Base: replace chilled water lines specker barracks northern area. Option: replace chilled water lines specker barracks southern area at fort leonard wood, MO
Change Order
1U · Modification for unusually severe weather resulting in a time extension to contract for ugtransite chilled water line replacement specker barracks at FT.…
$0
Close Out
28 · Replace specker chilled water lines, fort leonard wood, MO, global settlement of reas in preparation for contract closeout.
$800,000
Change Order
1T · Modification for delays caused by adverse weather in excess of anticipated to contract for UG transite chilled water line replacement specker barracks at FT.…
$0
Change Order
1S · Modification for weather time extension due to delays caused by adverse weather in excess of anticipated to contract for UG transite chilled water line…
$0
Change Order
1R · Modification for turf establishment by SOD and additional sidewalks to contract for ugtransite chilled water line replacement specker barracks at FT. Leonard…
$149,322
Change Order
1Q · Modification for automatic air release vents in MH's to contract for UG transite chilled water line replacement specker barracks at FT. Leonard wood, missouri.
$40,210
Change Order
1P · Modification for exterior light pole bases to contract for UG transite chilled water line replacement specker barracks at FT. Leonard wood, missouri.
$30,426
Change Order
1N · Modification for time for delays caused by adverse weather in excess of anticipated to contract for ugtransite chilled water line replacement specker barracks…
$0
Change Order
1M · Modification for cross connection to contract for underground transite chilled water line replacement specker barracks at FT. Leonard wood, missouri.
$16,528
Change Order
1J · Modification for time extension due to unusually severe weather to contract for ugtransite chilled water line replacement specker barracks at FT. Leonard…
$0
Change Order
1H · Modification for flowable fill to contract for ugtransite chilled water line replacement specker barracks at FT. Leonard wood, missouri.
$1,579
Change Order
27 · Modification for MH 11 laterals and MH 10 laterals to contract for under ground transite chilled water line replacement specker barracks at FT. Leonard wood,…
$152,426
Change Order
1G · Modification to add GIS for option to contract for underground transite chilled water line replacement specker barracks at FT. Leonard wood, missouri.
$12,516
Change Order
1F · Modification for sump pump and electric for MH 2 and MH 6; and, main bypass to contract for underground transite chilled water line replacement specker barracks…
$32,899
Change Order
1E · Modification for repair 90 degree adapter at bldg 1704; and, MH-13 compression couplings to contract for underground transite chilled water line replacement…
$7,451
Change Order
1D · Modification for manhole (MH) 11 pipe size change to contract for under ground transite chilled water line replacement specker barracks at FT. Leonard wood,…
$6,664
Change Order
1C · Modification for weather time extension to contract for underground transite chilled water line replacement specker barracks at FT. Leonard wood, missouri.
$0
Change Order
1B · Modification for manhole(MH)-9 to MH-10 non-typical bend; and, carbon steel to yelomine & thrust block to contract for under ground transite chilled water…
$69,834
Change Order
1A · Modification for booster pumps to contract for UG transite chilled water line replacement specker barracks at FT. Leonard wood, missouri.
$115,645
Change Order
26 · Modification for weather time extension to contract for UG transite chilled water line replacement specker barracks at FT. Leonard wood, missouri.
$0
Change Order
25 · Modification to delete manholes MH5A and MH10A to contract for ugtransite chilled water line replacement specker barracks at FT. Leonard wood, missouri.
-$12,311
Change Order
24 · Modification for carbon steel rfso flange use; compression coupling use; and material increase to contract for UG transite chilled water line replacement…
$39,609
Change Order
23 · Modification for sump pumps with elec. @ MH's 4, 7, 8, 13 to contract for UG transite chilled water line replacement specker barracks at FT. Leonard wood,…
$50,122
Change Order
22 · Modification for RE-route trench & pipe around ADA ramp to contract for UG transite chilled water line replacement specker barracks at FT. Leonard wood,…
$2,088
Change Order
21 · Modification for relocate fence at jobsite staging area to contract for ugtransite chilled water line replacement specker barracks at FT. Leonard wood,…
$4,231
Change Order
20 · Modification for credit for two 45 degree fittings; delete gate valves and bypass piping; and, change from gate valves to butterfly valves to contract for…
-$33,430
Change Order
19 · Modification for RE work from MH4 back to MH3 to contract for ugtransite chilled water line replacement specker barracks at FT. Leonard wood, missouri.
$231,004
Change Order
18 · Modification to insulate hthw lines in MH's 4, 6, 7, 8,9 to contract for UG transite chilled water line replacement specker barracks at FT. Leonard wood,…
$72,371
Change Order
17 · Modification for install sump pump between MH1 & chiller to contract for ugtransite chilled water line replacement specker barracks at FT. Leonard wood,…
$1,975
Change Order
16 · Modification for differing site condition at MH 7 to contract for ugtransite chilled water line replacement specker barracks at FT. Leonard wood, missouri.
$30,078
Change Order
15 · Modification for differing site condition on laterals to contract for ugtransite chilled water line replacement specker barracks at FT. Leonard wood, missouri.
$67,699
Change Order
14
-$431
Change Order
13 · Modification for damaged piping due to hot water temp to contract for ugtransite chilled water line replacement specker barracks at FT. Leonard wood, missouri.
$20,000
Change Order
12 · Modification due to unusually severe weather resulting in a weather time extension to contract for ugtransite chilled water line replacement specker barracks at…
$0
Change Order
11 · Modification for rerouting of new CWR & CW piping MH4-MH5 to contract for ugtransite chilled water line replacement specker barracks at FT. Leonard wood,…
$43,423
Change Order
10 · Modification for delete 16 inch shutoff valves at MH 4 to contract for ugtransite chilled water line replacement specker barracks at FT. Leonard wood, missouri.
-$22,087
Change Order
9 · The MOD is to add geospatial deliverables. Contract for ugtransite chilled water line replacement specker barracks at FT. Leonard wood, missouri.
$7,653
Change Order
8 · Modification for rfos steel flanges and yelomine adapters to contract for ugtransite chilled water line replacement specker barracks at FT. Leonard wood,…
$84,581
Change Order
7 · Modification for revised differing site conditions to contract for ugtransite chilled water line replacement specker barracks at FT. Leonard wood, missouri.
$87,474
Change Order
6 · Modification for unusually severe weather resulting in a time extension to contract for ugtransite chilled water line replacement specker barracks at FT.…
$0
Other Administrative Action
5 · Modification for ssho requirement and QC responsibilities to contract for ugtransite chilled water line replacement specker barracks, fort leonard wood,…
$0
Exercise an Option
4 · Replace chilled water lines. The purpose of this modification is to exercise option clin 0002.
$2,816,248
Other Administrative Action
3 · Modification to the field office overhead method in SCR_CT_002
$0
Supplemental Agreement for work within scope
2
$0
Supplemental Agreement for work within scope
1 · Modification to extend the government's right to exercise option clin 0002
$0
Original award
$3,442,080
Show all 46
Quick answers
Who was awarded contract 0002?
0002 was awarded to HGL Construction Inc. by ENDIST Kansas City (US Army Corps of Engineers) on September 27, 2014.
How much is contract 0002 worth?
The government has obligated $8,367,876 on 0002.
Is contract 0002 an order under another contract?
Yes. 0002 is a delivery order under W912DQ14D4005, an indefinite delivery contract, on USACE KC SDVOSB Construction 2014-2017.
Was contract 0002 competed?
The extent of competition for 0002 was full and open competition after exclusion of sources. The government received 4 offers. It was set aside: Service-Disabled Veteran-Owned Small Business.