Operations, maintenance and repair services of facilities, structures, equipment and systems for port of entries.

Ended Indefinite Delivery Contract Awarded Last action

Contract number
GS09P09KSD0138
Awardee
Awarding agency
Task orders
204 $4,052,370 obligated

Award facts

Combined order value
$4,052,370 Current and potential, with all options
Last date to order 100% complete
IDV ceiling 6% used
$68,243,851.43
Award type
Single award
Who can order
Only the awarding agency
Set-aside
8(a) Sole Source
Competition
Not Available for Competition · 1 offer Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Legislative mandates

Award details come from SAM.gov/FPDS.

Task orders

Task order Ordering agency Obligated Awarded
See sustainable clause 47PK0920F0007 Region 9 (PBS) $8,934
Abate several areas of VCT floor tile (non-ACM) and mastic (ACM). 47PK0919F0132 Region 9 (PBS) $6,939
Repair water main leak at NW corner 47PK0919F0128 Region 9 (PBS) $20,072
Repair water main leak 47PK0919F0127 Region 9 (PBS) $9,133
Provide and install ten (10) new 30,000 BTU high efficiency, mini split, heat pump type units. 47PK0919F0113 Region 9 (PBS) $40,039
The contractor shall provide labor, materials, equipment and supervision necessary to replace the tstats with remote… 47PK0919F0112 Region 9 (PBS) $5,974
Contractor to provide all labor, materials and support necessary to saw cut and remove damaged concrete around two fire… 47PK0919F0111 Region 9 (PBS) $24,795
Install two additional electrical circuits in joint use breakroom 47PK0919F0106 Region 9 (PBS) $6,347
Replace damaged or missing bollards with heavy duty bollards. 47PK0919F0105 Region 9 (PBS) $18,548
CA0267JJ painting 47PK0919F0103 Region 9 (PBS) $6,306
CA0267 stucco repairs 47PK0919F0102 Region 9 (PBS) $13,110
Installation of mecho shades at calexico east lpoe 47PK0919F0097 Region 9 (PBS) $11,332
CBP property line markings 47PK0919F0088 Region 9 (PBS) $5,328
CA0289JJ NE vehicle gate modifications 47PK0919F0087 Region 9 (PBS) $4,081
Contractor to provide all labor, materials, and support necessary to relocate a CBP provided booth to Z-portal office… 47PK0919F0080 Region 9 (PBS) $17,410
Replace BAS head end and upgrade software 47PK0919F0082 Region 9 (PBS) $16,235
Contractor to provide all labor, materials, and support necessary to install insulation to roof and walls of 20'X 8'… 47PK0919F0077 Region 9 (PBS) $13,866
Repair damaged vehicle gate and install curb at the base of gate to prevent future gate damage. 47PK0919F0076 Region 9 (PBS) $8,027
Install new HVAC units for the public shelters in secondary lanes Z-portal area at calex lpoe 47PK0919F0075 Region 9 (PBS) $15,006
CBP cell light fixture replacement in cells 220 and 223 with ceiling mount fixtures designed for cells. 47PK0919F0074 Region 9 (PBS) $8,541
Multiple follow on project at calexico wests 47PK0919F0073 Region 9 (PBS) $31,388
Repair 4 downspouts to drain away from building foundation 47PK0919F0068 Region 9 (PBS) $4,557
Replace 5 standard drinking fountains with bottle filling fountains at multiple sites at otay mesa land port of entry. 47PK0919F0067 Region 9 (PBS) $11,194
Install new digital controls for both air handlers. 47PK0919F0063 Region 9 (PBS) $20,906
Repari and paint damaged gates at the waste collection area. Vertical supports need straightening or replacement… 47PK0919F0057 Region 9 (PBS) $5,629
Install a standoff fence adjacent to the K9 enclosures to protect the building from damage. 47PK0919F0051 Region 9 (PBS) $6,517
