Change Order
22 · Modification for removal of remaining closeout reqs. To 071502 - AIT complex 2, PH 1 - BN HQ at fort leonard wood, missouri
-$10,000
Change Order
1B · Modification for landscape changes to contract for advanced individual trainee barracks complex 2, phase 1 - BN HQ, fort leonard wood, missouri at FT. Leonard…
$7,990
Change Order
1A · Modification to improve sound transmission to contract for advanced individual trainee barracks complex 2, phase 1 - BN HQ, fort leonard wood, missouri at FT.…
$9,171
Change Order
21 · Modification for sound dampening/parking lot drainage to contract for advanced individual trainee barracks complex 2, phase 1 - BN HQ, fort leonard wood,…
$7,544
Change Order
20 · Change for occupancy sensor and partition circuits for advanced individual trainee barracks complex 2, phase 1 - BN HQ, at FT. Leonard wood, missouri.
$7,513
Change Order
19 · Change for weather time extension for advanced individual trainee barracks complex 2, phase 1 - BN HQ, at fort leonard wood, missouri.
$0
Change Order
18 · Contract for advanced individual trainee barracks complex 2, phase 1 - BN HQ, fort leonard wood, missouri at FT. Leonard wood, missouri. Reference no. R00018…
$8,593
Change Order
17 · Modification for weather time extension due to unusually severe weather to contract for advanced individual trainee barracks complex 2, phase 1 - BN HQ, fort…
$0
Change Order
16 · Modification for for delays caused by adverse weather in excess of anticipated resulting in a time extension to contract for advanced individual trainee…
$0
Change Order
15 · Modification for ventilation addition to contract for advanced individual trainee barracks complex 2, phase 1 - BN HQ, fort leonard wood, missouri at FT.…
$1,636
Change Order
14 · Modification for louver adjustment; anti-static flooring TER room addition; chair rail addition; and, hydrant to contract for advanced individual trainee…
$17,578
Change Order
13 · Modification for communications duct bank to contract for advanced individual trainee barracks complex 2, phase 1 - BN HQ, fort leonard wood, missouri at FT.…
$4,033
Change Order
12 · Modification for weather time extension due to unusually severe weather to contract for advanced individual trainee barracks complex 2, phase 1 - BN HQ, fort…
$0
Change Order
11 · Modification for latrine tile change to contract for advanced individual trainee barracks complex 2, phase 1 - BN HQ, fort leonard wood, missouri at FT. Leonard…
$3,272
Change Order
10 · Modification for drainage; and, lockset change to contract for advanced individual trainee barracks complex 2, phase 1 - BN HQ, fort leonard wood, missouri at…
$23,425
Supplemental Agreement for work within scope
8 · Modification to install louver to contract for advanced individual trainee barracks complex 2, phase 1 - BN HQ, fort leonard wood, missouri at FT. Leonard wood,…
$1,455
Supplemental Agreement for work within scope
9 · Modification for masonary veneer anchors to contract for advanced individual trainee barracks complex 2, phase 1 - BN HQ, fort leonard wood, missouri at FT.…
$21,589
Change Order
7 · Modification to install recirculation pump to contract for advanced individual trainee barracks complex 2, phase 1 - BN HQ, fort leonard wood, missouri at FT.…
$10,580
Change Order
6 · Modification for SOD placement to contract for advanced individual trainee barracks complex 2, phase 1 - BN HQ, fort leonard wood, missouri at FT. Leonard wood,…
$49,368
Change Order
5 · Modification extends the time for performance allowed for delays caused by adverse weather in excess of anticipated during the period 19 december 2014 through…
$0
Change Order
4 · Modification for time extension to contract for advanced individual trainee barracks complex 2, phase 1 - BN HQ, fort leonard wood, missouri at FT. Leonard…
$0
Change Order
3 · Modification for ADA parking stall redesign; and, credit for over excavation to contract for advanced individual trainee barracks complex 2, phase 1 - BN HQ,…
$12,590
Change Order
2 · Modification for replace clay tile with 8" PVC; comm OSP copper deletion; and, mobilization delay time extension to contract for advanced individual trainee…
$43,115
Change Order
1 · Modification for brace along grid 6 to contract for advanced individual trainee barracks complex 2, phase 1 - BN HQ, fort leonard wood, missouri at FT.…
$2,423
Original award
$4,796,238
Show all 25
Quick answers
Who was awarded contract 0004?
0004 was awarded to Zieson Construction Company, LLC by ENDIST Kansas City (US Army Corps of Engineers) on December 19, 2014.
How much is contract 0004 worth?
The government has obligated $5,018,113 on 0004.
Is contract 0004 an order under another contract?
Yes. 0004 is a delivery order under W912DQ14D4000, an indefinite delivery contract, on USACE KC SDVOSB Construction 2014-2017.
Was contract 0004 competed?
The extent of competition for 0004 was full and open competition after exclusion of sources. The government received 3 offers. It was set aside: Service-Disabled Veteran-Owned Small Business.