Delivery Order W912P717D0003-W9123822F0030
- Not listed
- This $4,554,466.11 firm-fixed-price delivery order was awarded to HDR GEI Joint Venture, a partnership between HDR, Inc. and CH2M, by the U.S. Army Corps of Engineers (USACE). The contract, which has no set-aside designation, is part of the USACE's larger Dam and Levee Safety Program Design Services indefinite-delivery/indefinite-quantity (IDIQ) contract. Under this delivery order, HDR GEI Joint Venture will provide services to update the water control manuals for five dams in California:...
- This is a $3,417,693.49 firm-fixed-price delivery order contract awarded by the U.S. Army Corps of Engineers to HDR Engineering, Inc. (HDR) for planning services related to updating the Water Control Manuals (WCM) for the Oroville Dam in Oroville, California and the New Bullards Bar Dam in Dobbins, California. The award is not associated with a set-aside program. The contract has a period of performance ending on October 31, 2025. HDR is a for-profit, Subchapter S Corporation that provides...
- This federal contract award was issued by the U.S. Army Corps of Engineers to HDR Engineering, Inc., a subsidiary of HDR, Inc., for the Folsom Dam Surcharge Operations Update project in Folsom, California. The $1,316,007.95 firm-fixed-price delivery order contract has an ultimate completion date of December 30, 2026. The purpose of this modification is to extend the performance period. The contract is not set aside for any specific business type. HDR Engineering, Inc. is a for-profit, Subchapter...
- This federal contract award was issued by the U.S. Army Corps of Engineers (USACE) to HDR Engineering, Inc. (HDR) as the prime contractor. The contract, valued at $93,175.52, is for engineering design and review services to support a dam raise gate modification project in Folsom, California. The contract is a delivery order with a firm fixed price pricing type, and the ultimate completion date is November 24, 2016. This award is not associated with a set-aside program. HDR is a for-profit...
- The U.S. Army Corps of Engineers awarded a $134,319.06 firm fixed price purchase order to HDR Engineering, Inc. for hydrologic engineering center geographic river forecast system model services. The contract has no set-aside designation and work will be performed in Folsom, California with a completion date of February 8, 2023. HDR Engineering, Inc. is a subsidiary of Hdr, Inc., which also does business as Hdr-Ch2M JV. No additional details were provided on subcontractors or the specific...
- The Department of the Army Corps of Engineers Engineering District Sacramento awarded a $343,205.87 firm fixed price delivery order to HDR Engineering, Inc., a for-profit S-corporation that provides engineering, architecture, environmental, and construction services, for the FY20 Defense Depot San Joaquin (DDJC) Water & Energy Plan project in Tracy, California. This order was not set aside for any specific type of business. HDR Engineering has received numerous prime contract awards from the...
- The Department of the Army Corps of Engineers awarded a Firm Fixed Price Delivery Order contract to HDR Engineering Inc. (HDR), a for-profit engineering, architecture, environmental, and construction services firm, for an "Ampacity Analysis" project in Lakeview, AR. The potential value of the contract is $67,768.40 and the completion date is March 24, 2022. The contract is not designated as a set-aside. HDR, a Subchapter S Corporation, has provided a range of professional services to...
- The U.S. Army Corps of Engineers awarded a $625,014.73 firm-fixed-price purchase order contract to HDR Engineering, Inc. for a biological assessment related to the Yuba Biological Assessment Technical project. The contract has an ultimate completion date of March 31, 2025. HDR Engineering, Inc. is a subsidiary of the larger engineering firm HDR, Inc., which holds multiple indefinite delivery contracts with federal agencies like the U.S. Army Corps of Engineers, Department of Defense, and...
- This is a firm fixed-price delivery order contract awarded by the U.S. Army Corps of Engineers Engineering District Sacramento to HDR Engineering, Inc. (doing business as HDR) for $154,640.76 to provide engineering post-construction support services for the Folsom Dam Modifications project in Folsom, California. The contract does not have a set-aside designation. HDR Engineering, Inc. is a for-profit subchapter S corporation that provides a range of engineering, architecture, environmental,...
- This is a delivery order awarded by the U.S. Army Corps of Engineers (USACE) to HDR Engineering, Inc. (HDR) for $100,410.71 to provide technical support for a paleoflood analysis of the Feather River and Oroville Dam in California. The contract has a completion date of June 30, 2023 and is a firm fixed price type. HDR has been awarded multiple prime contracts and task orders from USACE for a variety of engineering, design, and consulting services in support of the agency's civil works,...
- W912P717D0003Indefinite Delivery Contract
- W912P717D0003-W9123822F0030Delivery Order
The U.S. Army Corps of Engineers awarded a $1,802,737.05 firm-fixed-price delivery order to HDR Engineering, Inc. for updates to the Programmatic Water Control Manual covering multiple dams in California, including Black Butte Dam, Hidden Dam, Merced County Streams Group Dams, New Hogan Dam, and Terminus Dam. This contract is not set aside for any small business program. HDR Engineering, Inc., a for-profit Subchapter S Corporation, is the prime contractor. As an architecture, engineering, environmental, and construction services firm, HDR has extensive experience supporting the U.S. Army Corps of Engineers' civil works programs involving water resource development and infrastructure projects. The contract completion date is November 16, 2023.
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| P00001 | Supplemental Agreement for work within scope | $0 | 5/5/23 | |
| Not listed | Not listed | $1.8m | 7/20/22 |