Remove existing industrial garbage disposal and replace with new commercial garbage disposal. 47PK0919F0046 Region 9 (PBS) $6,097
Contractor to replace mirrors with new vandal resistant mirrors in main pedestrian bathroom 47PK0919F0045 Region 9 (PBS) $2,741
Install a seismic safety valve (pipe rupture valve) to provide protection against supply line failure or over speed… 47PK0919F0041 Region 9 (PBS) $8,869
Contractor to provide all labor, materials and support necessary to remove door lock mechanism from public restrooms… 47PK0919F0036 Region 9 (PBS) $3,354
Contractor to provide all labor, materials and support necessary to install window blinds and shades in locations… 47PK0919F0031 Region 9 (PBS) $18,123
Contractor to provide all labor, material and equipment to repair irrigation lines at the 905 employee parking lot to… 47PK0919F0021 Region 9 (PBS) $5,986
Install an epoxy lining in a broken sewer line near the public men's restroom on the 1ST floor. 47PK0919F0020 Region 9 (PBS) $4,443
Purchase and install handicapped door openers at the employee restrooms near the GYM at the otay mesa lpoe, 2500… 47PK0918F0125 Region 9 (PBS) $16,476
Fire alarm panel replacement provide all design services, labor, supervision, and materials necessary to complete the… 47PK0918F0124 Region 9 (PBS) $89,036
Contractor to provide materials and support to repair concrete at vehicle/truck bridge. 47PK0918F0114 Region 9 (PBS) $17,816
The contractor shall provide labor, materials, equipment and supervision necessary to remove the south railing at the… 47PK0918F0111 Region 9 (PBS) $4,468
The contractor shall provide labor, materials, equipment and supervision necessary to repair or replace failed… 47PK0918F0107 Region 9 (PBS) $4,837
To replace existing damaged and worn yellow speed bumps at the pre-primary vehicle lane at the calexico east lpoe and… 47PK0918F0095 Region 9 (PBS) $24,153
Multiple projects at calexico east and calexico west land port of entries. 47PK0918F0093 Region 9 (PBS) $75,495
Replace deteriorating walkway, replace inspection booth HVAC unit with a new efficient unit and repair asphalt in… 47PK0918F0084 Region 9 (PBS) $66,084
Contractor to provide all labor, materials and support to repair the damaged roll gate and install photo sensor at… 47PK0918F0079 Region 9 (PBS) $4,308
Provide labor and materials to demo existing vehicle lift and install new reinforced approach ramp. 47PK0918F0080 Region 9 (PBS) $5,438
The contractor shall provide labor, materials, equipment and supervision necessary to: replace non-code compliant… 47PK0918F0056 Region 9 (PBS) $9,293
The contractor shall furnish and supply all labor, materials, equipment, and supervision to complete a cross connection… 47PK0918F0047 Region 9 (PBS) $24,990
The contractor shall provide all labor, materials, equipment, management, supervision, and support services necessary… 47PK0918F0040 Region 9 (PBS) $98,491
Contractor to furnish and supply all necessary labor, materials and equipment to relocate a drinking fountain and… 47PK0918F0045 Region 9 (PBS) $2,638
The contractor shall provide labor, materials, equipment and supervision necessary to replace the cooling coil in AH-2… 47PK0918F0032 Region 9 (PBS) $3,796
To repair and RE-stripe the employee parking lot in the cargo area of the calexico east land port of entry at 1699 east… 47PK0918F0026 Region 9 (PBS) $19,575
Contractor to install directional arrows, portable shower and remove and replace carpet at the calexico east port of… 47PK0918F0016 Region 9 (PBS) $91,731
Show 40 more

