This regionalized multiple award construction contract two (MACC-II) resulted in twenty-four (24) indefinite delivery/indefinite quantity (IDIQ) in support MACC-II. The MACC-II provides a critical…

Active Indefinite Delivery Contract Awarded Last action

Contract number
80SSC018D0011
Awardee
Awarding agency
Task orders
13 $78,237,959 obligated

Award facts

Opportunity
  • NNS17612547R Solicitation number
Combined order value
  • $78,237,959 Current, with exercised options
  • $97,737,959 Potential, with all options
Last date to order 95% complete
IDV ceiling 34% used
$229,680,511.82
Award type
Multiple award
Who can order
Only the awarding agency
Set-aside
Service-Disabled Veteran-Owned Small Business
Competition
Full and Open Competition after exclusion of sources · 71 offers Negotiated Proposal / Quote
Pricing
Order Dependent (IDV only)
Legislative mandates

Award details come from SAM.gov/FPDS.

About this IDV

NASA's John C. Stennis Space Center awarded a multiple-award IDIQ to Birmingham Industrial Construction, LLC, a service-disabled veteran-owned small business, on October 24, 2017, with a contract ceiling of $229.68 million and an ultimate completion date of April 23, 2027. This regionalized IDIQ is one of a maximum of 24 awards under the Multiple Award Construction Contract II (MACC-II) program.

The IDIQ supports general construction, alteration, modification, maintenance and repair, demolition, design-build, and new construction of buildings, facilities, and real property at John C. Stennis Space Center, Johnson Space Center (including White Sands Test Facility), Kennedy Space Center, and Marshall Space Flight Center (including Michoud Assembly Facility). MACC-II also supports emergency response to natural disasters and emergencies. Other NASA centers and federal tenants at NASA facilities may utilize MACC-II with Stennis Space Center procurement officer approval. The vehicle is not a requirements contract and is intended to provide highly flexible construction contracting for participating centers.

Recent task order activity under this IDIQ reflects work across multiple NASA installations. Marshall Space Flight Center issued delivery orders valued at $27.9 million for Revitalize Pressurants and Propellants Systems Phase 3 (Huntsville, October 2026) and $26.0 million for roof replacement at Building 103, Michoud Assembly Facility (New Orleans, September 2025). Stennis Space Center issued a $1.1 million delivery order for Level 4 Aspirator Deck Refurbishment at Building 4120 (October 2025). Langley Research Center issued a $9.25 million delivery order for sanitary sewer system replacement and repair (Hampton, September 2024). Additional orders span facility infrastructure, HVAC systems, thermal energy storage, and specialized electrical design-build work across the NASA center network.

Description

This regionalized multiple award construction contract two (MACC-II) resulted in twenty-four (24) indefinite delivery/indefinite quantity (IDIQ) in support MACC-II. The MACC-II provides a critical in-place contractual mechanism through a regionalized multiple award, indefinite delivery, indefinite quantity (IDIQ) contract to support general construction, alteration, modification, maintenance and repair, demolition, design-build, and new construction of buildings, facilities, and real property at john c. Stennis space center (SSC), johnson space center (JSC) including white sands test facility (wstf), kennedy space center (KSC), and marshall space flight center (msfc) including michoud assembly facility (MAF). MACC-II will also support emergency response to natural disasters and emergencies. Other NASA centers and federal tenants at NASA facilities may utilize MACC-II with SSC procurement officer approval. The MACC-II is not a requirements contract and therefore not mandatory. The MACC-II is intended to provide a highly flexible construction contracting vehicle for participating centers.

Task orders

Task order Ordering agency Obligated Awarded
Revitalize pressurants and propellants systems phase 3 80MSFC26F7050 Marshall Space Flight Center $8,400,000
A1 level 4 aspirator deck refurbishment 80SSC025F7016 Stennis Space Center $1,097,981
The purpose of this task order is to replace the roof of the main manufacturing building at michoud assembly… 80MSFC25F7047 Marshall Space Flight Center $26,042,042
Replace and repair of sanitary sewer systems at NASA langley research center - phase 1. 80LARC24F0042 Langley Research Center $9,583,317
National center for critical information processing and storage IPS zone H1 buildout at stennis space center, MS 80SSC024F0019 Stennis Space Center $4,879,363
Low voltage ARC flash design/build 80SSC023F0005 Stennis Space Center $744,397
This project will add a second thermal energy storage (TES) tank to the central chilled water plant (ccwp) system… 80MSFC22F0222 Marshall Space Flight Center $4,237,483
Design build sewer pipping rehabilitation building 1100 area at stennis space center, MS 80SSC022F0006 Stennis Space Center $483,654
The work to be performed under this project consists of providing the labor, equipment, and materials to perform the… 80MSFC21F0257 Marshall Space Flight Center $12,811,399
National center for critical information processing and storage (nccips) zone c additional infrastructure 80SSC021F0006 Stennis Space Center $3,004,551
High purity air dryer design high pressure gas facility 80SSC019F0056 Stennis Space Center $2,967,260
The contractor shall provide all resources (except as may be expressly stated in the contract as furnished by the… 80LARC19F0081 Langley Research Center $3,981,512
Safety & health requirements in accordance with paragraph h.10 on the basic contract. 80SSC018F0021 Stennis Space Center $5,000
Show all 13

Transactions

Action Obligated Date
Exercise an Option P00010 $0
Other Administrative Action P00009 $0
Other Administrative Action P00008 $0
Vendor Address Change P00007 · This regionalized multiple award construction contract two (MACC-II) shall result in the award of a maximum of twenty-four (24) indefinite delivery/indefinite… $0
Supplemental Agreement for work within scope P00006 · This regionalized multiple award construction contract two shall result in the award of a maximum of twenty-four indefinite delivery/indefinite quantity in… $0
Other Administrative Action P00005 $0
Supplemental Agreement for work within scope P00004 $0
Supplemental Agreement for work within scope P00003 $0
Supplemental Agreement for work within scope P00002 $0
Other Administrative Action P00001 · This regionalized multiple award construction contract two (MACC-II) shall result in the award of a maximum of twenty-four (24) indefinite delivery/indefinite… $0
Original award $0
Show all 11

Quick answers

Who was awarded contract 80SSC018D0011?

80SSC018D0011 was awarded to Birmingham Industrial Construction, LLC by Stennis Space Center (National Aeronautics and Space Administration) on October 24, 2017.

How much is contract 80SSC018D0011 worth?

Orders under 80SSC018D0011 have obligated $78,237,959. Their combined potential value, with all options, is $97,737,959. 80SSC018D0011's own ceiling is $229,680,512.

How many orders have been placed under contract 80SSC018D0011?

13 orders have been placed under 80SSC018D0011, the latest on October 1, 2026.

Who can order from contract 80SSC018D0011?

80SSC018D0011 is a multiple award indefinite delivery contract. Only the awarding agency can place orders on it.

Was contract 80SSC018D0011 competed?

The extent of competition for 80SSC018D0011 was full and open competition after exclusion of sources. The government received 71 offers. It was set aside: Service-Disabled Veteran-Owned Small Business.

On GovTribe

See this IDV's full record

  • Every order and transaction
  • The awardee's other awards and teaming partners
  • Similar IDVs and recompete opportunities
  • Ask GovTribe AI about this IDV