Delivery Order W912EQ19D0001-W912EQ22F0053
Award Date 7/18/22
Potential Completion Date 9/6/22
Potential Value $5.3M
Funding Federal Agency
Contracting Federal Agency
Ultimate Awardee
Not listed NAICS Category
Set-Aside Type
No Set-Aside Used
Federal Contract Vehicle
- Not listed
Extent Competed
Full and Open Competition
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
West Memphis, AR 72301, USA
Solicitation Procedures
Multiple Award, Fair Opportunity
Number Of Offers Received
2
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- The Department of Defense, Army Corps of Engineers awarded a $6.08 million firm fixed price delivery order contract to Luhr Bros., Inc. to provide 3001AE stone delivery in Arkansas City, Arkansas. The contract period of performance is from August 5, 2022 through December 3, 2022. No subcontractors were identified. Based on the limited information provided, it appears Luhr Bros., Inc. will deliver various types of stone material to support Army Corps of Engineers projects in Arkansas under this...
- This federal contract award to Luhr Bros., Inc., a prime contractor, is for the delivery of graded stone materials to support civil works projects managed by the U.S. Army Corps of Engineers. The $8,292,600.00 firm fixed price delivery order has an ultimate completion date of September 30, 2024 and was issued under an existing indefinite delivery/indefinite quantity (IDIQ) contract vehicle utilized by the Corps for recurring infrastructure and environmental restoration needs. Luhr Bros. is a...
- The U.S. Army Corps of Engineers Engineering District Memphis awarded a $2.4 million firm fixed price delivery order to Luhr Bros., Inc. for Mississippi River stone structures. Under this contract, Luhr Bros. will provide construction services related to river structures for the Corps of Engineers District in Braggadocio, Missouri, with work to be completed by September 30, 2020. No subcontractors or set aside designations were identified. The Army Corps of Engineers oversees civil works...
- The U.S. Army Corps of Engineers awarded a $1.3 million firm fixed price delivery order to Luhr Bros., Inc. for Mississippi River stone structures. Under this order, Luhr Bros. will provide construction services to build stone structures along the Mississippi River in Gates, Tennessee by October 12, 2021. The Corps of Engineers manages civil works projects, including river and harbor construction, across the United States to support navigation and reduce flood risk. No set aside designation or...
- <p>The Department of Defense, Army Corps of Engineers awarded an $8.5 million firm fixed price delivery order contract to Luhr Bros., Inc. to provide stone dike construction task order services involving stone placement in Memphis, Tennessee. The period of performance for this contract is from July 10, 2023 through April 17, 2023. No subcontractors were identified.</p>
- The U.S. Army Corps of Engineers awarded a $9.3 million firm fixed price delivery order to Luhr Bros., Inc. for Mississippi River stone structures. Under this contract, Luhr Bros. will construct unspecified river structures for the Corps from September to November 2021 in Wynnburg, Tennessee. As the prime, Luhr Bros. will likely utilize regional subcontractors with expertise in river construction, quarrying, and transportation. The Corps manages civil works projects that maintain navigation...
- <p>The Department of Defense, Army Corps of Engineers awarded an $11.1 million firm fixed price delivery order contract to Luhr Bros., Inc. to provide Mississippi River stone structures at Holly Grove, Arkansas. The contract runs from December 22, 2021 through December 22, 2022 and will likely involve construction services for riverbank stabilization or navigation structures using locally quarried stone. No subcontractors were identified.</p>
- The Department of the Army Corps of Engineers awarded a $9.4 million firm fixed price delivery order to Luhr Bros., Inc. for Mississippi River stone structures. The Corps utilizes delivery orders against its multiple award construction contracts to complete critical infrastructure projects that support navigation and flood control along the Mississippi River. Work will be performed in Atoka, Tennessee by Luhr Bros., Inc. and is expected to be completed by June 30, 2022. No set aside...
- This firm fixed price delivery order contract was awarded by the U.S. Army Corps of Engineers to Luhr Bros., Inc., a for-profit marine construction company, with a potential value of $5,784,962.60. The contract is for the delivery of graded stone materials, dike and revetment construction, hydraulic dredging, and habitat restoration work in support of the Corps' civil works mission involving flood control and environmental restoration along the Mississippi River system. The contract was not...
- This is a firm fixed price delivery order contract awarded by the U.S. Army Corps of Engineers (USACE) to Luhr Bros., Inc., a for-profit construction company, to perform stone placement work along the Atchafalaya Basin, Mississippi River, and associated inflow channels. The $1,020,488.00 contract is part of the USACE's civil works mission to support flood control and environmental restoration along the Mississippi River system. Luhr Bros. has multiple active indefinite delivery/indefinite...
- W912EQ19D0001Indefinite Delivery Contract
- W912EQ19D0001-W912EQ22F0053Delivery Order
The Department of Defense, Army Corps of Engineers awarded Luhr Bros., Inc. a $5.34 million firm fixed price delivery order contract to provide graded stone for construction projects in West Memphis, Arkansas. The contract runs from July 18, 2022 through September 6, 2022 and will supply graded stone materials to support Army Corps of Engineers construction activities in the specified location. No information was provided about subcontractor involvement on this contract award.
Generated 11/28/23, 3:02 AM
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
Mississippi River Stone Placement | W912EQ23S0007 | Department of the Army Corps of Engineers Engineering District Memphis | Special Notice 1/2 | 5/26/23, 1:45 PM | |
Justification and Approval-MS River Stone Placement | W912EQ23S0007 | Department of the Army Corps of Engineers Engineering District Memphis | Limited / Sole Source Justification 2/2 | 7/19/23, 6:57 PM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| Not listed | Not listed | $5.3m | 7/20/22 |