General construction basic ordering agreement. BOA will be used on an as needed basis for various construction projects, not to exceed $4M or 5 years, which ever comes first, with no express or…

Ended Basic Ordering Agreement Awarded Last action

Contract number
W911PT12G0001
Awardee
Awarding agency
Task orders
21 $1,777,873 obligated

Award facts

Opportunity
Combined order value
$1,777,873 Current and potential, with all options
Last date to order 100% complete
Maximum order
$4,000,000.00
Award type
Single award
Who can order
Only the awarding agency
Set-aside
No set-aside
Pricing
Firm Fixed Price
Legislative mandates

Award details come from SAM.gov/FPDS.

Description

General construction basic ordering agreement. BOA will be used on an as needed basis for various construction projects, not to exceed $4M or 5 years, which ever comes first, with no express or written guarantee of work.

Task orders

Task order Ordering agency Obligated Awarded
Modification for electrical conduits to be added into existing order W911PT-12-G-0001-0019, for install of generator in… 0021 TACOM Life Cycle Management Command (AMC) $1,980
To cover the cost of labor, equipment and material for the plaster repair and change of occupancy repairs on the… 0020 TACOM Life Cycle Management Command (AMC) $221,446
To provide all labor, material, parts and equipment to construct a BBQ PIT behind building 41, watervliet arsenal, NY 0018 TACOM Life Cycle Management Command (AMC) $23,000
To provide all labor, material, parts and equipment to install electrical generator, benet lab building 115, watervliet… 0019 TACOM Life Cycle Management Command (AMC) $114,900
To cover the cost of labor, equipment and material for the replacement of broken window panes at the watervliet arsenal… 0017 TACOM Life Cycle Management Command (AMC) $8,435
Mori seiki foundat B-25 G5, WVA 0016 TACOM Life Cycle Management Command (AMC) $95,000
Procurement is for the material, labor and equipment for the pavilion renovation, building 52, at the watervliet… 0015 TACOM Life Cycle Management Command (AMC) $69,699
Level foundation floor, B-35 and B-20, WVA 0014 TACOM Life Cycle Management Command (AMC) $71,000
Install snow scaffolding, B-40 0013 TACOM Life Cycle Management Command (AMC) $46,055
To cover the cost of labor, material and equipment for install electrical service to chiller at building 115, benet… 0012 TACOM Life Cycle Management Command (AMC) $10,500
Clin 0001 bourn & koch foundation, B-35,B13,&clin 0002 remove old machine foundation, B-110, WVA clin 0003- fill… 0010 TACOM Life Cycle Management Command (AMC) $333,211
To cover the cost of labor, material and equipment for replacement of underground steam line between residential… 0011 TACOM Life Cycle Management Command (AMC) $177,266
FSC Z1AA: secure/door-renovate bldg 10 rooms 205 and 205A at the watervliet arsenal NY. 0009 TACOM Life Cycle Management Command (AMC) $48,319
FSC Z1AA: remodel/renovate B10-105 in building 10 at the watervliet arsenal NY. 0008 TACOM Life Cycle Management Command (AMC) $15,500
Installation of scaffolding to protect against falling snow and ICE at the watervliet arsenal. 0007 TACOM Life Cycle Management Command (AMC) $15,000
FSC: Z2FA repair replace ceiling, B-21 and bath, quarters 21 0006 TACOM Life Cycle Management Command (AMC) $42,452
FSC: Z2AC firehouse renovation, building 22, at watervliet arsenal 0005 TACOM Life Cycle Management Command (AMC) $70,077
Repair of quarter's one deck at the watervliet arsenal. 0004 TACOM Life Cycle Management Command (AMC) $41,678
To cover the cost of labor, equipment, and material for construction for 16' X 12' water meter PIT and reduced pressure… 0002 TACOM Life Cycle Management Command (AMC) $296,584
Delivery order issued to cover costs of repair/replacement of tile floors in bldgs 40-1 and 40-3 at the watervliet… 0003 TACOM Life Cycle Management Command (AMC) $30,561
Delivery order is issued to cover the cost of material and labor emergency repair of sanitary sewer pipe at building… 0001 TACOM Life Cycle Management Command (AMC) $45,210
Show all 21

Transactions

Action Obligated Date
Other Administrative Action P00006 · General construction BOA modification issued to correct end date. $0
Supplemental Agreement for work within scope P00005 · General construction BOA - modification to extend the POP $0
Supplemental Agreement for work within scope P00004 · MOD to add local clause general construction BOA $0
Supplemental Agreement for work within scope P00003 · General construction BOA $0
Supplemental Agreement for work within scope P00002 · To exercise option year 1 of general construction basic ordering agreement for various projects at the watervliet arsenal, NY 12189-4000 $0
Other Administrative Action P00001 · Extension of general construction basic ordering agreement per article V of base order at watervliet arsenal, NY. $0
Original award $0

Quick answers

Who was awarded contract W911PT12G0001?

W911PT12G0001 was awarded to Oddo Construction Services, LLC by TACOM Life Cycle Management Command (Army Materiel Command) on January 31, 2012.

How much is contract W911PT12G0001 worth?

Orders under W911PT12G0001 have obligated $1,777,873. A single order can be worth up to $4,000,000.

How many orders have been placed under contract W911PT12G0001?

21 orders have been placed under W911PT12G0001, the latest on December 27, 2016.

Who can order from contract W911PT12G0001?

W911PT12G0001 is a single award basic ordering agreement. Only the awarding agency can place orders on it.

On GovTribe

See this IDV's full record

  • Every order and transaction
  • The awardee's other awards and teaming partners
  • Similar IDVs and recompete opportunities
  • Ask GovTribe AI about this IDV