Virginia Passenger Rail Authority UEI SKW7P8W12MA4
- Awarding agency
-
Federal Railroad Administration
Department of Transportation
- Obligated
- $70,000,000
Award facts
- Assistance listing
- 20.314 Railroad Development
- Completion date 7% complete
- Funding
-
- $56,000,000.00 Federal
- $14,000,000.00 Non-federal
- Place of performance
- Virginia, USA
Award details come from USAspending.gov.
About this award
The Department of Transportation's Federal Railroad Administration awarded the Virginia Passenger Rail Authority $70 million on September 25, 2026, under the Railroad Development program (Assistance Listing 20.314), to fund the Atlantic Gateway Arlington to Alexandria Fourth Track Project. The award will build approximately six miles of new fourth track on the CSX RF&P Subdivision within the existing right-of-way in Arlington County and the City of Alexandria, Virginia, with the existing tracks shifted to make room. It also includes improvements to the three existing mainline tracks to accommodate the new track, as defined in the DC2RVA project. The award's stated purpose notes $56 million in CMAQ funding. Deliverables are an updated project management plan, a final performance report, a complete set of as-built drawings, and a project outcomes report. The project is intended to benefit the traveling public by supporting increased passenger rail service and improving air quality, with Amtrak and VRE passengers, rail operators, and communities across Northern Virginia named as beneficiaries. Ultimate completion is January 31, 2029. The award lists no sub-recipients.
Description
- Purpose
- The purpose of this award ($56M cmaq) is to provide federal assitance to vpra for the atlantic gateway, arlington to alexandria fourth track project. The project will increase rail capacity by constructing approx. 6 miles of new track along the CSX richmond, fredericksburg, and potomac subdivision in arlington county and the city of alexandria. 2.
- Activities
- The project will include the construction of approximately six miles of new fourth track on the CSX (RF P) subdivision. The existing tracks will be shifted, and a new fourth track will be added, within the existing right-of-way. The project also includes improvements to the three existing mainline tracks to accommodate the new track as defined in the DC2RVA project. 3. Deliverables expected outcomes: updated PMP, final performance report, and a complete set of as-built drawings, and project outcomes report. 4. Intended beneficiary: the project is intended to benefit the traveling public by supporting increased passenger rail service and help improve air-quality. This project will also positively impact amtrak and VRE passengers and rail operators as well as the communities served throughout northern virginia. 5. Sub-recipient activities: N a
Quick answers
Who received award 69A36526420030RLDVA?
69A36526420030RLDVA was awarded to Virginia Passenger Rail Authority by Federal Railroad Administration (Department of Transportation) on September 25, 2026.
How much is award 69A36526420030RLDVA worth?
$70,000,000 has been obligated on 69A36526420030RLDVA: $56,000,000 in federal funding and $14,000,000 in non-federal funding.