Partitioning and miscellaneous repairs award (GS-04P-13-BV-D-0021) for the atalanta central service center/atlanta, GA. Partitioning and miscellaneous repairs award

Ended Indefinite Delivery Contract Awarded Last action

Contract number
GS04P13BVD0021
Awardee
Awarding agency
Task orders
80 $1,973,612 obligated

Award facts

Opportunity
  • GS04P13BVD0021 Solicitation number
Combined order value
  • $1,980,482 Current, with exercised options
  • $1,994,384 Potential, with all options
Last date to order 100% complete
Award type
Single award
Who can order
Only the awarding agency
Set-aside
8(a) Sole Source
Competition
Not Competed under SAP · 1 offer Simplified Acquisition
Pricing
Firm Fixed Price
Legislative mandates

Award details come from SAM.gov/FPDS.

Task orders

Task order Ordering agency Obligated Awarded
"other requirements" repair ceiling drain line for the GSA at the RBR usfb/CH in atlanta, GA GSP0415RR5083 Region 4 (PBS) $4,403
"other requirements" this is a request to paint the loading dock hallway at the RBR usfb/CH for the U.S. General… GSP0415RR5037 Region 4 (PBS) $6,043
Other functions rome ceiling repair in the rome federal building and courthouse, rome GA GS04P15EXD0055 Region 4 (PBS) $65,605
The purpose of this requirement is to renovate the 3RD floor for the U.S. Trustees at the richard B. Russell federal… GSP0415EX5046 Region 4 (PBS) $163,076
Replace conference room ceiling - RBR bldg / atlanta, GA GSP0415EX5093 Region 4 (PBS) $6,700
Other functions renovations to the 3RD floor solicitors officer in russell B richard building atlanta, GA GSP0415EX5095 Region 4 (PBS) $43,657
Renovations to 13TH break room, RBB, atlanta GSP0415EX5090 Region 4 (PBS) $3,190
Other functions renovations to judges chamber suite 2167 russsell B richard federal building, atlanta, GA GS04P15EXD0043 Region 4 (PBS) $66,573
Other functions renovate suite 1921 richard B russell building. Atlanta, GA GS04P15EXD0044 Region 4 (PBS) $55,973
Ceiling repair 2121 RBR, atlanta, GA GS04P15EXD0061 Region 4 (PBS) $70,310
"other requirements" emergency space renovations funded by GSA for the uscoa at the tuttle CH in atlanta, GA GSP0415EX5054 Region 4 (PBS) $16,376
Project: build-out of three (3) offices on the 22ND floor. Richard B. Russell federal courthouse atlanta, GA GSP0415EX5049 Region 4 (PBS) $34,584
Renovations to chambers 1788 atlanta, GA GS04P15EXC0032 Region 4 (PBS) $72,626
Other functions ceiling repair suite 1988 richard B russell building GS04P15EXD0042 Region 4 (PBS) $70,103
Other functions build out parittion offices in the godbold building GS04P15EXD0009 Region 4 (PBS) $110,205
Removal and replacement of ceiling in suite 1921 of the richard B. Russell federal building located in atlanta, GA GSP0415EX5018 Region 4 (PBS) $68,486
F/I crown molding and paint bookcases, U.S. District court, richard B. Russell FB, atlanta, GA. GSP0415RB0022 Region 4 (PBS) $0
Renovate admin area on the 22D floor for U.S. District court at the richard B. Russell FB, atlanta, GA. GSP0415RB0021 Region 4 (PBS) $11,279
Renovate suites 2015 NAD 2017 restroom in the U.S. District courts located in the richard B. Russell FB, atlanta, GA. GSP0415RB0024 Region 4 (PBS) $21,696
F/I wall covering, paint door frames, walls, chair rails, cove base for U.S. Bankruptcy. Richard B. Russell FB… GSP0415RB0019 Region 4 (PBS) $14,655
Remove and replace carpet in gainsville FB/CH, gainsville, GA. GSP0415RB0020 Region 4 (PBS) $6,820
Remove and replace carpet in judge's chamber in the rome federal building, rome, GA. GSP0415RB0023 Region 4 (PBS) $12,253
Removal of ceiling grid system on the 21ST floor of the richard B. Russell federal building. GSP0415EX5015 Region 4 (PBS) $26,686
Remove and replace carpet in two rooms on 12TH and 14TH floors U.S. Bankruptcy court in the richard B. Russell… GSP0415RB0017 Region 4 (PBS) $3,070
F/I new ceiling tile and grid system, to include new lights, HVAC diffusers for U.S. District court, richard B. Russell… GSP0415RB0018 Region 4 (PBS) $4,158
Renovate room G-18 in the gainesville federal building, gainesville, GA. GSP0415RB0016 Region 4 (PBS) $6,329
F/I tankless water heater and electrical in suite 505 break room located in the court of appeals FB, elbert P. Tuttle… GSP0415RB0015 Region 4 (PBS) $3,010
F/I chair rail and wallcovering on the 13 the floor, US bankruptcy court in the richard B. Russell federal building… GSP0415RB0014 Region 4 (PBS) $18,601
Remove and replace floor tiles on the floor and tile base of judge's restroom on 1ST floor of the gainesville federal… GSP0415RB0006 Region 4 (PBS) $4,280
F/I bright brass handrails on the 1ST and 3RD floor courtrooms in the gainesville federal courthouse, gainesville, GA. GSP0415RB0007 Region 4 (PBS) $5,300
F/I security gate for custom and border protection, college park, GA. GSP0415RB0008 Region 4 (PBS) $8,550
F/I picture frame molding to induction unit and paint suites 2321 and 2342 at the richard B. Russell FB, atlanta, GA. GSP0415RB0005 Region 4 (PBS) $6,176
F/I light fixtures and EGG crate returns in judge's chambers on the 4TH floor of the ebert P. Tuttle FB., atlanta, GA. GSP0415RB0003 Region 4 (PBS) $9,996
Paint door frames in the back hallways of the 12TH and 14TH floors at the richard B. Russell federal building, atlanta… GSP0415RB0002 Region 4 (PBS) $3,932
F/I panel trim and paint doors on 17,19,21 and 23 floors at the richard B. Russell FB, atlanta, GA. GSP0415RB0004 Region 4 (PBS) $8,825
Remove and replace wallcovering in suite 505 court of appeals, richard B. Russell federal courthouse building, atlanta… GSP0414EX5106 Region 4 (PBS) $33,353
Furnish and install partition wall in the basement storage room, located in the richard B. Russell federal building… GSP0414RB0055 Region 4 (PBS) $3,525
Rome third floor common space renovations phase 1, rome federal building, rome, georgia contractor shall furnish all… GSP0414EX5062 Region 4 (PBS) $78,618
Replace three cypher electronic lockskeyed to match existing on the 13TH floor of U.S. Bankruptcy court, richard B… GSP0414RB0053 Region 4 (PBS) $3,484
Remove and replace wallcovering in U.S. Bankruptcy court in the richard B. Russell FB, atlanta, GA. GSP0414RB0052 Region 4 (PBS) $6,848
Paint and RE-carpet the FBI space in the rome federal building, rome, GA. GSP0414RB0049 Region 4 (PBS) $13,091
Remove and replace carpet in suite 1471 in US bankruptcy court, richard B. Russell FB, atlanta, GA. GSP0414RB0050 Region 4 (PBS) $10,917
Remove and replace wallcovering at U.S. Bankruptcy court, richard B. Russell FB, atlanta, GA. GSP0414RB0051 Region 4 (PBS) $5,410
F/I crown molding, side trim and paint bookcase in suite 2321 in the richard B. Russell FB/CH, atlanta, GA. GSP0414RB0045 Region 4 (PBS) $9,589
Remove wall covering and paint walls on the 20TH floor in judges chambers in the richard B. Russell FB/CH, atlanta, GA. GSP0414RB0048 Region 4 (PBS) $14,495
Paint registers on the 12TH and 14TH floor as requested by the US bankruptcy cort in the richard B. Russell federal… GSP0414RB0046 Region 4 (PBS) $4,812
Furnish and install chair rail to match building standard, paint chair rail, paint wall in back hallways in the US… GSP0414RB0040 Region 4 (PBS) $16,875
Remove and replace counter-tops usbc 12TH and 14 floor located in the richard B. Russell federal building, atlanta, GA. GSP0414RB0037 Region 4 (PBS) $0
Paint walls and clean or change out carpet for HUD, 3D floor located in the richard B. Russell federal building… GSP0414RB0032 Region 4 (PBS) $15,505
Install government furnished carpet on 3RD floor hallway in the newnan federal building, newnan, GA. GSP0414RB0030 Region 4 (PBS) $2,066
Show 40 more