Latest 50 of 204 listed here. See the rest on GovTribe.

Transactions

Action Obligated Date
Other Administrative Action PA38 · O & M and VTE at the otay mesa, calexico W & E and andrade lpoes $2,513,780
Other Administrative Action PA37 $4,981,281
Other Administrative Action PA36 $0
Exercise an Option PO35 $502,756
Other Administrative Action PA34 $0
Supplemental Agreement for work within scope PS33 $74,064
Other Administrative Action PA32 $0
Supplemental Agreement for work within scope PS31 · Project: operations and maintenance and vertical transportation equipment services at the otay mesa, calexico west & east, and andrade lpoes. The purpose of… $290,068
Other Administrative Action PA30 · The purpose of this modification is to: a) revise PS29 modification description from: limitation of the government's obligation: this award is a fixed price… $0
Supplemental Agreement for work within scope PS29 · Project: operations and maintenance and vertical transportation equipment services at the otay mesa, calexico west/east and andrade lpoe. The purpose of this… $58,900
Exercise an Option PO28 · Reconcile obligation amount for OY4 (contract year 9) for services provided 06/01/2017 to 04/30/2018 and exercise OY5 (contract year 10); one month obligated,… $4,473,775
Funding Only Action PS27 · OY4 (contract year 9) wage adjustment for changes in the collective bargaining agreement (CBA) for operations & maintenance and vertical transportation services… -$3,180
Funding Only Action PA26 · Admin MOD (PA26) to reconcile option year 3 (contract year 8) POP 05/01/2016 to 04/30/2017 for operations & maintenance and vertical transportation equipment… $3,928,931
Other Administrative Action PA25 · Operations & maintenance and vertical transportation equipment service at the otay mesa, calexico east, calexico west and andrade land ports of entry in… $0
Exercise an Option PO23 · Exercise OY4 (contract year 9) POP: 01 may 2017 - 30 APR 2018 for operations & maintenance (O & M) and vertical transportation equipment (VTE) services at the… $374,145
Exercise an Option PS21 · Exercise OY03 from may 01, 2015 to april 30, 2017 for operations and maintenance and vertical transportation equipment services at the andrade, otay mesa and… $358,609
Other Administrative Action PA15 · O & M and VTE services $7,369,435
Supplemental Agreement for work within scope PS14 · O & M and VTE $341,760
Supplemental Agreement for work within scope PS13 · O & M/VTE at otay mesa, calexico and andrade land ports of entry $145,696
Supplemental Agreement for work within scope PS12 · O & M and VTE services $3,792,569
Supplemental Agreement for work within scope PS11 · O & M services at the otay mesa, calexico and andrade lpoes $387,567
Supplemental Agreement for work within scope PS10 · Operations, maintenance and repar services $0
Other Administrative Action PA09 $0
Supplemental Agreement for work within scope PS08 · O & M services $181,742
Change Order PS07 · "other functions" - project: operations, maintenance and repair services at the otay mesa land port of entry, calexico west and east land port of entry, and… $19,080
Supplemental Agreement for work within scope PS06 · O & M services contract for the calexico, andrade and otay mesa lpoe's. Wage adjustment for the period 5/1/2011 thru 4/30/2012. $333,751
Other Administrative Action PA05 · Operations & mechanical maintenance services for the calexico, otay mesa and andrade land ports of entry (LPOE). This is an administrative MOD to correct the… $0
Supplemental Agreement for work within scope PS04 · CBA wage adjustment for O & M services at otay mesa, calexico and andrade lpoe, POP 5/1/2009 thru 4/30/2014 $743,528
Other Administrative Action PA03 · Operations & maintenance services otay mesa, calexico and andrade land ports of entry $0
Supplemental Agreement for work within scope PS02 $180,695
Supplemental Agreement for work within scope PS01 · Operations, maintenance and repair services $776,037
Original award $12,977,576
Show all 32

Quick answers

Who was awarded contract GS09P09KSD0138?

GS09P09KSD0138 was awarded to Kcorp Technology Services, Inc. by Region 9 (Public Buildings Service) on April 29, 2009.

How much is contract GS09P09KSD0138 worth?

Orders under GS09P09KSD0138 have obligated $4,052,370. GS09P09KSD0138's own ceiling is $68,243,851.

How many orders have been placed under contract GS09P09KSD0138?

204 orders have been placed under GS09P09KSD0138, the latest on October 28, 2019.

Who can order from contract GS09P09KSD0138?

GS09P09KSD0138 is a single award indefinite delivery contract. Only the awarding agency can place orders on it.

Was contract GS09P09KSD0138 competed?

The extent of competition for GS09P09KSD0138 was not available for competition. The government received 1 offer. It was set aside: 8(a) Sole Source.

On GovTribe

See this IDV's full record

  • Every order and transaction
  • The awardee's other awards and teaming partners
  • Similar IDVs and recompete opportunities
  • Ask GovTribe AI about this IDV