Delivery Order W912EE25DA003-W912EE26FA027
Award Date 2/13/26
Potential Completion Date 3/31/27
Potential Value $4.4M
Federal Agency
Awardee
Ultimate Awardee
Not listed NAICS Category
Federal Contract Vehicle
- Not listed
Set-Aside Type
No Set-Aside Used
Extent Competed
Full and Open Competition
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
Vicksburg, MS, USA
Solicitation Procedures
Negotiated Proposal / Quote
Number Of Offers Received
Not listed
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- The U.S. Army Corps of Engineers, Engineering and Support Center (ENDIST) Vicksburg awarded a $9.84 million firm fixed-price delivery order to Luhr Crosby, LLC on August 10, 2025, for stone repairs to revetments and dikes along the Mississippi River under the Channel Improvement Program. Designated as Task Order No. 2 under an Indefinite Delivery/Indefinite Quantity (ID/IQ) contract vehicle, this delivery order supports critical flood control and navigation infrastructure maintenance in the...
- The U.S. Army Corps of Engineers (USACE) awarded a $6.02 million delivery order to Luhr Crosby, LLC on June 2, 2025, for FY25 Mississippi River Operations and Maintenance services. This firm fixed price contract, with an ultimate completion date of August 5, 2026, was awarded without a set-aside designation, indicating the work was competed in the open market. Luhr Crosby, a construction and engineering firm based in Columbia, Illinois, specializes in waterway infrastructure projects including...
- The U.S. Army Corps of Engineers (USACE) awarded a $24.6 million firm fixed price delivery order to Luhr Crosby, LLC for construction and maintenance of rivers, with performance scheduled through June 10, 2026. The work will be performed in St. Louis, Missouri, and represents a continuation of USACE's ongoing civil works mission to maintain critical waterway infrastructure across the Midwest and Gulf Coast regions. This delivery order was issued without a small business set-aside designation,...
- This is a firm-fixed-price delivery order awarded by the U.S. Army Corps of Engineers (USACE) to Luhr Crosby, LLC, a for-profit construction and engineering firm. The $3,753,877.20 contract is for stone placement work and has an ultimate completion date of August 8, 2024. Luhr Crosby, LLC is an experienced USACE contractor, holding several Indefinite Delivery Contracts (IDCs) with the agency for civil works projects such as dredging, river structure construction and maintenance, and flood...
- The U.S. Army Corps of Engineers awarded a $4.8M firm fixed-price delivery order to Luhr Crosby, LLC on June 25, 2024, for FY24 Lower D&R (Dredging and Repair) services, with completion scheduled for November 2025. The work will be performed in St. Louis, Missouri. This delivery order was awarded without a small business set-aside, reflecting Luhr Crosby's capacity to compete for substantial federal infrastructure work. As a specialized waterway construction and engineering firm...
- This is a firm fixed-price delivery order contract awarded by the U.S. Army Corps of Engineers (USACE) to Luhr Crosby, LLC, a for-profit construction and engineering firm specializing in waterway infrastructure projects. The contract, valued at $11,353,388.90, is for stone paving work in New Orleans, Louisiana with a performance period through March 8, 2024. This contract does not utilize a small business set-aside. Luhr Crosby, LLC is an experienced federal contractor, holding several...
- This is a firm fixed price delivery order awarded by the U.S. Army Corps of Engineers to Luhr Bros., Inc. to perform stone repairs to revetments and dikes in Vicksburg, Mississippi. The contract has a potential value of $1,912,066.00 and a completion date of August 31, 2023. Luhr Bros. is a for-profit organization that provides marine construction services, including rock and stone placement, bank stabilization, and dredging, for the U.S. Army Corps of Engineers. This delivery order is likely...
- This firm fixed price delivery order was awarded by the U.S. Army Corps of Engineers (USACE) to Luhr Bros., Inc., a construction firm that provides marine services such as rock and stone placement, bank stabilization, and dredging. The $4,205,769.50 contract is for flood control work along the Mississippi, Atchafalaya, and Red Rivers, including stone placement at specific locations. It was issued under an indefinite delivery, indefinite quantity (IDIQ) contract vehicle the USACE uses for...
- The U.S. Army Corps of Engineers (USACE) awarded a $12,214,600.52 firm-fixed-price delivery order contract to Luhr Crosby, LLC, a for-profit construction and engineering firm, for MAIN SURVEY AND DREDGE TASK ORDER #5. This award is under a larger indefinite delivery contract vehicle held by Luhr Crosby with USACE for waterway maintenance and construction services. The contract supports USACE's civil works mission of maintaining navigable waterways and reducing flood risks, with the work to be...
- This firm-fixed-price delivery order was awarded by the U.S. Army Corps of Engineers (USACE) to Luhr Crosby, LLC, a for-profit construction and engineering firm specializing in waterway infrastructure projects. The $4,774,127.70 contract is for Task Order #5 under a broader USACE contract vehicle. Luhr Crosby, LLC has established expertise in civil works and flood control services, with a focus on river and coastal infrastructure projects. The company holds several substantial Indefinite...
- W912EE25DA003Indefinite Delivery Contract
- W912EE25DA003-W912EE26FA027Delivery Order
The U.S. Army Corps of Engineers (ENDIST Vicksburg) issued a $4.407 million delivery order to Luhr Crosby, LLC on February 13, 2026, for stone repairs to Mississippi River revetments and dikes under a $30 million single-award indefinite delivery contract from USACE Vicksburg District. The parent IDC, awarded in June 2025, supports stone repairs across a 290-mile Mississippi River stretch and runs through March 2027. This delivery order, Task Order No. 3 for FY25 MS River Stone Repairs, is priced firm fixed price with an ultimate completion date of March 31, 2027. Place of performance is Vicksburg, MS.
Generated 5/22/26, 9:53 AM
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| Not listed | Not listed | $4.4m | 2/19/26 |