Bechtel national, incorporated project: front-end engineering design (feed) study for a carbon capture plant retrofit to a natural gas-fired gas turbine combined cycle power plant

Ended Cooperative Agreement Awarded Last action

Award ID
DEFE0031848
Recipient
Awarding agency
Obligated
$1,470,765

Award facts

Assistance listing
81.089 Fossil Energy Research and Development
Completion date
Originally
Funding
  • $1,151,152.43 Federal
  • $319,613.00 Non-federal
Funding agency
Office of Fossil Energy Department of Energy
Place of performance
Reston, VA 20190, USA

Award details come from USAspending.gov.

Transactions

Action Federal Non-federal Date
Amendment Feed study for a carbon capture plant retrofit to a natural gas-fired gas turbine combined cycle power plant. -$82,071 $0
Amendment $0 $0
Amendment $0 $0
Amendment $0 $0
Amendment $0 $0
Amendment Bechtel national, incorporated project - front-end engineering design $0 $0
Amendment $233,223 $0
Amendment $0 $11,307
Original award $1,000,000 $308,306

Quick answers

Who received award DEFE0031848?

DEFE0031848 was awarded to Bechtel National, Inc. by National Energy Technology Lab (Department of Energy) on October 1, 2019.

How much is award DEFE0031848 worth?

$1,470,765 has been obligated on DEFE0031848: $1,151,152 in federal funding and $319,613 in non-federal funding.

Which agency awarded DEFE0031848?

National Energy Technology Lab (Department of Energy) awarded DEFE0031848, with funding from Office of Fossil Energy (Department of Energy).

On GovTribe

See this award's full record

  • Every transaction and subaward
  • The recipient's other awards and teaming partners
  • Similar grant awards
  • Ask GovTribe AI about this award