Seed project for the HUBZONE multiple award indefinite delivery/indefinite quantity. Building 52, infrastructure repair, fort leavenworth, kansas.

Ended Awarded Last action

Contract number
W912DQ17F4041
Awardee
Awarding agency
Obligated
$4,987,258

Award facts

Opportunity
Contract value 100% obligated
$4,987,258.05 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
HUBZone
Competition
Full and Open Competition after exclusion of sources · 5 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Kansas City, MO 64145, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Change Order A00017 · Modification for delays caused by adverse weather in excess of anticipated to contract for CAC infrastructure repair - building 52 FY17 infrastructure repairs… $0
Supplemental Agreement for work within scope A00016 · Modification for delete attic mechanical equipment; grant hall pediments; and, reduction of grant hall roof insulation to contract for CAC infrastructure repair… $30,692
Supplemental Agreement for work within scope A00015 · Modification for additional curb & sidewalk work to contract for CAC infrastructure repair - building 52 FY17 infrastructure repairs at fort leavenworth,… $7,873
Supplemental Agreement for work within scope A00013 · Modification for delays caused by adverse weather in excess of anticipated to contract for CAC infrastructure repair - building 52 FY17 infrastructure repairs… $0
Supplemental Agreement for work within scope A00014 · Modification for storm drain line 601 - deletion; differing site condition damp proofing; and, foundation drain redesign REA to contract for CAC… $138,194
Supplemental Agreement for work within scope A00012 · Modification for replace deteriorating stone; and, repair damage to scott avenue to contract for CAC infrastructure repair - building 52 FY17 infrastructure… $55,812
Supplemental Agreement for work within scope A00011 · Modification for deletion of drop off lane to contract for 451675 CAC infrastructure repair - building 52 FY17 infrastructure repairs at fort leavenworth,… $8,398
Supplemental Agreement for work within scope A00010 · Modification for differing site condition damp proofing to contract for CAC infrastructure repair - building 52 FY17 infrastructure repairs at fort leavenworth,… $0
Supplemental Agreement for work within scope A00009 · Modification for scott AVE - repair of sub-base 2 to contract for CAC infrastructure repair - building 52 FY17 infrastructure repairs at fort leavenworth,… $119,455
Supplemental Agreement for work within scope A00008 · Modification for scott avenue - repair of sub-base to contract for CAC infrastructure repair - building 52 FY17 infrastructure repairs at fort leavenworth,… $219,958
Supplemental Agreement for work within scope A00007 · Modification for miscellaneous subsurface conflicts to contract for CAC infrastructure repair - building 52 FY17 infrastructure repairs at fort leavenworth,… $50,000
Change Order A00006 · Modification for scott AVE - full depth replacement PT 2 to contract for CAC infrastructure repair - building 52 FY17 infrastructure repairs at fort… $110,693
Supplemental Agreement for work within scope A00005 · Modification for telecom work in CAC campus to contract for CAC infrastructure repair - building 52 FY17 infrastructure repairs at fort leavenworth, kansas. $164,412
Supplemental Agreement for work within scope A00004 · Modification for differing site condition damp proofing to contract for CAC infrastructure repair - building 52 FY17 infrastructure repairs at fort leavenworth,… $270,000
Supplemental Agreement for work within scope A00003 · Modification for sheridan attic beam support to contract for CAC infrastructure repair - building 52 FY17 infrastructure repairs at fort leavenworth, kansas. $22,614
Supplemental Agreement for work within scope A00002 · Modification for scott AVE - full depth replacement PT 1 to contract for CAC infrastructure repair - building 52 FY17 infrastructure repairs at fort… $250,000
Supplemental Agreement for work within scope A00001 · Modification for scott avenue full depth design to contract for CAC infrastructure repair - building 52 FY17 infrastructure repairs at fort leavenworth, kansas. $36,731
Original award $3,502,426
Show all 18

About this award

This firm fixed-price delivery order was awarded by the Department of the Army Corps of Engineers Engineering District Kansas City to Frontier-Arrowhead JVA, a Veteran Owned Business and Self-Certified HUBZone Joint Venture. The contract, valued at $4,987,258.05, is for the SEED PROJECT FOR THE HUBZONE MULTIPLE AWARD INDEFINITE DELIVERY/INDEFINITE QUANTITY, with the work to be performed in Kansas City, Missouri. The contract has a HUBZone set-aside designation and is for building 52 infrastructure repair at Fort Leavenworth, Kansas, to be completed by January 9, 2020.

Quick answers

Who was awarded contract W912DQ17F4041?

W912DQ17F4041 was awarded to Frontier-Arrowhead JVA by ENDIST Kansas City (US Army Corps of Engineers) on September 29, 2017.

How much is contract W912DQ17F4041 worth?

The government has obligated $4,987,258 on W912DQ17F4041.

Is contract W912DQ17F4041 an order under another contract?

Yes. W912DQ17F4041 is a delivery order under W912DQ17D4017, an indefinite delivery contract.

Was contract W912DQ17F4041 competed?

The extent of competition for W912DQ17F4041 was full and open competition after exclusion of sources. The government received 5 offers. It was set aside: HUBZone.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award