Delivery Order W912DY14D0007-0003
Award Date 9/30/16
Potential Completion Date 8/1/17
Potential Value $135K
Funding Federal Agency
Contracting Federal Agency
Ultimate Awardee
Not listed NAICS Category
PSC Category
Set-Aside Type
Competitive 8(a)
Federal Contract Vehicle
Extent Competed
Full and Open Competition after exclusion of sources
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
Lawton, OK 73503, USA
Solicitation Procedures
Multiple Award, Fair Opportunity
Number Of Offers Received
1
Legislative Mandate
Walsh Healy Act
National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- <p>This is a firm fixed-price delivery order awarded by the U.S. Department of Defense, Southwest Region, to the Sheffield-Herring Joint Venture, a minority-owned, small disadvantaged, woman-owned, Native American-owned business. The contract has a ceiling value of $442,039.00 and is for the repair or replacement of an automatic transfer switch at Fort Sill, Oklahoma. The contract was set aside for competition among 8(a) small businesses.</p>
- <p>This is a firm fixed-price delivery order contract awarded by the U.S. Army Engineering Support Center Huntsville, a defense agency, to Donley-Kirlin JV, a minority-owned limited liability company. The contract is for the repair and renewal of facilities at Fort Sill, Oklahoma, with a completion date of December 31, 2016. The contract was set aside for competition among 8(a) small businesses and has a ceiling value of $679,847.86.</p>
- This is a firm fixed-price delivery order awarded by the Army Installation Management Command (IMCOM) Southwest Region to FSA Construction, LLC, a tribally-owned, minority-owned small business. The contract is for the construction of a containment pad at Fort Sill, Oklahoma, with an ultimate completion date of January 21, 2025 and a ceiling value of $89,288.33. FSA Construction has previously performed various infrastructure and construction projects at Army installations in Oklahoma and...
- This is a Firm Fixed Price Delivery Order awarded to OK2 Construction, LLC, a small disadvantaged, veteran-owned, and service-disabled veteran-owned business, under the Civil Engineering Multiple Award Construction Contract III (CEMACC III) Indefinite Delivery Vehicle (IDV) with the Air Force Materiel Command. The contract has a ceiling value of $434,473.00 and a completion date of April 30, 2026. The project involves the repair and installation of emergency power connections at the Headquarters...
- <p>This is a Firm Fixed Price Delivery Order contract awarded by the Southwest Region of the Defense agency to Sheffield-Herring JV, a minority-owned, small disadvantaged business. The $670,467.53 contract is for COC (Center of Capabilities) rebuild, repair, and demolition work at Fort Sill, Oklahoma, and was set aside for competitive 8(a) small business participation. The contract has an ultimate completion date of March 26, 2017.</p>
- This is a firm fixed-price delivery order awarded by the U.S. Army Corps of Engineers Engineering District Tulsa to Firelake-Diversified Joint Venture, a self-certified small disadvantaged business, for 30th Air Defense Artillery (ADA) Secure Lab Modifications and Door Reconfiguration at Fort Sill, OK. The award date was September 28, 2018, with a completion date of January 11, 2021, and a potential value of $892,663.59. The contract was not set aside for any specific socioeconomic program.
- This is a firm-fixed-price delivery order awarded by the U.S. Army Corps of Engineers (USACE) to Cherokee Nation Environmental Solutions, L.L.C., a tribally-owned, SBA-certified 8(a) and HUBZone small disadvantaged business, for the FORT SILL DOAU & CONTROLS project. The contract has a ceiling value of $3,300,933.01 and a completion date of October 30, 2023. It does not have a set-aside designation. The contract includes two subcontractors: Vango, LLC, an economically disadvantaged...
- This firm-fixed-price delivery order, valued at $276,289.00, was awarded by the U.S. Army Corps of Engineers to FSA Construction, LLC, a tribally owned, minority-owned small business. The contract is for the reconfiguration of Rooms 113 and 114 in Building 3041 at Fort Sill, Oklahoma. No set-aside designation was used for this award. FSA Construction, LLC has a history of performing infrastructure and construction work at Army installations, including previous projects at Fort Sill and Offutt...
- This is a firm fixed-price delivery order awarded by the U.S. Army Engineering Support Center Huntsville, a Defense agency, to Ma-Chis Kawv III, LLC, a Tribally Owned, Minority Owned, For Profit Limited Liability Company. The contract is for the design and construction of an Access Control Point (ACP) at Fort Hood, Texas. The award has a ceiling value of $4,172,202.20 and an ultimate completion date of April 4, 2018. This delivery order was placed under a larger Access Control Point Design-Build...
- This is a federal contract award to Advanced Engineering Consultants PLLC, a self-certified small disadvantaged and Asian-Pacific American owned business based in Columbus, Ohio. The contract, valued at $444,597.29, was issued by the U.S. Army Corps of Engineers to install a substation interconnection at Fort Sill, Oklahoma. The contract is a firm-fixed-price delivery order that was awarded on May 29, 2018, with an ultimate completion date of April 22, 2021. Advanced Engineering Consultants...
- Access Control Point Design-BuildMaster IDIQ
- W912DY14D0007Indefinite Delivery Contract
- W912DY14D0007-0003Delivery Order
This is a firm fixed price delivery order awarded under the Access Control Point Design-Build contract, with a ceiling value of $134,805.00. The contract was awarded by the Office of the Chief of Staff, a Defense agency, to Zieson Construction Company, LLC, a minority-owned, small disadvantaged, and service-disabled veteran-owned business. The contract is for the ACP Power Conduit Infrastructure project at Fort Sill, Oklahoma, and has a competitive 8(a) set-aside designation. The ultimate completion date for the work is August 1, 2017.
Generated 4/3/25, 2:50 AM
Name | Description | Solicitation Number | FederalAgency | Type | PostedDate |
|---|---|---|---|---|---|
Access Control Point Design - Build (ACP D-B) | W912DY-11-R-0027 | Department of the Army Corps of Engineers Engineering Support Center Huntsville | Award Notice 1/1 | 1/6/12, 11:00 AM |
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| 2 | Change Order | $0 | 6/5/17 | |
| 1 | Change Order | $36.2k | 4/14/17 | |
| Not listed | Not listed | $98.6k | 9/29/16 |