Delivery Order W912P914D0501-W912P918F0402
Award Date 9/26/18
Potential Completion Date 9/30/19
Potential Value $210K
Federal Agency
Ultimate Awardee
Not listed NAICS Category
Federal Contract Vehicle
- Not listed
Set-Aside Type
No Set-Aside Used
Extent Competed
Full and Open Competition after exclusion of sources
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
West Alton, MO 63386, USA
Solicitation Procedures
Negotiated Proposal / Quote
Number Of Offers Received
Not listed
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- <p>This is a $144,356.99 firm fixed-price delivery order contract awarded by the U.S. Army Corps of Engineers Engineering District St. Louis to Widman Construction Inc., a for-profit organization, for the Upper River Land Repair & Floating Plant project. The contract has a completion date of September 30, 2018 and is not associated with a set-aside program. The contract requires the performance of work in West Alton, Missouri.</p>
- The Department of the Army Corps of Engineers Engineering District St Louis awarded a Firm Fixed Price Delivery Order contract to Widman Construction Inc. for the "LD 24 SCOUR REPAIR" project. The contract, which does not have a set-aside designation, has a potential value of $179,466.16 and a completion date of June 30, 2018. The project is located in West Alton, Missouri. Widman Construction Inc. is a for-profit organization that will be delivering the requested products and services...
- <p>This is a federal contract award made by the U.S. Department of the Army Corps of Engineers Engineering District St Louis to Widman Construction Inc., a for-profit organization, on June 22, 2018. The contract, which has a potential value of $147,000.00, is for a delivery order with a firm fixed price and a completion date of June 30, 2018. The contract does not have a set-aside designation and the place of performance is West Alton, Missouri.</p>
- <p>This is a federal contract award from the U.S. Army Corps of Engineers Engineering District St. Louis to Widman Construction Inc., a for-profit organization, for the "Lower River Land Repair" project. The contract is a delivery order with a firm fixed price of $1,108,941.37 and a completion date of September 30, 2019. The place of performance is West Alton, Missouri. This contract does not have a set-aside designation.</p>
- <p>The Department of the Army Corps of Engineers Engineering District St Louis awarded a Delivery Order contract to Widman Construction Inc., a for-profit organization, for the UPPER RIVER LAND REPAIR & FLOATING PLANT project. The $367,313.89 Firm Fixed Price contract was awarded on September 25, 2017 and has a completion date of September 30, 2018. The contract does not have a set-aside designation and the place of performance is West Alton, Missouri.</p>
- <p>The Department of the Army Corps of Engineers Engineering District St Louis awarded a Firm Fixed Price Delivery Order contract to Widman Construction Inc., a for-profit organization, for the UPPER RIVER LAND REPAIR & FLOATING PLANT project in West Alton, Missouri. The contract has a potential value of $200,248.26 and a completion date of June 30, 2018. The contract does not have a set-aside designation.</p>
- <p>The Department of the Army Corps of Engineers Engineering District St Louis awarded a Firm Fixed Price Delivery Order contract to Widman Construction Inc., a For Profit Organization, for FY18 MPLD MAIN LOCK SUPPORT services in West Alton, Missouri. The potential value of the contract is $797,060.12, and the completion date is December 31, 2018. This contract is not set aside for a specific business type.</p>
- <p>The Department of the Army Corps of Engineers Engineering District St Louis awarded a firm fixed-price delivery order contract to Widman Construction Inc., a for-profit organization, for the Upper River Land Repair & Floating Plant project. The contract, which does not have a set-aside designation, has a potential value of $1,648,255.75 and a completion date of September 30, 2019. The project is located in West Alton, Missouri.</p>
- This is a firm fixed-price delivery order issued by the U.S. Army Corps of Engineers, Engineering District St. Louis to Widman Construction Inc., a small business contractor. The $276,270.94 contract is for COR System Levee Repairs and Lower River Land Repair in West Alton, Missouri. The work involves civil construction services such as channel debris removal, levee and embankment repairs, road construction, and infrastructure maintenance along the Mississippi River system. Widman Construction...
- <p>The Department of the Army Corps of Engineers Engineering District St. Louis awarded a $112,633.48 firm fixed-price delivery order contract to Widman Construction Inc., a for-profit organization, for the LOWER NAV COR FLOOD DEBRIS REMOVAL project in West Alton, Missouri. The contract does not have a set-aside designation and was awarded on September 22, 2017, with a completion date of March 31, 2018.</p>
- W912P914D0501Indefinite Delivery Contract
- W912P914D0501-W912P918F0402Delivery Order
This is a firm-fixed-price delivery order contract awarded by the U.S. Army Corps of Engineers Engineering District St. Louis to Widman Construction Inc., a for-profit organization, for the LD 24 & LD 25 AUX GATE SILT REMOVAL project in West Alton, Missouri. The contract has a potential value of $210,291.18 and a completion date of September 30, 2019. The contract type is Firm Fixed Price, and there is no set-aside designation mentioned. The award date was September 26, 2018.
Generated 3/23/24, 3:26 PM
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
UPPER RIVER LAND REPAIR & FLOATING PLANT | W912P914D0501 | Department of the Army Corps of Engineers Engineering District St Louis | Award Notice 1/1 | 10/24/13, 3:22 PM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| P00002 | Change Order | $0 | 5/23/19 | |
| P00001 | Change Order | $0 | 3/11/19 | |
| Not listed | Not listed | $210.3k | 9/26/18 |