Latest 50 of 80 listed here. See the rest on GovTribe.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope PS06 · Modification to correct the period of performance in option period II for partition contract GS-04P-13-BV-D-0021/ATL central. $0
Supplemental Agreement for work within scope PO05 · Modification to exercise option period II for contract GS-04P-13-BV-D-0021/ATL central. $0
Supplemental Agreement for work within scope PS04 · This modification added the task order ordering procedures to the contract scope and changed contracting officer authority. Other functions $0
Supplemental Agreement for work within scope PS03 · Modification to deobligate the minimum guarantee for partition contract GS-04P-13-BV-D-0021/ATL central $0
Supplemental Agreement for work within scope PS02 · The modification to exercise option period I for partitinoning & MIS. Repairs contract GS-04P-13-BV-D-0021/ATL central. $0
Change Order PC02 · Modification to add an additional line item to partition contract GS-04P-13-BV-D-0021/ATL central service center. $0
Other Administrative Action PS01 · Modification to update partition & miscellaneous repairs to on contract no. GS-04P-13-BV-D-0021. $0
Original award $0

Quick answers

Who was awarded contract GS04P13BVD0021?

GS04P13BVD0021 was awarded to Synergy Development Partners, LLC by Region 4 (Public Buildings Service) on August 6, 2013.

How much is contract GS04P13BVD0021 worth?

Orders under GS04P13BVD0021 have obligated $1,973,612. Their combined current value, with exercised options, is $1,980,482. Their combined potential value, with all options, is $1,994,384.

How many orders have been placed under contract GS04P13BVD0021?

80 orders have been placed under GS04P13BVD0021, the latest on September 30, 2015.

Who can order from contract GS04P13BVD0021?

GS04P13BVD0021 is a single award indefinite delivery contract. Only the awarding agency can place orders on it.

Was contract GS04P13BVD0021 competed?

The extent of competition for GS04P13BVD0021 was not competed under sap. The government received 1 offer. It was set aside: 8(a) Sole Source.