Construct "warrior in transition" headquarters building, FT. Knox, KY

Ended Awarded Last action

Contract number
0012
Awardee
Awarding agency
Obligated
$2,709,156

Award facts

Contract value 100% obligated
$2,709,155.68 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
Set-aside
HUBZone
Competition
Full and Open Competition after exclusion of sources · 5 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Fort Knox, KY 40121, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Change Order 1M · Case 0015, credit for missing leed silver certification, warriors in transition s/HQ building, FT. Knox, KY -$3,125
Supplemental Agreement for work within scope 1L · Case 014 remove concrete from trane raceway, warrior in transition small company headquarters building, FT. Knox, KY $6,225
Supplemental Agreement for work within scope 1K · Case 0013 termination of fiber optic cable contract -WIT s/HQ building non-arra $4,308
Supplemental Agreement for work within scope 1J · Case 0012 time extension due to weather delays, warrior in transition small company headquarters building, FT. Knox, KY $0
Supplemental Agreement for work within scope 1H · Case 011 install raceway from utility pole to communications room, warrior in transition small company headquarters building, FT. Knox, KY $16,006
Supplemental Agreement for work within scope 1G · Case 0010 weather time extension, warrior in transition small company headquarters, FT. Knox, KY $0
Supplemental Agreement for work within scope 1F · Case 0009 conference room projector screen, warrior in transition small company headquarters building, FT. Knox, KY $3,378
Supplemental Agreement for work within scope 1E · Case 0008 - weather time extensioncontract -WIT s/HQ building non-arra $0
Supplemental Agreement for work within scope 1D · Case 1 install 5'wide concrete sidewalk parallel to road; saw cut existing curb and install sloped transitions; seed/straw all disturbed ground and new graded… $13,419
Supplemental Agreement for work within scope 1C · Case 6 unsuitable soils in parking lot - excavate and backfill 5 areas, warrior in transition small company headquarters building, FT. Knox, KY $10,826
Change Order 1B · Case 0004 - time weather extension contract -WIT s/HQ building non-arra $0
Supplemental Agreement for work within scope 1A · Case 0002 remove concrete footings from GEO trench; case 0003 remove and replace unsuitable soils under footers, warrior in transition small company… $43,231
Original award $2,614,888
Show all 13

About this award

This is a delivery order contract awarded by the U.S. Army Corps of Engineers (USACE) Louisville District to Intersteel, Inc., a Small Business Administration (SBA) certified HUBZone firm, to construct a "Warrior in Transition" headquarters building at Fort Knox, Kentucky. The contract has a firm fixed price of $2,709,155.68 and a completion date of May 12, 2014. The contract was set aside for HUBZone small businesses.

Quick answers

Who was awarded contract 0012?

0012 was awarded to Intersteel, Inc. by ENDIST Louisville (US Army Corps of Engineers) on August 28, 2012.

How much is contract 0012 worth?

The government has obligated $2,709,156 on 0012.

Is contract 0012 an order under another contract?

Yes. 0012 is a delivery order under W912QR09D0016, an indefinite delivery contract.

Was contract 0012 competed?

The extent of competition for 0012 was full and open competition after exclusion of sources. The government received 5 offers. It was set aside: HUBZone.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award