The U.S. Army Corps of Engineers has awarded a $7,939,956.29 firm fixed price definitive contract to BCI Construction USA, Inc., a Veteran Owned Small Business, to replace two sluice gates at the Saylorville Dam in Johnston, Iowa. The contract, which has a period of performance of 730 days, was issued under an unrestricted solicitation for the Saylorville Control Tower Sluice Gate Project. The scope of work includes designing, fabricating, delivering, and installing the new gates as well as...
This federal contract was awarded by the U.S. Army Corps of Engineers to Johnson Machine Works, Inc., a manufacturer of fabricated steel products, for the construction of an emergency bulkhead for the Saylorville Lake Reservoir Control Tower in Chariton, Iowa. The $199,963 firm-fixed-price contract was set aside for small businesses and was awarded in April 2019, with a completion date of June 2020. The original solicitation was for the fabrication and delivery of bulkheads, under NAICS code...
The U.S. Army Corps of Engineers awarded a $313 thousand firm fixed price delivery order to Affordable Concrete, LLC of Johnston, Iowa. The order is against an indefinite-delivery/indefinite-quantity multiple award contract to provide concrete work at various locations within the Saylorville Lake area, including Prairie Flower Campsites, the Bob Shetler Archery Range, Neil Smith Trails, and the Western Resident Parking Lot. The work supports maintenance and infrastructure improvements at...
This is a $108,143.81 firm fixed-price delivery order awarded by the U.S. Army Corps of Engineers to Cerebral MPS JV, LLC, a minority-owned limited liability company, for the Prairie Flower Campground Campsite Concrete Slab Replacement project at Saylorville Lake in Johnston, Iowa. The contract is not set aside and has an ultimate completion date of April 8, 2017. The U.S. Army Corps of Engineers is the funding agency for this project, which is part of their responsibilities for managing...
The U.S. Army Corps of Engineers awarded a $22,187.50 firm fixed price contract to MB Enterprises Of Ames, LC, doing business as Trenchless Solutions Iowa and Neighbors HTG CLG PLG, for horizontal directional drilling services at the Saylorville Lake, Bob Shetler-Cottonwood Recreation Area in Johnston, Iowa. The contract, set aside for total small businesses, calls for MB Enterprises to complete the drilling by April 30, 2021. As the award was made under a blanket purchase agreement call, the...
The U.S. Army Corps of Engineers awarded a $400,731.00 firm fixed-price purchase order to Pentair Pump Group, Inc. (doing business as Fairbanks Morse Pump) for long-term repairs to Pump #1, Pump #2, and Pump #3 at the Big Creek Pump Station Facility in Saylorville Lake, Johnston, Iowa. The contract has an ultimate completion date of January 16, 2016 and was not designated as a set-aside. The contract was awarded by the Rock Island District (ENDIST Rock Island) of the U.S. Army Corps of...
The U.S. Army Corps of Engineers awarded a $8,026,502.40 Firm Fixed Price contract to Better By Design LLC, an SBA-certified Economically Disadvantaged Women-Owned Small Business, 8(a) Program Participant, Women-Owned Small Business, and HUBZone Firm. The contract, awarded on April 28, 2022, is for the Saylorville Shoreline Erosion Protection project, which includes tree clearing, installation of bedding stone and riprap, road replenishment, and haul road construction. The base contract and...
This federal contract award, W912EK22D0011|W912EK24F0008, was issued by the U.S. Army Corps of Engineers (USACE), a defense agency, to Gale Construction Company of Illinois, a Small Business Administration (SBA) certified Economically Disadvantaged Women-Owned Small Business (EDWOSB), 8(a) Program Participant, and HUBZone firm. The contract, titled "SAYLORVILLE LAKE TASK ORDER FIVE," is a Firm Fixed Price Delivery Order with a ceiling value of $502,799.72 and an ultimate completion...
The Department of the Army Corps of Engineers awarded a firm-fixed-price purchase order contract to Unified Contracting Services, Inc., a Disadvantaged Business Enterprise (DBE), for the installation of an above-ground split cell fuel storage system at the Saylorville Lake Administration and Maintenance Compound in Pleasant Hill, Iowa. The contract, which was set aside for small businesses, has a potential value of $118,096.00 and a completion date of April 2, 2023. This contract was awarded...
This is a $103,524.37 firm fixed-price delivery order contract awarded by the U.S. Department of the Army Corps of Engineers to Fickett Structural Solutions Inc., a for-profit Subchapter S Corporation, for quality assurance inspection services related to the fabrication of sluice gates at the Saylorville project location in Vancouver, Washington. The contract has a completion date of September 26, 2025. Fickett Structural Solutions Inc. is a specialized provider of nondestructive testing,...