Bipartisan infrastructure law (BIL) - preventing outages and enhancing the resilience of the electric grid formula grants to states and indian tribes

Active Formula Grant Awarded Last action

Award ID
DEGD0000013
Recipient
Awarding agency
Obligated
$16,792,381

Award facts

Completion date 38% complete
Originally
Funding
  • $14,602,071.00 Federal
  • $2,190,310.00 Non-federal
Funding agency
Department of Energy
Place of performance
Boise, ID 83720, USA

Award details come from USAspending.gov.

Description

The overall objective of this project is to improve the resilience of the electric grid against disruptive events.

Transactions

Action Federal Non-federal Date
Amendment $5,345,482 $2,190,310
Amendment $0 $0
Original award $9,256,589 $0

Subawards

Subrecipient Amount Awarded
Kootenai Electric Cooperative, Inc. Activity 1: Vegetation Analysis Contract with a vendor to use satellite imagery and AI to identify dead and dying trees near power lines in high‑fire‑risk… $423,031
Fall River Rural Electric Cooperative, Inc. Activity 1: Replace 1.77 miles of old overhead power lines with new underground cables in Fremont County. Activity 2: Replace 1.45 miles of old overhead power… $470,178
Raft River Rural Electric Cooperative Inc. Activity 1: Replace 32 relaying and overcurrent protection devices. Activity 2: Upgrade a total of 35 downstream reclosers in Cassia County, including 21 new… $998,581
United Electric Co-Op, Inc. Activity 1: Installation of 16 reclosers with control cabinets, communication equipment (e.g., RTACs, switches), and system integration across six… $1,026,851
Inland Power & Light CO. Activity 1: Install eight (8) single-phase advanced reclosers with modern controls and twelve (12) three-phase advanced reclosers with modern controls in… $417,614
Northern Lights Inc. Activity 1: Replace fifty (50) wooden sub-transmission poles with ductile iron poles along Eastriver Road, south of Priest Lake, in Bonner County. Activity 2:… $811,413
Idaho Power Company Converting three-line miles of of overhead powerlines to underground construction and hardening/rebuilding of at least two line miles of overhead facilities. $2,000,000
Clearwater Power Company The purpose of the project is to enhance grid resilience by improving the reliability of two key substations that serve the Dworshak National Fish Hatchery, the… $349,864
City Of Idaho Falls Activity 1: Underground power lines in each of the Idaho Falls downtown A Street alley, totaling at least 2,500 feet when combined with Activities 2 and 3. This… $1,300,000
Lower Valley Energy, Inc. Activity 1: Install new underground line near the Calamity Campground in an area also referred to as the “Calamity area” in Bonneville County. Remove old… $625,816
Fall River Rural Electric Cooperative, Inc. Activity 1: Move at least 1 mile of distribution power lines underground in the Caribou-Targhee National Forest near Fransen Mill that will service at least… $439,157
Northern Lights Inc. Convert at least 33,000 feet of existing overhead power line to new single phase underground powerline, and transition services to businesses and homes from… $1,543,542
Clearwater Power Company Contract with a vendor that uses satellites and AI to scan the vegetation conditions surrounding Clearwater Power’s Right-of-Way (ROW) in high-fire-risk areas… $2,000,000
Show all 13

Quick answers

Who received award DEGD0000013?

DEGD0000013 was awarded to Executive Office Of The State Of Idaho by National Energy Technology Lab (Department of Energy) on June 6, 2023.

How much is award DEGD0000013 worth?

$16,792,381 has been obligated on DEGD0000013: $14,602,071 in federal funding and $2,190,310 in non-federal funding.

Which agency awarded DEGD0000013?

National Energy Technology Lab (Department of Energy) awarded DEGD0000013, with funding from Department of Energy.