clause 47PK0920F0042 Region 9 (PBS) $47,914
Replacement of bad cast iron piping. 47PK0619F0046 Region 9 (PBS) $14,345
Contractor to provide labor, materials, equipment and supervision necessary to remove window tint at the schwartz per… 47PK0619F0048 Region 9 (PBS) $8,400
Generator refueling 47PK0619F0047 Region 9 (PBS) $17,969
Fire sprinkler repairs 47PK0919F0125 Region 9 (PBS) $7,557
Painting of curbs and other areas. 47PK0619F0045 Region 9 (PBS) $9,912
Repair of roll up gate to carter keep garage. 47PK0919F0116 Region 9 (PBS) $19,167
Replace glass that was vandalized and tint removal. 47PK0919F0114 Region 9 (PBS) $4,914
To furnish and install eighteen kane stainless steel defender interview screens at the carter keep federal building… 47PK0919F0110 Region 9 (PBS) $121,995
Schwartz usch broken window replacement 47PK0919F0101 Region 9 (PBS) $5,034
FOB sidewalk repair - demo and haul away damaged bricks, apply concrete bonding coat, supply and install new bricks… 47PK0919F0099 Region 9 (PBS) $4,251
Show 40 more

Latest 50 of 229 listed here. See the rest on GovTribe.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope PS39 · O & M services for SAN diego, CA. $0
Other Administrative Action PA40 · O & M at the SAN diego downtown federal buildings, SAN diego, CA. $3,217,409
Supplemental Agreement for work within scope PS38 · O & M and VTE at the SAN diego downtown federal buildings, SAN diego, CA $7,659
Other Administrative Action PS37 · SAN diego downtown federal buildings O & M and VTE services. $320,072
Supplemental Agreement for work within scope PS36 · O & M and VTE at the SAN diego downtown federal buildings. $320,072
Supplemental Agreement for work within scope PS35 · O & M and VTE at the downtown federal buildings, SAN diego, CA. $0
Other Administrative Action PA34 · Administrative correction to PS18 $0
Supplemental Agreement for work within scope PS33 · O & M and VTE at the SAN diego downtown federal buildings, CA. $11,636
Supplemental Agreement for work within scope PS32 · O & M and VTE services at the downtown SAN diego federal buildings. $317,627
Exercise an Option PO31 · O & M at the downtown federal buildings $1,562,633
Supplemental Agreement for work within scope PS30 · O & M at the SAN diego downtown federal buildings. $0
Other Administrative Action PA29 · O & M at the downtown federal buildings in SAN diego, CA -$87,405
Supplemental Agreement for work within scope PS28 · O & M at the downtown federal buildings, SAN diego, CA. $1,736,236
Supplemental Agreement for work within scope PS27 · O & M and VTE at the SAN diego downtown federal buildings. $0
Supplemental Agreement for work within scope PS26 · O & M and VTE at the downtown federal buildings, SAN diego, CA $283,042
Supplemental Agreement for work within scope PS25 · O & M at the downtown federal buildings in SAN diego, CA $3,303,774
Supplemental Agreement for work within scope PS24 $26,974
Exercise an Option PO23 · Project: operations and maintenance and vertical transportation equipment (VTE) services for the edward schwartz federal building, jacob weinberger… $3,247,443
Funding Only Action PS22 · Incorporate the current CBA and SCA and provide wage adjustment for OY5 (contract year 7) POP 10/01/2017 to 09/30/2018 for the operations & maintenance and… $11,283
Exercise an Option PO21 · Reconcile last 3 months of OY4 (july, AUG, sept 2017) and exercise OY5 (10/01/2017 to 09/30/2018) for the operations, maintenance and vertical transportation… $1,044,475
Change Order PC20 · Remove escalator maintenance service from the downtown SAN diego operations & maintenance (O & M) and vertical transportation equipment (VTE) contract. Reduce… $1,042,789
Funding Only Action PS19 · Option period 4 (contract year 6) wage adjustment for operations & maintenance and vertical transportation equipment services at the downtown SAN diego… $1,053,633
Other Administrative Action PA18 · Admin MOD to update the end date in easi from 09/30/2016 to 09/30/2017. $0
Funding Only Action PA17 · Reconciliation modification for limitation of government's obligation (LOGO) award at downtown SAN diego federal buildings - OY3 O & M services, clin 8031 (01… $2,767,128
Exercise an Option PS16 · Exercise OY4 (contract year 6) of the O & M and VTE service contract for the downtown federal buildings in SAN diego, CA. Clin: 8040 POP: 01 OCT 16 - 30 sept… $251,557
Other Administrative Action PA15 · O & M and VTE services $4,599,402
Other Administrative Action PA14 · O & M and VTE $0
Supplemental Agreement for work within scope PS13 · O & M and VTE for SAN diego downtown federal buildings. $251,557
Supplemental Agreement for work within scope PS12 · O & M and VTE $0
Supplemental Agreement for work within scope PS11 · O & M and VTE for the down town SAN diego federal buildings. $3,335
Supplemental Agreement for work within scope PS10 · O & M and VTE services, SAN diego, CA $3,366,761
Other Administrative Action PA09 · O & M and VTE $0
Supplemental Agreement for work within scope PS08 · O & M and VTE services $2,004,473
Supplemental Agreement for work within scope PS07 · Operation, maintenance and related services. $0
Supplemental Agreement for work within scope PS06 · O & M and VTE services $36,240
Other Administrative Action PA05 $0
Supplemental Agreement for work within scope PS04 · Closely associated- operations and mechanical maintenance services for the SAN diego courthouses. This modification adds a nearby daycare center building… $113,677
Supplemental Agreement for work within scope PS02 · Closely associated- MOD to change performance period dates for operations & mechanical maintenance services for the US courthouse annex in SAN diego, CA $35,742
Original award $3,294,085
Show all 39

Quick answers

Who was awarded contract GS09P11KSD0042?

GS09P11KSD0042 was awarded to Kcorp Technology Services, Inc. by Region 9 (Public Buildings Service) on September 1, 2011.

How much is contract GS09P11KSD0042 worth?

Orders under GS09P11KSD0042 have obligated $5,193,613. Their combined potential value, with all options, is $5,197,464. GS09P11KSD0042's own ceiling is $34,143,311.

How many orders have been placed under contract GS09P11KSD0042?

229 orders have been placed under GS09P11KSD0042, the latest on October 22, 2021.

Who can order from contract GS09P11KSD0042?

GS09P11KSD0042 is a single award indefinite delivery contract. Only the awarding agency can place orders on it.

Was contract GS09P11KSD0042 competed?

The extent of competition for GS09P11KSD0042 was full and open competition after exclusion of sources. The government received 6 offers. It was set aside: Competitive 8(a).

On GovTribe

See this IDV's full record

  • Every order and transaction
  • The awardee's other awards and teaming partners
  • Similar IDVs and recompete opportunities
  • Ask GovTribe AI about this IDV