This agreement provides funding to the university of new orleans research and technology foundation (UNORTF) to support the lake pontchartrain basin restoration program which maintains, protects and…

Ended Cooperative Agreement Awarded Last action

Award ID
01F84101
Recipient
Awarding agency
Obligated
$3,068,031

Award facts

Completion date
Originally
Funding
  • $2,388,000.00 Federal
  • $680,031.00 Non-federal
Place of performance
Louisiana, USA

Award details come from USAspending.gov.

Description

This agreement provides funding to the university of new orleans research and technology foundation (UNORTF) to support the lake pontchartrain basin restoration program which maintains, protects and restores the water quality of the lake pontchartrain basin. UNORTF will oversee projects to monitor the lake's water quality and determine the health of the watershed, develop green infrastructure municipal education, educate basin residents on water protection and pollution prevention, conduct sewer system evaluations and surveys, and develop designs and studies to determine infrastructure upgrades to prevent or reduce pollution.

Transactions

Action Federal Non-federal Date
Amendment $0 $0
Amendment Activities:.subrecipient:outcomes:. $0 $0
Amendment $1,441,000 $680,031
Original award $947,000 $0

Subawards

Subrecipient Amount Awarded
Jefferson Parish Government The objective of this project is to rehabilitate Lift Station F7-13 located north of Canal No. 3 on the corner of Veterans and Neyrey, to eliminate SSOs. This… $44,000
Town Of Madisonville The proposed corrective action is to rehabilitate or reconstruct sections of lines in the existing sewer infrastructure in the critical areas of the Town. A… $136,500
ST. John The Baptist Parish Council The project goals and objectives are to prepare design plans and specifications to upgrade Central Lift Station capacity to pump wet weather flow from its… $29,525
City Of Slidell The project goal is to prepare a plan to smoke test approximately 37,816 linear feet of gravity sewer main and identify inflow connections to the san¡tary… $39,550
ST. Bernard Parish Government The goal of the project is to creat a prioritized plan of action the will: (1) Reduce stormwater inflow into the wastewater collection system during wet weather… $35,000
Pontchartrain Conservancy Task 1 – WQ Weekly Recreational Water Monitoring Water quality monitoring is conducted at 12 sites across the Lake Pontchartrain Basin. Sampling sites… $342,970
City Of Mandeville The project goal and objective are to prepare design plans and specifications for public bid for the Upgrades to Sewer Lift Stations No. 3 and 39. Upgrading the… $41,500
ST Charles Parish The goal of the proposed project is to allow St. Charles Parish to complete the design plans and specifications to improve and upgrade three lift stations… $70,000
Jefferson Parish Government Projects that are implemented through the Ecosystem and Coastal Management need to align with the Jefferson Parish Coastal Strategic Action Plan… $77,000
ST. John The Baptist Parish Council The goal of the project is to create a prioritized plan of action that will reduce stormwater inflow into the wastewater collection system during wet weather… $34,000
City Of Kenner The project goal and objective is to prepare design plans and specifications for public bid for the improvements to the 42nd & Lake Trail and 31st & Loyola… $33,040
Jefferson Parish Government The goal of the project is to promote and cultivate a community urban gardening initiative within Jefferson Parish. Local industry leaders will be engaged for… $18,000
ST. Bernard Parish Government The overall goal of this project is to design upgrades to the existing Walkers Lane Sewer Lift Station and Force Main. These upgrades will consist of increasing… $40,000
Jefferson Parish Government The objective of this project is to rehabilitate Lift Station D4-7 located near the Suave Rd Canal Crossing at the Soniat Canal, to eliminate SSOs. This will be… $41,146
ST Tammany Parish Government Within the 25 unsewered subdivisions in the Bayou Bonfouca Watershed, there are estimated to be more than 649 residences that have septic tanks or Aerated… $82,360
City Of Hammond The goal of this project aligns with Strategy 1: infíltration/inflow (l/l) correction to ensure the ¡ntegrity of Hammond's collection… $55,000
City Of New Orleans The goal of the project is to design a permeable parking lot for Lincoln Beach. The objective is to have bid-ready construction documents that the City of New… $41,230
City Of Mandeville The project goal and objectíve are to prepare design plans and specifications for public bid for the upgrades to Sewer Lift Stations No. 42 and 43. Upgrading… $37,230
City Of Hammond The goal of this project aligns with Strategy 1: ínfiltration/inflow (l/l) correction to ensure the integrity of Hammond's collection system-specifically… $105,000
City Of Walker New City Hall With the population of the City exceeding 6000, and many of those being on the public sewer system with more to come, it is important to reduce the amount of… $50,565
Tangipahoa Parish Council The project will help identify large land parcels that can be used for stormwater retention and prepare design modifications and cost estimates for at least 3… $69,720
Town Of Madisonville The proposed corrective action is to rehabilitate or reconstruct sections of lines of the existing sewer infrastructure in the critical areas of the Town. A… $67,100
ST Bernard Parish Goverment The goals of this project are to establish a baseline dry weather wastewater flow within the Fazendville, Munster and Violet/Riverbend wastewater collection… $61,000
ST Tammany Parish Government Complete review of existing ordinances for construction developments, amend as required existing codes or ordinances or other construction requirements to… $30,500
ST. John The Baptist Parish Council The project goals and objectives are to prepare design plans and specifications for a new sewer force main extension connection that will connect the River Road… $71,985
Pontchartrain Conservancy Eight (8) needs in the Lake Pontchartrain Basin Comprehensive Management Plan (CMP) and three (3) needs in the Comprehensive Habitat Management Program (CHMP)… $2,367,600
ST. John The Baptist Parish Council The goal of this project is to collect wet weather storm water quality data that the Parish can use to identify areas that may be contributing excess pollutants… $23,325
City Of Slidell The project goal and objective is to prepare design plans and specifications for public bid for the PS 200 Lindberg Sewer Lift Station Upgrades project. The… $43,310
City Of Kenner The project goal and objective is to prepare design plans and specifications for public bid for the St. Jude Sewer Lift Station Upgrades project. Upgrading… $44,225
Jefferson, Parish Of The objective of the project is to rehabilitate Lift Station E8-1 located at Transcontinental and Belle, to reduce the risk of SSO's. This will be achieved by… $25,825
Jefferson Parish Government The Southshore of Lake Pontchartrain in Jefferson Parish includes the Hurricane Storm Damage Risk Reduction System (HSDRRS), which includes miles of levees that… $35,375
Jefferson, Parish Of The goal of the project is to complete an audit of the Parish's existing codes and ordinances pertaining to clearing & grubbing and sediment erosion control,… $18,000
City Of Hammond The goal of this project aligns with Strategy 3: ensuring the uninterrupted operation of lift stations during power failures and prolonged power… $47,580
Show all 33

Quick answers

Who received award 01F84101?

01F84101 was awarded to University Of New Orleans Research And Technology Foundation, Inc. by EPA Region 6 (Regional Offices) on July 14, 2020.

How much is award 01F84101 worth?

$3,068,031 has been obligated on 01F84101: $2,388,000 in federal funding and $680,031 in non-federal funding.

On GovTribe

See this award's full record

  • Every transaction and subaward
  • The recipient's other awards and teaming partners
  • Similar grant awards
  • Ask GovTribe AI about this award