Purchase Order AG24H8P110073
Award Date 9/28/11
Potential Completion Date 12/6/11
Potential Value $10K
Federal Agency
Ultimate Awardee
Not listed NAICS Category
PSC Category
Not listed Federal Contract Vehicle
- Not listed
Set-Aside Type
No Set-Aside Used
Extent Competed
Not Competed under SAP
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
Rutland, VT 05701, USA
Solicitation Procedures
Simplified Acquisition
Number Of Offers Received
1
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- The USDA Forest Service, Region 9, issued a purchase order to Harveys Excavating, LLC on May 15, 2026, for reconstruction of Forest Road 42C on the Green Mountain National Forest, with a ceiling value of $41,142.50. The order is set aside for total small business. Work is performed in Rochester, Vermont, and includes roadway reconstruction, rock excavation, clearing and grubbing, bank armoring, linear grading, and installation of drainage structures under NAICS 237310. The order is firm fixed...
- This is a $637,888.84 definitive, firm-fixed-price contract awarded by the U.S. Department of Agriculture (USDA) Forest Service, Region 9 - Eastern Region, to Birdseye Building Co, a small business, for the replacement of a culvert on Forest Road 59-4.9 in the Green Mountain National Forest in Ripton, Vermont. The contract work includes excavation, removal of the existing culvert, installation of a government-furnished plate arch culvert, construction of concrete substructures and stream...
- This is a firm fixed-price contract awarded by the U.S. Department of Agriculture Forest Service to Neil H. Daniels, Inc., a small business concern, for the replacement of two culverts on Forest Road 10 in the Green Mountain National Forest in Vermont. The contract, valued at $1,307,180.00, includes the removal of existing structures and the installation of new metal and precast culverts, as well as associated site work such as backfilling, embankment construction, and guardrail installation....
- This is a $637,675 firm-fixed price contract awarded by the U.S. Forest Service, a component of the U.S. Department of Agriculture, to Hunter Excavating, Inc., a small business contractor, for culvert replacement services in the Green Mountain National Forest in Vermont. The contract has a total small business set-aside designation under NAICS code 237310. The work includes excavation, removal of existing culverts, installation of new precast culverts, associated backfill and embankment...
- Harveys Plumbing And Excavating, LLC was awarded a $6,640.36 firm fixed-price delivery order against the Department of Agriculture Forest Service's Green Mountain NF General Construction IDIQ contract number 12168119D0003. The delivery order is to provide emergency flood repair services for damage from the August 4, 2023 weather event on GMFL, as part of the Forest Service's Eastern Region program to address construction needs. Funding is provided by the USDA Forest Service R9-Eastern Region....
- This is a firm fixed price delivery order contract awarded to Harveys Plumbing And Excavating, LLC, a small business, by the U.S. Forest Service's Eastern Region office. The contract is for culvert replacement and road improvement work on the north half of the Green Mountain National Forest (GMNF) in Vermont, with a ceiling value of $39,824.60 and a completion date of October 7, 2015. The contract was set aside for total small business participation. Harveys Plumbing And Excavating has held...
- This is a delivery order awarded by the U.S. Forest Service under the ARRA-FS-CIM (American Recovery and Reinvestment Act - Forest Service - Capital Improvement & Maintenance) program. The contract is for a road resurfacing project on the Green Mountain National Forest in Vermont, with a ceiling value of $25,297.50. The prime contractor is Champlain Construction Company, Inc., a for-profit Subchapter S Corporation. The contract is a firm fixed-price delivery order, with a period of...
- The U.S. Department of Agriculture Forest Service awarded a $98,117.80 firm fixed price delivery order contract to Jack Bowen Excavating of Mt Tabor, Vermont. The contract calls for the replacement of an existing five-foot diameter culvert with a new seven-foot, three-inch wide by five-foot, three-inch high by seventy-eight-foot long aluminized steel pipe arch culvert. Additional work includes removal of an existing temporary bridge and its relocation. The contract was awarded on April 26,...
- The Department of Agriculture Forest Service awarded a $429,400 firm fixed-price contract to Renaud Bros., Inc. doing business as Renaud Brothers Inc. to replace Bridge 10-6.9 located on Forest Route 10-6.9 in the Green Mountain National Forest in Rutland County, Vermont. The solicitation sought proposals to demolish the existing bridge and construct a new cast-in-place concrete bridge with precast concrete slabs, timber railings, and site work. The contract is set aside for total small business...
- <p>This is a firm fixed-price purchase order awarded by the U.S. Department of Agriculture, Forest Service to Ferncroft Property Services, LLC (doing business as Kurtz Excavating) for the repair of a scoured abutment under a 22-foot span, bottomless arch culvert on the Manchester Ranger District in Vermont. The contract, valued at $67,200.00, is funded through the Great American Outdoors Act and has a total small business set-aside. The work is required to be completed by October 30, 2026.</p>
FR72 RED MILL EMERGENCY CULVERT BACKFILL - TROPICAL STORM IRENE RECOVERY. GREEN MOUNTAIN NATIONAL FOREST.
Posted 9/28/11
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| 1 | Close Out | ($50) | 12/6/11 | |
| Not listed | Not listed | $10.0k | 9/28/11 |