Purchase Order W912P920P0048
Award Date 5/20/20
Potential Completion Date 1/17/21
Potential Value $227K
Funding Federal Agency
Contracting Federal Agency
Awardee
Ultimate Awardee
Not listed NAICS Category
PSC Category
Set-Aside Type
Total Small Business
Federal Contract Vehicle
- Not listed
Extent Competed
Competed under SAP
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
East Alton, IL, USA
Solicitation Procedures
Simplified Acquisition
Number Of Offers Received
4
Legislative Mandate
Service Contract Act
National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- <p>This is a firm fixed-price purchase order contract awarded by the Department of the Army Corps of Engineers Engineering District St Louis to Adgo Inc., a self-certified small disadvantaged, veteran-owned manufacturer, for FY18 L24/L25 PLC UPGRADES / PHASE 1 LD25. The contract has a potential value of $846,126.90 and a completion date of August 5, 2022. It was set aside for total small business participation.</p>
- This is a $157,000 firm fixed price purchase order awarded by the U.S. Army Corps of Engineers to Frontline Engineering Inc., a minority-owned, veteran-owned, and Black American-owned small business, for the installation and programming of programmable logic controller (PLC) units on the Dredge Goetz. The contract is set aside for small businesses and has an ultimate completion date of April 15, 2024. The original solicitation sought to procure, install, program, commission, and test the PLC...
- The U.S. Army Corps of Engineers, Rock Island District awarded a $676,186.10 Firm Fixed Price contract to Manufacturing Maintenance Solutions, Inc. to upgrade the Programmable Logic Controller (PLC) system at the Peoria Lock and Dam. The contract was awarded on September 28, 2023 and has an ultimate completion date of September 30, 2024. The contract was not set aside for any specific business type. The work involves replacing the existing PLC hardware and software, upgrading Human-Machine...
- This contract award is for the provision of additional handrail components for the LaGrange Lock and Dam, Peoria Lock and Dam, and Brandon Road Lock and Dam located in Illinois. The contract was awarded on a sole source basis under the 8(a) program to Supplied Industrial Solutions Inc., a veteran-owned, Small Disadvantaged Business (SDB) and 8(a) participant. The firm fixed price contract has a potential value of $120,644.97 and was issued by the U.S. Army Corps of Engineers, Engineering...
- The Department of the Army Corps of Engineers awarded a $279,475 firm fixed price purchase order to M Wilkinson Construction Company of West Alton, Missouri. This contract is for fence line protection work along the River's Project in support of the Corps' civil works mission. The solicitation sought technical support and software maintenance services for Allen-Bradley and Rockwell Automation products used across multiple Corps districts in Illinois. The awarded contract provides 24/7 online and...
- <p>The US Army Corps of Engineers awarded an $684,630.50 definitive contract to Gwo, Inc. for Illinois Waterway Lockport dewatering supplies on January 29, 2026, under an 8(a) sole-source set-aside.</p> <p>Gwo, Inc. is an SBA-certified economically disadvantaged women-owned small business and 8(a) program participant. Place of performance is Lockport, IL. The contract carries a firm fixed price and concludes on June 22, 2026.</p>
- The Department of the Army Corps of Engineers awarded a $366,199.76 firm fixed price purchase order to Southern Supply Company, doing business as SMC Electric Supply, to deliver programmable logic controllers and supporting hardware and software. The prime contractor will provide three Allen Bradley Contrologix 1769 programmable logic controllers along with over 200 supporting modules, interfaces, cables and software to the specified location in Branson, Missouri by September 30, 2020 in...
- This is a $114,315.42 firm fixed-price contract awarded by the U.S. Army Corps of Engineers to ESI Acquisition Corporation, Engineered Sales Division, for a winch control system for the Peoria and LaGrange Lock & Dam on the Illinois Waterway. The contract was set aside for small businesses. ESI Acquisition Corporation is a subsidiary of the industrial distributor Applied Industrial Technologies, Inc. The contract involves the delivery of specialized hydraulic components and fluid power...
- The Army Corps of Engineers Engineering and Support Center issued a delivery order to Addon Services LLC on September 30, 2024, with a ceiling value of $8,074,118.82 for construction of a new maintenance building with administrative area at Lock 27 in Granite City, Illinois, under firm fixed-price terms. Ultimate completion is May 14, 2027. Place of performance is Mitchell, Illinois. The order includes a supplemental agreement to add an overhead door and fire water supply change to contract...
- The U.S. Army Corps of Engineers awarded a $2.1 million firm fixed-price definitive contract to Alberici Constructors Inc. for infrastructure improvements at Alton, Illinois. The project encompasses construction of a main lock and auxiliary lock, a dam featuring nine Tainter gates, and a fixed submersible dike extending to the Missouri side of the river. The contract carries an ultimate completion date of February 20, 2027, and represents open competitive contracting with no set-aside...
The Department of the Army Corps of Engineers awarded a Firm Fixed Price purchase order contract to Adgo Inc., a self-certified small disadvantaged, veteran-owned manufacturer, for $227,122.03 to provide PLC (Programmable Logic Controller) upgrades at Locks 27 in East Alton, Illinois. This contract was set aside for small businesses and originated from a total small business solicitation for brand name PLC replacement and migration at the Locks 27 facility. The contract has a completion date of January 17, 2021.
Generated 3/23/24, 1:05 PM
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
PLC Upgrades - Locks 27 - Rivers Project Office | W912P920R0043 | Department of the Army Corps of Engineers Engineering District St Louis | Solicitation 1/1 | 4/9/20, 3:46 PM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| P00001 | Supplemental Agreement for work within scope | ($5k) | 7/1/20 | |
| Not listed | Not listed | $232.4k | 5/20/20 |