Base: replace chilled water lines specker barracks northern area. Option: replace chilled water lines specker barracks southern area at fort leonard wood, MO

Ended Awarded Last action

Contract number
0002
Awardee
Awarding agency
Obligated
$8,367,876

Award facts

Opportunity
Contract value 100% obligated
$8,367,875.63 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
236220 Commercial and Institutional Building Construction
PSC
Y1JZ Construction Of Miscellaneous Buildings
Set-aside
Service-Disabled Veteran-Owned Small Business
Competition
Full and Open Competition after exclusion of sources · 4 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
FT LEONARD WD, MO 65473, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Change Order 1U · Modification for unusually severe weather resulting in a time extension to contract for ugtransite chilled water line replacement specker barracks at FT.… $0
Close Out 28 · Replace specker chilled water lines, fort leonard wood, MO, global settlement of reas in preparation for contract closeout. $800,000
Change Order 1T · Modification for delays caused by adverse weather in excess of anticipated to contract for UG transite chilled water line replacement specker barracks at FT.… $0
Change Order 1S · Modification for weather time extension due to delays caused by adverse weather in excess of anticipated to contract for UG transite chilled water line… $0
Change Order 1R · Modification for turf establishment by SOD and additional sidewalks to contract for ugtransite chilled water line replacement specker barracks at FT. Leonard… $149,322
Change Order 1Q · Modification for automatic air release vents in MH's to contract for UG transite chilled water line replacement specker barracks at FT. Leonard wood, missouri. $40,210
Change Order 1P · Modification for exterior light pole bases to contract for UG transite chilled water line replacement specker barracks at FT. Leonard wood, missouri. $30,426
Change Order 1N · Modification for time for delays caused by adverse weather in excess of anticipated to contract for ugtransite chilled water line replacement specker barracks… $0
Change Order 1M · Modification for cross connection to contract for underground transite chilled water line replacement specker barracks at FT. Leonard wood, missouri. $16,528
Change Order 1J · Modification for time extension due to unusually severe weather to contract for ugtransite chilled water line replacement specker barracks at FT. Leonard… $0
Change Order 1H · Modification for flowable fill to contract for ugtransite chilled water line replacement specker barracks at FT. Leonard wood, missouri. $1,579
Change Order 27 · Modification for MH 11 laterals and MH 10 laterals to contract for under ground transite chilled water line replacement specker barracks at FT. Leonard wood,… $152,426
Change Order 1G · Modification to add GIS for option to contract for underground transite chilled water line replacement specker barracks at FT. Leonard wood, missouri. $12,516
Change Order 1F · Modification for sump pump and electric for MH 2 and MH 6; and, main bypass to contract for underground transite chilled water line replacement specker barracks… $32,899
Change Order 1E · Modification for repair 90 degree adapter at bldg 1704; and, MH-13 compression couplings to contract for underground transite chilled water line replacement… $7,451
Change Order 1D · Modification for manhole (MH) 11 pipe size change to contract for under ground transite chilled water line replacement specker barracks at FT. Leonard wood,… $6,664
Change Order 1C · Modification for weather time extension to contract for underground transite chilled water line replacement specker barracks at FT. Leonard wood, missouri. $0
Change Order 1B · Modification for manhole(MH)-9 to MH-10 non-typical bend; and, carbon steel to yelomine & thrust block to contract for under ground transite chilled water… $69,834
Change Order 1A · Modification for booster pumps to contract for UG transite chilled water line replacement specker barracks at FT. Leonard wood, missouri. $115,645
Change Order 26 · Modification for weather time extension to contract for UG transite chilled water line replacement specker barracks at FT. Leonard wood, missouri. $0
Change Order 25 · Modification to delete manholes MH5A and MH10A to contract for ugtransite chilled water line replacement specker barracks at FT. Leonard wood, missouri. -$12,311
