HHD MATOC cutoff wall construction

Ended Awarded Last action

Contract number
W912EP19F0119
Awardee
Awarding agency
Obligated
$72,544,394

Award facts

Opportunity
  • W912EP18R0019 Solicitation number
Contract value 100% obligated
  • $72,544,393.88 Current, with exercised options
  • $72,727,436.87 Potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition · 3 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Clewiston, FL 33440, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00010 $441,466
Supplemental Agreement for work within scope A00019 -$92,045
Supplemental Agreement for work within scope P00009 -$897,424
Supplemental Agreement for work within scope P00008 $648,687
Supplemental Agreement for work within scope A00018 $0
Supplemental Agreement for work within scope P00007 · Revised clin 0011 cutoff wall phase 2 $3,313,206
Supplemental Agreement for work within scope P00005 · Revision of specification section 13 50 05. $0
Supplemental Agreement for work within scope P00006 · Exposed embankment REA-001 $609,586
Supplemental Agreement for work within scope A00017 · Additional scope for stilling wells S236 (clin 0047) $24,334
Supplemental Agreement for work within scope A00016 · A00016 piezometers within riprap (clin 0046) $59,380
Supplemental Agreement for work within scope A00015 · HS018 credits for unused clins 17 and 27 -$79,469
Supplemental Agreement for work within scope A00014 · HS016 piezometer installation $9,291
Supplemental Agreement for work within scope A00013 · (HS015) S-236 asbestos remediation impacts $203,822
Supplemental Agreement for work within scope A00012 · HS008 DSC asphalt thickness and HS010 REA 2 $240,285
Supplemental Agreement for work within scope A00011 · HS014 extension of bypass pumping standby $67,166
Supplemental Agreement for work within scope A00010 · Weather time extension $0
Supplemental Agreement for work within scope A00009 · Stilling well impacts $14,540
Supplemental Agreement for work within scope A00008 $231,524
Change Order A00007 · Revised clin 0011 cutoff wall phase 2 $84,290
Supplemental Agreement for work within scope A00006 · Concrete encased conduit $31,696
Change Order A00005 · HS002 remove SPT tasks bulkheads/manatee scre -$5,318
Change Order A00004 · WH006 REF no R00006 emergency armoring $462,189
Funding Only Action A00003 $13,137
Funding Only Action A00002 · Revised clin 0011 cutoff wall phase 2 $283,440
Change Order A00001 · Standby time VEQ to 83.75% clin 0006 $0
Change Order P00002 · Revised clin 001, 0033 and added deduct from A00001 (standy by clin 0006) -$178,719
Change Order P00003 · Payment for preparatory work (WH005) $0
Supplemental Agreement for work within scope P00001 · DE-obligating funding from the original contract funding. RE-obligating 1002 and 12-28 with himsup funds in sub-clins. Federal funds in sub-clins mentioned… $0
Original award $67,059,331
Show all 29

About this award

The U.S. Army Corps of Engineers awarded a $72.3 million firm fixed price delivery order against its MATOC (Multiple Award Task Order Contract) to Bauer Foundation Corporation for HHD (Horizontal Hydraulic Drilling) cutoff wall construction in Clewiston, Florida. As part of its civil works program, the Corps utilizes MATOC vehicles and task orders to complete flood risk management and coastal storm damage reduction projects. No subcontractors or set aside designations were indicated. This delivery order will support cutoff wall construction to reduce flood risks through December 2022 in Clewiston, consistent with the Corps' project responsibilities.

Quick answers

Who was awarded contract W912EP19F0119?

W912EP19F0119 was awarded to Bauer Foundation Corp by ENDIST Jacksonville (US Army Corps of Engineers) on April 22, 2019.

How much is contract W912EP19F0119 worth?

The government has obligated $72,544,394 on W912EP19F0119. Its potential value, with all options, is $72,727,437.

Is contract W912EP19F0119 an order under another contract?

Yes. W912EP19F0119 is a delivery order under W912EP19D0012, an indefinite delivery contract.

Was contract W912EP19F0119 competed?

The extent of competition for W912EP19F0119 was full and open competition. The government received 3 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award