The purpose of this task order is to construct engineer tactical equipment maintenance facility traffic improvements at fort leonard wood, missouri.

Ended Awarded Last action

Contract number
0002
Awardee
Awarding agency
Obligated
$2,405,616

Award facts

Contract value 100% obligated
$2,405,616.44 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
HUBZone
Competition
Full and Open Competition after exclusion of sources · 2 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Phoenix, AZ 85034, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Change Order 10 · Modification for weather time extension to contract for road & traffic intersection improvements adjacent to new temf & COF projects at FT. Leonard wood,… $0
Change Order 8 · Modification for soil replacement; end of project deduct; and, roundabout landscape center to contract for road & traffic intersection improvements adjacent… $8,104
Change Order 9 · Modification for adding traffic markings and SOD; additional curbing; and, traffic marking paint to contract for road & traffic intersection improvements… $194,126
Change Order 7 · Change for street signage adjustment for road & traffic intersection improvements adjacent to new temf & COF projects at FT. Leonard wood, missouri. $6,680
Change Order 6 · Modification for bldg 986 duct tie-in to contract for road & traffic intersection improvements adjacent to new temf & COF projects at FT. Leonard wood,… $4,741
Change Order 5 · Modification for revised telecommunications rerouting and water & electrical addition to contract for road & traffic intersection improvements adjacent to new… $130,231
Change Order 4 · Modification for replacement of ductile iron water main to contract for road & traffic intersection improvements adjacent to new temf & COF projects at FT.… $124,689
Change Order 3 · Modification for concrete encased duct bank to contract for road & traffic intersection improvements adjacent to new temf & COF projects at FT. Leonard wood,… $36,006
Change Order 2 · Modification for road addition to nebraska; and, relocate 12IN waterline to contract for road & traffic intersection improvements adjacent to new temf & COF… $55,319
Change Order 1 · Modification for pot hole existing underground utilities; and, additional traffic control signs to contract for road & traffic intersection improvements… $18,079
Original award $1,827,642
Show all 11

About this award

This is a Delivery Order contract awarded by the U.S. Army Corps of Engineers (USACE) Kansas City District to Fortis Networks, Inc., a HUBZone certified small disadvantaged business. The purpose of this $2,405,616.44 firm-fixed-price task order is to construct an Engineer Tactical Equipment Maintenance Facility Traffic Improvements project at Fort Leonard Wood, Missouri. The contract is part of the USACE KC HUBZone Construction 2014-2017 multiple-award task order contract vehicle.

Quick answers

Who was awarded contract 0002?

0002 was awarded to Fortis Networks, Inc. by ENDIST Kansas City (US Army Corps of Engineers) on September 30, 2015.

How much is contract 0002 worth?

The government has obligated $2,405,616 on 0002.

Is contract 0002 an order under another contract?

Yes. 0002 is a delivery order under W912DQ14D4011, an indefinite delivery contract, on USACE KC HUBZone Construction 2014-2017.

Was contract 0002 competed?

The extent of competition for 0002 was full and open competition after exclusion of sources. The government received 2 offers. It was set aside: HUBZone.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award