Change Order 24 · Modification for carbon steel rfso flange use; compression coupling use; and material increase to contract for UG transite chilled water line replacement… $39,609
Change Order 23 · Modification for sump pumps with elec. @ MH's 4, 7, 8, 13 to contract for UG transite chilled water line replacement specker barracks at FT. Leonard wood,… $50,122
Change Order 22 · Modification for RE-route trench & pipe around ADA ramp to contract for UG transite chilled water line replacement specker barracks at FT. Leonard wood,… $2,088
Change Order 21 · Modification for relocate fence at jobsite staging area to contract for ugtransite chilled water line replacement specker barracks at FT. Leonard wood,… $4,231
Change Order 20 · Modification for credit for two 45 degree fittings; delete gate valves and bypass piping; and, change from gate valves to butterfly valves to contract for… -$33,430
Change Order 19 · Modification for RE work from MH4 back to MH3 to contract for ugtransite chilled water line replacement specker barracks at FT. Leonard wood, missouri. $231,004
Change Order 18 · Modification to insulate hthw lines in MH's 4, 6, 7, 8,9 to contract for UG transite chilled water line replacement specker barracks at FT. Leonard wood,… $72,371
Change Order 17 · Modification for install sump pump between MH1 & chiller to contract for ugtransite chilled water line replacement specker barracks at FT. Leonard wood,… $1,975
Change Order 16 · Modification for differing site condition at MH 7 to contract for ugtransite chilled water line replacement specker barracks at FT. Leonard wood, missouri. $30,078
Change Order 15 · Modification for differing site condition on laterals to contract for ugtransite chilled water line replacement specker barracks at FT. Leonard wood, missouri. $67,699
Change Order 14 -$431
Change Order 13 · Modification for damaged piping due to hot water temp to contract for ugtransite chilled water line replacement specker barracks at FT. Leonard wood, missouri. $20,000
Change Order 12 · Modification due to unusually severe weather resulting in a weather time extension to contract for ugtransite chilled water line replacement specker barracks at… $0
Change Order 11 · Modification for rerouting of new CWR & CW piping MH4-MH5 to contract for ugtransite chilled water line replacement specker barracks at FT. Leonard wood,… $43,423
Change Order 10 · Modification for delete 16 inch shutoff valves at MH 4 to contract for ugtransite chilled water line replacement specker barracks at FT. Leonard wood, missouri. -$22,087
Change Order 9 · The MOD is to add geospatial deliverables. Contract for ugtransite chilled water line replacement specker barracks at FT. Leonard wood, missouri. $7,653
Change Order 8 · Modification for rfos steel flanges and yelomine adapters to contract for ugtransite chilled water line replacement specker barracks at FT. Leonard wood,… $84,581
Change Order 7 · Modification for revised differing site conditions to contract for ugtransite chilled water line replacement specker barracks at FT. Leonard wood, missouri. $87,474
Change Order 6 · Modification for unusually severe weather resulting in a time extension to contract for ugtransite chilled water line replacement specker barracks at FT.… $0
Other Administrative Action 5 · Modification for ssho requirement and QC responsibilities to contract for ugtransite chilled water line replacement specker barracks, fort leonard wood,… $0
Exercise an Option 4 · Replace chilled water lines. The purpose of this modification is to exercise option clin 0002. $2,816,248
Other Administrative Action 3 · Modification to the field office overhead method in SCR_CT_002 $0
Supplemental Agreement for work within scope 2 $0
Supplemental Agreement for work within scope 1 · Modification to extend the government's right to exercise option clin 0002 $0
Original award $3,442,080
Show all 46

Quick answers

Who was awarded contract 0002?

0002 was awarded to HGL Construction Inc. by ENDIST Kansas City (US Army Corps of Engineers) on September 27, 2014.

How much is contract 0002 worth?

The government has obligated $8,367,876 on 0002.

Is contract 0002 an order under another contract?

Yes. 0002 is a delivery order under W912DQ14D4005, an indefinite delivery contract, on USACE KC SDVOSB Construction 2014-2017.

Was contract 0002 competed?

The extent of competition for 0002 was full and open competition after exclusion of sources. The government received 4 offers. It was set aside: Service-Disabled Veteran-Owned Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award