New task order for chiller system at aberdeen proving ground

Ended Awarded Last action

Contract number
0087
Awardee
Awarding agency
Obligated
$3,528,299

Award facts

Opportunity
Contract value 83% obligated
  • $3,528,298.50 Current, with exercised options
  • $4,241,545.97 Potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
541512 Computer Systems Design Services
PSC
N059 Installation Of Equipment- Electrical And Electronic Equipment Components
Set-aside
No set-aside
Competition
Full and Open Competition · 1 offer Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Aberdeen Proving Ground, MD 21005, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Close Out 15 · Task order modification to deobligation remaining funds to prepare for closeout of task order. -$201
Change Order 14 · Additional funding for T & M clin 0013 $30,152
Exercise an Option 13 · The purpose of this modification is to exercise optional clin 4001 and fund IT in the amount of $265,734.75 for chiller system winter option 2014; and establish… $303,785
Supplemental Agreement for work within scope 12 · Emergency service order APG DPW replace chiller compressor bldg E3244. $30,000
Funding Only Action 11 · So 087-0008-0006 DPW building A316 liebert HVAC repair $25,000
Exercise an Option 10 · Exercise option clin 3001. Clin 3001 was reduced from $1,083,888.92 by $818,154.17 to $265,734.75; period of performance for clin 3001 is 1 may 2013 to 1 august… $315,735
Change Order 9 · Purpose of modification is to fund urgent service order 127-001902-0004 for compressor replacement at ARL building A120. Notice to proceed was issued by the… $53,849
Change Order 8 · Purpose of modification is to incorporate PWS REV. 7 dated 17 december 2012 and provide funds for contractor to complete emergency service orders (T & M) at DPW… $110,830
Change Order 7 · Provide additional funds for the processing of emergency service orders at APG, MD. Funds may not be used without the prior approval of the contracting officer.… $5,000
Other Administrative Action 6 · Administrative modification to identify contracting officer. $0
Change Order 5 · Descope summer and winter 2012 maintenance and services for chiller system preventive maintenance at aberdeen proving grounds, MD. Clin 1001 was decreased to… $741,175
Change Order 4 · Purpose of modification is to provide additional funds for emergency service orders for DPW chiller maintenance at aberdeen proving grounds, MD. $30,000
Supplemental Agreement for work within scope 3 · Chiller system summer option 2012; ECP 087-0003 and 0004 $97,292
Exercise an Option 2 · The purpose of this modification is to exercise the option for the preventative maintenance for the summer chiller option 2012 for the period of 14 april 2012… $983,119
Change Order 1 · Modification for two engineers in the power plant at aberdeen proving ground. $98,981
Original award $703,582
Show all 16

Quick answers

Who was awarded contract 0087?

0087 was awarded to Johnson Controls Building Automation Systems, LLC by Engineering Support Center Huntsville (US Army Corps of Engineers) on September 23, 2011.

How much is contract 0087 worth?

The government has obligated $3,528,299 on 0087. Its potential value, with all options, is $4,241,546.

Is contract 0087 an order under another contract?

Yes. 0087 is a delivery order under W912DY09D0037, an indefinite delivery contract.

Was contract 0087 competed?

The extent of competition for 0087 was full and open competition. The government received 1 offer.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award