Project Grant 33000100822026
- Federal Grant Award Summary The Federal Aviation Administration (FAA) awarded a Project Grant of $5,629,956.84 to the Gallatin Airport Authority on August 6, 2025, under the Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs (CFDA 20.106). This Phase 2 construction grant funds critical airfield infrastructure improvements at Bozeman Yellowstone International Airport in Belgrade, Montana, to bring the facility into conformity with...
- Federal Grant Award Summary The Federal Aviation Administration (FAA) Northwest Mountain Region awarded $800,031.58 to the City of Billings, Montana on September 10, 2025, under the Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs (CFDA 20.106) to reconstruct terminal components at Billings Logan International Airport. This Phase 1 project funds design activities for a terminal renovation focused on improving passenger and baggage...
- Federal Grant Award Summary The Great Falls International Airport Authority received $559,183.16 in federal funding through the Department of Transportation Federal Aviation Administration (FAA) Airport Infrastructure Grants program (CFDA 20.117) for a terminal expansion project. Awarded on April 29, 2026, with completion scheduled for April 28, 2030, this project expands the existing terminal at Great Falls International Airport in Montana by 3,663 square feet to accommodate increased passenger...
- Federal Grant Award Summary The Montana Department of Transportation received a $1,354,746.32 project grant from the Federal Aviation Administration (FAA) under the Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs (CFDA 20.106), awarded on July 31, 2025. The grant funds Phase Seven of a terminal construction project at West Yellowstone Airport in Montana, representing approximately 5% of the vertical construction work. The project...
- The Department of Transportation Federal Aviation Administration (DOT FAA) awarded a $3,053,981.11 Project Grant under the Airport Improvement Program, COVID-19 Airports Programs, and Infrastructure Investment and Jobs Act Programs (CFDA 20.106) to the Gallatin Airport Authority, doing business as Gallatin Field Airport, on August 2, 2023. The grant funds a partial reimbursement for the completed expansion of the existing terminal building by 89,934 square feet to better accommodate existing...
- Federal Project Grant Award Summary The Federal Aviation Administration (FAA) awarded Flathead Municipal Airport Authority a Project Grant of $1,042,105.26 on May 12, 2025, under the Airport Improvement Program (AIP), Infrastructure Investment and Jobs Act (IIJA) Programs, and COVID-19 Airports Programs (CFDA 20.106). This grant provides partial funding for a terminal expansion project at Glacier Park International Airport in Kalispell, Montana, designed to expand the existing terminal...
- Federal Grant Award Summary The Federal Aviation Administration (FAA) Northwest Mountain Region awarded $4.44 million to Gallatin Airport Authority on June 24, 2026, under the Airport Improvement Program (CFDA 20.116) to construct two new commercial aprons at Bozeman's Gallatin Field Airport. The project deliverables consist of a 10,400 square-yard concrete commercial apron and a 13,500 square-yard asphalt commercial apron, totaling 23,900 square yards of new pavement infrastructure. These...
- Federal Grant Award Summary The Federal Aviation Administration (FAA) awarded Missoula County Airport Authority a Project Grant of $3,831,334.44 under the Airport Improvement Program (CFDA 20.106) on August 8, 2025, to fund Phase 14 of terminal construction at Missoula International Airport in Montana. Phase 14 encompasses the continuation and completion of critical infrastructure components including site civil utility installations, grading and pavement sections, structural steel erection,...
- Federal Grant Award Summary The Federal Aviation Administration (FAA) awarded Great Falls International Airport Authority a $1.14 million project grant under the Airport Improvement Program (CFDA 20.106) on September 18, 2025, to support Phase 2 construction activities for terminal reconstruction and expansion at Great Falls International Airport in Montana. This grant funds a portion of the eligible project costs, with an associated Airport Infrastructure Grant covering the remaining eligible...
- Federal Grant Award Summary The Federal Aviation Administration (FAA) awarded Great Falls International Airport Authority a $434,822.11 Project Grant on September 18, 2025, under the Airport Improvement Program (CFDA 20.106), which encompasses traditional Airport Improvement Program funding, Infrastructure Investment and Jobs Act (IIJA) appropriations, and COVID-19 relief initiatives. This Phase 1 award funds the design services for a terminal expansion and reconstruction project at Great...
The Federal Aviation Administration (FAA) Northwest Mountain Region awarded $12.1 million to the Gallatin Airport Authority under the Airport Terminal Program (CFDA 20.118) on July 13, 2026, to fund Phase 2 of a terminal expansion project at Bozeman Yellowstone International Airport in Belgrade, Montana. Phase 2 encompasses building interiors and systems installation for a 257,080-square-foot terminal expansion that includes three new gates, hold rooms, and expanded baggage handling areas. This expansion is designed to improve passenger and baggage flow while bringing airport infrastructure into conformance with current operational standards. The project carries a completion date of July 12, 2030. The Airport Terminal Program, established under the Infrastructure Investment and Jobs Act, provides competitive grant funding for reconstruction, rehabilitation, modernization, and expansion of airport terminal facilities nationwide. This award represents one component of a broader multi-phase terminal modernization initiative at Gallatin Field Airport, with Phase 1 engineering and site work previously funded at $10.5 million in May 2025. The grant recipient will be required to maintain detailed accounting records, submit periodic progress reports documenting contract awards and work completion, and retain project documentation for three years following the final expenditure report submission.Federal Grant Award Summary
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| Not listed | $11.5m | 7/13/26 |