Project Grant 30500260372026
- Federal Project Grant Award Summary The Federal Aviation Administration (FAA) Southwestern Region awarded Boone County Airport a $6.76 million project grant under the Airport Improvement Program (CFDA 20.106) on August 5, 2025, to construct a new 7,255 square foot passenger terminal building in Harrison, Arkansas. This grant funds Phase 2 of the terminal development project, with an ultimate completion date of August 4, 2029. The terminal construction will facilitate improved movement of...
- Federal Grant Award Summary On May 15, 2025, the Federal Aviation Administration (FAA) awarded Boone County Airport in Harrison, Arkansas, a Project Grant of $867,811.58 under the Airport Improvement Program, Infrastructure Investment and Jobs Act Programs, and COVID-19 Airports Programs (CFDA 20.106). The grant funds the construction of a new 7,000 square foot sponsor-owned aircraft storage hangar. This infrastructure improvement project is designed to enhance the airport's operational...
- Federal Grant Award Summary The Federal Aviation Administration (FAA) awarded Boone County Airport a Project Grant totaling $526,315.79 on June 6, 2025, under the Airport Improvement Program (CFDA 20.106) to reseal and resurface 6,161 linear feet of existing Runway 18/36 pavement at this non-primary airport in Harrison, Arkansas. This grant funds a portion of the total project cost, with an associated Airport Improvement Program grant covering the remaining eligible project expenses. The...
- Federal Grant Award Summary The Federal Aviation Administration (FAA) awarded Boone County Airport a Project Grant totaling $472,752.63 on July 23, 2025, under the Airport Improvement Program (CFDA 20.106). This grant funds a portion of a runway reseal and resurface project that will extend the useful life of 6,161 linear feet of existing Runway 18/36 pavement at this nonprimary airport located in Harrison, Arkansas. The project is scheduled for completion by July 22, 2029, and is supplemented...
- Federal Grant Award Summary The Federal Aviation Administration (FAA) awarded $159,486.32 to Carroll County Airport under the Airport Improvement Program (CFDA 20.116) on June 11, 2026, to construct a new 7,497-square-foot non-exclusive aircraft storage hangar. This facility is designed to enhance airport revenue generation and operational self-sustainability by providing additional tenant space for aircraft storage. The project represents one component of a paired funding structure, with this...
- Federal Grant Award Summary The Federal Aviation Administration (FAA) awarded $315,789.47 through the Airport Improvement Program (CFDA 20.116) to the City of Boone City Hall on July 14, 2026, for runway pavement preservation at Boone Municipal Airport. The grant funds a portion of a project to reseal and resurface 3,000 feet of existing Runway 15/33 pavement at the nonprimary airport to extend its useful life. This award is paired with complementary funding through an Infrastructure...
- Federal Grant Award Summary The Federal Aviation Administration (FAA) awarded $8.73 million to the Northwest Arkansas Regional Airport Authority on April 16, 2026, under the Airport Improvement Program (CFDA 20.116) to fund Phase 1 of a comprehensive northwest terminal apron reconstruction and expansion project. The grant supports reconstruction of 9,450 square yards of terminal apron pavement that has reached the end of its useful life, representing a portion of a larger coordinated project...
- Federal Project Grant Summary The Federal Aviation Administration (FAA), through the Airport Improvement Program (CFDA 20.106), awarded $615,748.42 to Carroll County Airport on August 19, 2025, for the construction of a new 7,350-square-foot sponsor-owned aircraft hangar at the Berryville, Arkansas airport. This project is designed to support aircraft storage and maintenance operations while enhancing the airport's revenue-generating capacity and long-term financial sustainability. The grant...
- Federal Project Grant Award Summary The City of Arkadelphia received a $303,143.16 Project Grant from the Federal Aviation Administration (FAA) Southwestern Region under the Airport Improvement Program (CFDA 20.106) on September 8, 2025, with a completion date of September 7, 2029. The grant funds the resealing and resurfacing of 5,002 linear feet of Runway 4/22 pavement at Arkadelphia Municipal Airport, a non-primary public-use airport. This infrastructure improvement project extends the useful...
- Federal Project Grant Award Summary On September 12, 2025, the Federal Aviation Administration (FAA) Southwestern Region awarded a Project Grant of $279,634.74 to Batesville Regional Airport under the Airport Improvement Program (CFDA 20.106) for infrastructure rehabilitation activities. This grant funds Phase 1 design services for two critical airfield pavement rehabilitation projects: the rehabilitation of 6,002 feet of existing paved Runway 8/26 and 6,100 feet of existing paved Taxiway A....
The Federal Aviation Administration (FAA) awarded Boone County Airport $398,390.53 under the Airport Improvement Program (CFDA 20.116) on July 7, 2026, to rehabilitate an existing 35,700 square foot nonrevenue-generating parking lot at the nonprimary airport in Harrison, Arkansas. The project, with an ultimate completion date of July 6, 2030, is designed to extend the useful life of the terminal parking facility through comprehensive rehabilitation efforts. This investment will benefit aviation infrastructure serving the Harrison, Arkansas area and support the airport's operational efficiency and capacity. The Airport Improvement Program funds airport infrastructure investments for public-use airports included in the National Plan of Integrated Airports Systems. This project aligns with the program's broader mission to preserve and maintain airport infrastructure, complementing Boone County Airport's recent history of federally-funded capital improvements totaling approximately $8.6 million since 2021, which have included terminal construction, runway resurfacing, and hangar development. Project completion is expected over approximately four years from the award date.Federal Project Grant Award Summary
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| Not listed | $378.5k | 7/7/26 |