Delivery Order W912P716D0003-W9123821F0016

Award Date 12/16/20
Potential Completion Date 5/31/23
Potential Value $5M
Funding Federal Agency
US Army Corps of Engineers
Contracting Federal Agency
ENDIST Sacramento
Ultimate Awardee
Hdr, Inc.
Set-Aside Type
No Set-Aside Used
Federal Contract Vehicle
Extent Competed
Full and Open Competition
Major Defense Program
Not listed
Pricing Type
Firm Fixed Price
Place of Performance
West Sacramento, CA 95605, USA
Solicitation Procedures
Architect-Engineer FAR 6.102
Number Of Offers Received
Not listed
Legislative Mandate
Service Contract Act
National Interest Action
Not listed
Research Type
Not listed
Primary Consortia Member
Not listed
Similar Awards
This firm-fixed-price delivery order was awarded by the U.S. Army Corps of Engineers to HDR Engineering, Inc. (doing business as HDR) for the American River Common Features, Natomas Basin Reach B project in Sacramento County, California. The award, valued at $1,911,762.68, is for 60% through final design of this civil works project. HDR, a for-profit S corporation, provides engineering, architecture, environmental, and construction services to support infrastructure projects. The contract does...
This is a delivery order contract awarded by the U.S. Army Corps of Engineers to HDR Engineering, Inc., a subsidiary of HDR, Inc., for design and engineering services during construction of the American River Common Features, Natomas Basin Reach I, Contract 2 project in Sacramento County, California. The contract has a firm fixed price of $844,166.33 and a completion date of May 31, 2026. This effort is part of a larger indefinite delivery contract worth up to $99 million that HDR holds with the...
This firm-fixed-price delivery order was awarded by the U.S. Army Corps of Engineers to HDR Engineering, Inc. (doing business as HDR) on December 7, 2020 for $220,822.12. The contract is for engineering services during construction of the American River Common Features, Natomas Basin Reach B I-5 Window project in Sacramento County, California. The completion date is October 31, 2023. This contract was not set aside for a specific business type. HDR is a subchapter S corporation that provides...
The U.S. Army Corps of Engineers awarded a $310,148.29 firm fixed-price delivery order to HDR Engineering, Inc. for engineering services during construction on the American River Common Features, Natomas Basin Reach B project in Sacramento County, California. The contract has a completion date of May 1, 2023 and was awarded on March 10, 2020. HDR Engineering, Inc. is a for-profit subchapter S corporation that provides engineering, architecture, environmental, and construction services. The...
The U.S. Army Corps of Engineers Engineering District Sacramento awarded a $711,886.07 firm fixed price delivery order contract to HDR Engineering, Inc. to provide 65% to 100% design services for the American River Common Features, Natomas Basin Reach B, I-5 Window project in Sacramento County, California. This work is not associated with a larger contract vehicle. The contract has no set-aside designation. HDR Engineering, Inc. is the prime contractor; no major subcontractors were identified....
This is a firm fixed-price delivery order awarded by the U.S. Army Corps of Engineers Engineering District Sacramento to HDR Engineering, Inc. for engineering services and cultural resource monitoring during construction on the American River Common Features, Natomas Basin Reach I Contract 1 project in Sacramento County, California. The contract has a potential value of $499,299.10 and a completion date of December 31, 2020. HDR Engineering, Inc. is a for-profit, Subchapter S corporation that...
The U.S. Army Corps of Engineers awarded a $1,835,067.65 firm fixed price delivery order to HDR Environmental, Operations and Construction, Inc. for construction phase services in support of the FY23 Valley Resident Office project. This project involves levee improvements along the Sacramento River East Levee and construction activities for Contracts 2 and 3A along the Lower American River in Sacramento, California. The period of performance is through January 31, 2025. As the prime...
This is a firm fixed-price delivery order contract awarded by the U.S. Army Corps of Engineers (USACE), Sacramento District, to HDR Fugro WLA. The contract is for $1,236,708.78 and is related to the American River Watershed Common Features project, a flood risk management initiative authorized under the Water Resources Development Act of 1996 (WRDA96). The contract includes the Final Remediation Methods Report, 30% and 60% design plans, a Draft Design Documentation Report, rights-of-way and...
This federal contract award is for civil and fish passage engineering, design, and quality assurance (QA) laboratory testing services for the American River Common Features (ARCF) 2016 Project in Yolo County, California. The $7,081,990.91 Firm Fixed Price contract was awarded by the U.S. Army Corps of Engineers (USACE) to HDR GEI Joint Venture, a partnership between HDR, Inc. and CH2M. The contract has no set-aside designation and is a delivery order under the $110 million USACE South Pacific...
The Department of the Army Corps of Engineers awarded a $5,790,133.82 firm fixed price delivery order to HDR GEI Joint Venture under the Dam and Levee Safety Program Design Services multiple award indefinite delivery contract. This delivery order is for mitigation design of the Urritia Habitat Restoration and Enhancement Project on the Lower American River in Sacramento, California. No set-aside was used for this award. Performance will take place in Sacramento and is scheduled for completion by...
  • W912P716D0003
    Indefinite Delivery Contract
  • W912P716D0003-W9123821F0016
    Delivery Order

HDR Engineering, Inc. is delivering design services for the widening of the Sacramento Weir on the American River in Yolo County, California under a $5 million firm fixed price delivery order awarded by the U.S. Army Corps of Engineers (USACE). As part of the USACE's American River Common Features 2016 project, HDR will complete 100% design for the Sacramento Weir widening to make the structure ready for advertisement. Performance will take place in West Sacramento, California over a thirty-three month period ending in May 2023. No subcontractors or socioeconomic designations were indicated. The delivery order was issued against the multiple award USACE Planning, Design, and Construction Support indefinite delivery/indefinite quantity contract vehicle.