Arra::yes::arra construction of new albany, silver creek to 18TH street trailhead and kentucky & indiana railroad connector, ohio river greenway project, new albany, in

Ended Awarded Last action

Contract number
0008
Awardee
Awarding agency
Obligated
$1,715,373

Award facts

Contract value 263% obligated
$651,583.05 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Set-aside
HUBZone
Competition
Full and Open Competition after exclusion of sources · 5 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
New Albany, IN 47150, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope 1P · Arra::yes::arra case 0014 equitble adjustment for handrails, quarried block and electrical distribution and lighting fixtures, ohio river greenway, new… $0
Supplemental Agreement for work within scope 1P · Case 0014 equitble adjustment for handrails, quarried block and electrical distribution and lighting fixtures, ohio river greenway, new albany, in $77,000
Other Administrative Action 1 · Administrative modification to change company physical and remittance addresses, ohio river greenway project, new albany, in $0
Other Administrative Action 1 · Arra::yes::arra administrative modification to change company physical and remittance addresses, ohio river greenway project, new albany, in $0
Change Order 1N · Ohio river greenway new albany, in $1,615
Change Order 1N · Arra ohio river greenway new albany, in $0
Supplemental Agreement for work within scope 1M · Arra::yes::arra case 005 delete fabrication of 7-rung handrail and install 3-rung handrail, ohio river greenway project, silver creek to 18TH street trailhead… $0
Supplemental Agreement for work within scope 1M · Case 005 delete fabrication of 7-rung handrail and install 3-rung handrail, ohio river greenway project, silver creek to 18TH street trailhead and kentucky &… -$57,532
Supplemental Agreement for work within scope 1L · Arra::yes::arra case 010 complete road transition, incorporating 350 cubic yards of unsuitable material excavated at project to be used as interior fill,… $87,872
Supplemental Agreement for work within scope 1L · Case 010 complete road transition, incorporating 350 cubic yards of unsuitable material excavated at project to be used as interior fill, proof rolling material… $0
Supplemental Agreement for work within scope 1K · Arra::yes::arra case 0012 time extension due to weather delays, ohio river greenway project, new albany, in $0
Supplemental Agreement for work within scope 1K · Case 0012 time extension due to weather delays, ohio river greenway project, new albany, in $0
Supplemental Agreement for work within scope 1J · Case 011 time extension due to weather delay, construction of new albany, silver creek to 18TH street trailhead & k&i connector, ohio river greenway, new… $0
Supplemental Agreement for work within scope 1J · Arra::yes::arra case 011 time extension due to weather delay, construction of new albany, silver creek to 18TH street trailhead & k&i connector, ohio river… $0
Supplemental Agreement for work within scope 1H · Case 0009 time extension due to weather delays from FEB. 2011 through APR. 2011, ohio river greenway, new albany segment, ohio river, new albany, in $0
Supplemental Agreement for work within scope 1H · Arra::yes::arra case 0009 time extension due to weather delays from FEB. 2011 through APR. 2011, ohio river greenway, new albany segment, ohio river, new… $0
Change Order 1G · Case 008 delete overhead wiring and associated poles from existing utility power pole, relocate service point #2 to base of floodwall, provide new rigid… $0
Change Order 1G · Arra::yes::arra case 008 delete overhead wiring and associated poles from existing utility power pole, relocate service point #2 to base of floodwall, provide… $150
Change Order 1F · Ohio river greenway new albany, in $0
Change Order 1F · Arra ohio river greenway new albany, in arra "mods only" f/o FKDF48 96931340000 082437 3230FKDF48013151 $0
Change Order 1E · Ohio river greenway new albany, in $16,500
Change Order 1E · Arra ohio river greenway new albany, in $0
Change Order 1D · Case 008 delete overhead wiring and associated poles and convert to buried electrical, part i notice to proceed, ohio river greenway new albany, in $0
Change Order 1D · Arra::yes::arra case 008 delete overhead wiring and associated poles and convert to buried electrical, part i notice to proceed, ohio river greenway new albany,… $4,000
Supplemental Agreement for work within scope 1C · Case 001 excavate trail over existing pump station pipes, add concrete and neoprene cap over pipes, adjust upper limestone wall and reduce overall height,… $0
Supplemental Agreement for work within scope 1C · Arra::yes::arra case 001 excavate trail over existing pump station pipes, add concrete and neoprene cap over pipes, adjust upper limestone wall and reduce… $33,368
Change Order 1B · Case 006 excavate existing levee trench 1.5' deeper and replace with clean fill, compact and use excavated material for slope of adjacent trail, part i notice… $0
Change Order 1B · Arra::yes::arra case 006 excavate existing levee trench 1.5' deeper and replace with clean fill, compact and use excavated material for slope of adjacent trail,… $2,400
Supplemental Agreement for work within scope 1A · Arra::yes::arra case 00002 time extension due to weather delays, ohio river greenway - new albany segment, new albany, in $0
Supplemental Agreement for work within scope 1A · Case 00002 time extension due to weather delays, ohio river greenway - new albany segment, new albany, in $0
Modification Construction of new albany, silver creek to 18TH street trailhead and k & i connector, ohio river greenway project, new albany, in $614,000
Original award $936,000
Show all 32

About this award

This is a firm fixed-price delivery order contract awarded by the U.S. Army Corps of Engineers (USACE) Louisville District to TJC Engineering, Inc., a HUBZone small business. The contract is for the construction of the New Albany, Silver Creek to 18th Street Trailhead and Kentucky & Indiana Railroad Connector as part of the Ohio River Greenway Project in New Albany, Indiana. The contract has a ceiling value of $651,583.05 and a period of performance that runs through August 31, 2012. This contract is funded through the American Recovery and Reinvestment Act (ARRA).

Quick answers

Who was awarded contract 0008?

0008 was awarded to TJC Engineering, Inc. by ENDIST Louisville (US Army Corps of Engineers) on July 30, 2010.

How much is contract 0008 worth?

The government has obligated $1,715,373 on 0008. Its current value, with exercised options, is $651,583.

Is contract 0008 an order under another contract?

Yes. 0008 is a delivery order under W912QR09D0019, an indefinite delivery contract.

Was contract 0008 competed?

The extent of competition for 0008 was full and open competition after exclusion of sources. The government received 5 offers. It was set aside: HUBZone.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award