FT. Leonardwood building 1010 dining facilities renovation

Ended Awarded Last action

Contract number
0002
Awardee
Awarding agency
Obligated
$7,589,400

Award facts

Contract value 100% obligated
$7,589,400.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
No set-aside
Competition
Full and Open Competition after exclusion of sources · 1 offer Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
FT LEONARD WD, MO 65473, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Close Out 17 · Modification for settlement of REA's to contract for repair and upgrade dfac, building 1010 at FT. Leonard wood, missouri. $190,000
Change Order 1T · Modification for delete some testing; and, replace wet sprinkler heads to contract for repair and upgrade dfac, building 1010 at FT. Leonard wood, missouri. -$1,377
Supplemental Agreement for work within scope 16 · Modification for credit - daikin split system to contract for repair and upgrade dfac, building 1010 at FT. Leonard wood, missouri. -$97
Change Order 1R · Modification for switch over chilled water flow to contract for repair and upgrade dfac, building 1010 at FT. Leonard wood, missouri. $13,187
Change Order 1S · Modification for panic hardware, door 112A to contract for repair and upgrade dfac, building 1010 at FT. Leonard wood, missouri. $8,864
Change Order 1Q · Modification for pipe replacement in hardstand to contract for repair and upgrade dfac, building 1010 at FT. Leonard wood, missouri. $29,927
Change Order 15 · Modification to insulate HI-temp lines to contract for repair and upgrade dfac, building 1010 at FT. Leonard wood, missouri. $8,737
Change Order 1P · Modification for relocate knox box to contract for repair and upgrade dfac, building 1010 at FT. Leonard wood, missouri. $7,442
Change Order 1N · Modification for time extension to contract for repair and upgrade dfac, building 1010 at FT. Leonard wood, missouri. $0
Change Order 1M · Modification for construct crawlspace for HI-temp lines to contract for repair and upgrade dfac, building 1010 at FT. Leonard wood, missouri. $1,079
Change Order 1L · Modification to provide additional handrail; and, loading dock plate extensions to contract for repair and upgrade dfac, building 1010 at FT. Leonard wood,… $14,332
Change Order 1K · Modification for kitchen equipment changes to contract for repair and upgrade dfac, building 1010 at FT. Leonard wood, missouri. $30,807
Change Order 1J · Change for deleting some signs for repair and upgrade dfac, building 1010 at FT. Leonard wood, missouri. -$19,309
Change Order 1H · Modification to provide furniture to contract for repair and upgrade dfac, building 1010 at FT. Leonard wood, missouri. $144,254
Change Order 1G · Modification for weed barrier under rock mulch; and, custom dishwasher table to contract for repair and upgrade dfac, building 1010 at FT. Leonard wood,… $5,283
Change Order 1F · Modification for built-in counters; and, no smoking signs to contract for repair and upgrade dfac, building 1010 at FT. Leonard wood, missouri. $6,123
Change Order 1E · Modification for provide new 3-inch CW lines to contract for repair and upgrade dfac, building 1010 at FT. Leonard wood, missouri. $98,017
Change Order 1D · Modification to excavate rock for sanitary sewer to contract for repair and upgrade dfac, building 1010 at FT. Leonard wood, missouri. $7,021
Change Order 1C · Modification for epoxy floor moisture barrier to contract for repair and upgrade dfac, building 1010 at FT. Leonard wood, missouri. $7,700
Change Order 1A · Modification for credit - delete concrete slab demo; tile changes; and, credit - stoop footings to for repair and upgrade dfac, building 1010 at FT. Leonard… -$12,669
Change Order 1B · Modification to change door 119A to contract for repair and upgrade dfac, building 1010 at FT. Leonard wood, missouri. $3,076
Change Order 14 · Modification for catv entrance to contract for repair and upgrade dfac, building 1010 at FT. Leonard wood, missouri. $7,711
Change Order 13 · Modification for provide fire alarm devices; and, tile above six feet to contract for repair and upgrade dfac, building 1010 at FT. Leonard wood, missouri. $18,115
Change Order 12 · Modification to widen freezer doors to contract for repair and upgrade dfac, building 1010 at FT. Leonard wood, missouri. $2,554
Change Order 11 · Modification for kitchen equipment changes to contract for repair and upgrade dfac, building 1010 at FT. Leonard wood, missouri. -$2,414
Change Order 10 · Modification for NEC changes to contract for repair and upgrade dfac, building 1010 at FT. Leonard wood, missouri. $0
Change Order 8 · Modification for credit - delete dock roof to contract for repair and upgrade dfac, building 1010 at FT. Leonard wood, missouri. -$10,965
Change Order 9 · Modification to provide dimmer switch to contract for repair and upgrade dfac, building 1010 at FT. Leonard wood, missouri. $293
Change Order 7 · Modification for hydronic pipe flushing to contract for repair and upgrade dfac, building 1010 at FT. Leonard wood, missouri. $5,223
Change Order 6 · Modification for infrastructure dishwasher booster heater; provide two hollow metal doors; and, copper panel buses to contract for repair and upgrade dfac,… $13,956
Change Order 5 · Modification for glycol piping to contract for repair and upgrade dfac, building 1010 at FT. Leonard wood, missouri. $14,131
Change Order 4 · Modification for mechanical changes to contract for repair and upgrade dfac, building 1010 at FT. Leonard wood, missouri. $19,081
Supplemental Agreement for work within scope 3 · FT.leonardwood BLDG1010 dining facility renovation. Modification to revise task order clause to allow for payment for materials delivered off-site. $0
Change Order 2 · Modification for additional specifications to contract for repair and upgrade dfac, building 1010 at FT. Leonard wood, missouri. $0
Other Administrative Action 1 · FLW BLDG1010 dfac renovation administrative modification to include wage rates and other clauses from solicitation. $0
Original award $6,979,318
Show all 36

About this award

This is a firm fixed-price delivery order contract awarded by the U.S. Army Corps of Engineers (USACE) to Tunista Construction LLC, a general contracting and heavy civil Native Alaskan disadvantaged business enterprise (DBE) firm. The contract, with a ceiling value of $7,589,400.00, is for the renovation of the Fort Leonard Wood Building 1010 dining facilities in Missouri. The work is being performed under the USACE Kansas City HUBZone Construction 2014-2017 contract vehicle, which is a multiple-award, indefinite-delivery, indefinite-quantity (IDIQ) contract. This award was not set aside for any specific business type.

Quick answers

Who was awarded contract 0002?

0002 was awarded to Tunista Construction LLC by ENDIST Kansas City (US Army Corps of Engineers) on September 30, 2015.

How much is contract 0002 worth?

The government has obligated $7,589,400 on 0002.

Is contract 0002 an order under another contract?

Yes. 0002 is a delivery order under W912DQ14D4010, an indefinite delivery contract, on USACE KC HUBZone Construction 2014-2017.

Was contract 0002 competed?

The extent of competition for 0002 was full and open competition after exclusion of sources. The government received 1 offer.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award