Renovate hangar bathroom renovations, new century, KS

Ended Awarded Last action

Contract number
W912DQ23F4028
Awardee
Awarding agency
Obligated
$2,337,578

Award facts

Opportunity
Contract value 100% obligated
$2,337,577.60 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition after exclusion of sources · 1 offer Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
New Century, KS 66031, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope A00018 · Modification for room 114A exhaust to contract for new century bathroom renovations (building 21) at new century, kansas $1,973
Supplemental Agreement for work within scope A00017 · Modification for SK022 & SK023 to contract for new century bathroom renovations (building 21) at new century, kansas. $5,798
Supplemental Agreement for work within scope A00016 · Modification for floor drain/shower heights & chase doors to contract for new century bathroom renovations (building 21) at new century, kansas. $6,158
Supplemental Agreement for work within scope A00015 · Modification for janitor's sink/fire sprinkler to contract for new century bathroom renovations (building 21) at new century, kansas. $3,649
Supplemental Agreement for work within scope A00014 · Modification for SK018 & SK021 to contract for new century bathroom renovations (building 21) at new century, kansas. $13,999
Supplemental Agreement for work within scope A00013 · Modification for SK016 & SK017 contract for new century bathroom renovations (building 21) at new century, kansas. $7,615
Supplemental Agreement for work within scope A00012 · Modification for sound testing credit & misc changes to contract for new century bathroom renovations (building 21) at new century, kansas. $4,781
Supplemental Agreement for work within scope A00011 · Modification for plumbing changes to contract for new century bathroom renovations (building 21) at new century, kansas. $2,734
Supplemental Agreement for work within scope A00010 · Modification for west water heater relocation contract for new century bathroom renovations (building 21) at new century, kansas. $3,473
Supplemental Agreement for work within scope A00009 · Modification for east mech RM chase wall/asbestos east to contract for new century bathroom renovations (building 21) at new century, kansas. $37,045
Supplemental Agreement for work within scope A00008 · Modification for weather time extension SEP 23 - MAR 24 contract for new century bathroom renovations (building 21) at new century, kansas. $0
Supplemental Agreement for work within scope A00007 · Modification for OMS changes, ceiling grid, and dfountain to contract for new century bathroom renovations (building 21) at new century, kansas. $15,091
Supplemental Agreement for work within scope A00006 · Modification for misc kitchen changes to contract for new century bathroom renovations (building 21) at new century, kansas. $0
Supplemental Agreement for work within scope A00005 $68,610
Change Order A00004 · Modification for asbestos testing & abatement east to contract for new century bathroom renovations (building 21) at new century, kansas. $30,000
Change Order A00003 · Modification for descope temp facilities & clin 0004 to contract for new century bathroom renovations (building 21) at new century, kansas. -$26,638
Change Order A00002 · Modification for asbestos testing & abatement west to contract for new century bathroom renovations (building 21) at new century, kansas. $116,877
Change Order A00001 · Modification for asbestos and lead paint testing & abatem to contract for new century bathroom renovations (building 21) at new century, kansas. $10,000
Original award $2,036,412
Show all 19

About this award

This is a firm fixed-price delivery order contract awarded by the U.S. Army Corps of Engineers, Engineering District Kansas City (USACE Kansas City) to DAX / Gbab JV 3, LLC, a veteran-owned small business. The $2,337,577.60 contract is for renovations to a bathroom facility at a hangar in New Century, Kansas. The award is not a set-aside contract. DAX / Gbab JV 3, LLC has previously been awarded over $55 million in federal contracts from 2021-2023 to deliver infrastructure projects for the Department of Veterans Affairs and USACE, including renovations and modifications to VA medical centers and facilities. The company also holds a $45 million indefinite delivery contract from USACE Kansas City to provide general construction and renovation services in Kansas and Missouri.

Quick answers

Who was awarded contract W912DQ23F4028?

W912DQ23F4028 was awarded to DAX / Gbab JV 3, LLC by ENDIST Kansas City (US Army Corps of Engineers) on August 1, 2023.

How much is contract W912DQ23F4028 worth?

The government has obligated $2,337,578 on W912DQ23F4028.

Is contract W912DQ23F4028 an order under another contract?

Yes. W912DQ23F4028 is a delivery order under W912DQ22D4000, an indefinite delivery contract.

Was contract W912DQ23F4028 competed?

The extent of competition for W912DQ23F4028 was full and open competition after exclusion of sources. The government received 1 offer.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award