Delivery Order W912P813D0007-0002
Award Date 8/12/13
Potential Completion Date 8/30/14
Potential Value $24M
Federal Agency
Ultimate Awardee
Not listed NAICS Category
Federal Contract Vehicle
- Not listed
Set-Aside Type
No Set-Aside Used
Extent Competed
Full and Open Competition
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
New Orleans, LA 70118, USA
Solicitation Procedures
Sealed Bid
Number Of Offers Received
6
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- Stone Construction Company, Inc. was awarded a firm fixed price contract for $7,970 by the Department of the Army Corps of Engineers Engineering District New England to perform spillway access road repairs and weir cleaning at the Black Rock Dam in Thomaston, Connecticut. Work is to be completed by January 21, 2022 under a total small business set aside. As the prime contractor, Stone Construction will deliver the requested repair and maintenance services for dam infrastructure to support the...
- The U.S. Army Corps of Engineers, Pittsburgh District awarded a $952,195 firm fixed price contract to Coastal Drilling East, LLC Geotechnical Division for the Pike Island Monolith R33 and R34 River Wall Crack Stabilization project. Under the contract, Coastal Drilling East will perform repairs and stabilization of cracks within two concrete river wall monoliths at the U.S. Army Corps of Engineers' Pike Island Locks and Dam on the Ohio River in Wheeling, West Virginia. Work will include...
- Stone & Lime Imports, Inc. was awarded a $708,781.45 definitive contract by the U.S. Army Corps of Engineers, New England District to perform gatehouse masonry repairs at Knightville Dam in Huntington, Massachusetts. The contract is set aside for total small business participation. Stone & Lime Imports will clean and repoint interior and exterior brick, replace a failed protective coating, and complete other exterior repairs to the approximately 213-foot long gatehouse structure as...
- Stone Construction Company, Inc., doing business as Stone Construction Co Inc., has been awarded a firm fixed-price contract valued at seven thousand three hundred sixty dollars by the U.S. Army Corps of Engineers, New England District to perform spillway drainage clearing services at Thomaston Dam in Thomaston, Connecticut. The contract was awarded under the Corps' indefinite delivery/indefinite quantity BPA Call vehicle and has a period of performance from September 13, 2023 through January...
- The U.S. Army Corps of Engineers Engineering District New England awarded a firm fixed price contract to Stone Construction Company, Inc. valued at $13,848 to perform culvert, road, and trail repair work at Thomaston Dam in Thomaston, Connecticut. Set aside for total small businesses, the contract was issued under a blanket purchase agreement call and requires completion by May 21, 2022. Stone Construction will undertake the culvert, road, and trail repair services at the specified location to...
- This is a $776,416.00 firm fixed price definitive contract awarded by the National Park Service (NPS), a civilian federal agency, to Watershed Environmental Solutions LLC, a woman-owned small disadvantaged business, for the recovery, restoration, and griff creek culvert replacement project related to the Elwha River in Olympic National Park, Washington. The contract does not have a set-aside designation. The award date was May 5, 2010, with a completion date of September 12, 2010. Watershed...
- The U.S. Army Corps of Engineers Engineering District New England awarded a firm-fixed-price contract to Stone Construction Company, Inc. The, a small business, for retaining wall repair work at Colebrook River Lake in Colebrook, CT. The contract has a ceiling value of $10,240 and a period of performance through September 2024. This contract appears to be a call order under a larger Blanket Purchase Agreement (BPA) vehicle that the Corps has established with Stone Construction Company to support...
- This contract was awarded by the National Park Service (NPS), a civilian agency within the Department of the Interior, to Kovilic Construction Co Inc., a small business construction firm, to restore the canal prism and stabilize a historic dry laid stone wall along the Chesapeake & Ohio Canal National Historical Park. The $11,126,498.00 firm-fixed-price contract has an ultimate completion date of October 31, 2024. The work is being performed under the Great American Outdoors Act (GAOA)...
- The U.S. Army Corps of Engineers (USACE) awarded a $20,000.00 firm-fixed-price purchase order contract to Clear Stone GEO LLC for camera inspections, cleaning, and decommissioning of vertical and horizontal drains at the Howard A. Hanson Dam in Enumclaw, Washington. This requirement was originally announced as a sources sought for small businesses, including 8(a), woman-owned, veteran-owned, and HUBZone firms, under NAICS code 221310 - Water Supply and Irrigation Systems. The contract was set...
- This firm fixed price contract was awarded by the U.S. Army Corps of Engineers, New England District to Stone Construction Company, Inc. for repair of the rear access road at HOP BROOK LAKE in Middlebury, Connecticut. With a total small business set aside designation, the contract has a potential value of $0.00 and work is to be completed by December 19, 2019. As the awarding agency, the Corps of Engineers manages civil works projects including water resources development and regulatory...
- W912P813D0007Indefinite Delivery Contract
- W912P813D0007-0002Delivery Order
OP WATERSHED STONE REPAIRS
Posted 8/13/13
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
Flood Control, Mississippi River and Tributaries, 2013 Stone Placement, Mississippi, Atchafalaya, and Red Rivers and Old River Control Channels | W912P8-13-B-0048 | Department of the Army Corps of Engineers Engineering District New Orleans | Award Notice 1/1 | 4/11/13, 3:22 PM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| 1C | Supplemental Agreement for work within scope | $316.7k | 2/10/16 | |
| 2 | Other Administrative Action | ($880k) | 7/14/14 | |
| 1B | Change Order | ($491k) | 3/20/14 | |
| 1A | Change Order | $0 | 3/3/14 | |
| 1 | Other Administrative Action | $1.3m | 2/3/14 |