Fusrap ST. Louis north county (ATP #1).

Ended Awarded Last action

Contract number
0001
Awardee
Awarding agency
Obligated
$30,147,829

Award facts

Opportunity
Contract value 100% obligated
$30,147,829.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
NAICS code
562910 Remediation Services
PSC
F108 Environmental Systems Protection- Environmental Remediation
Set-aside
No set-aside
Competition
Full and Open Competition · 4 offers Multiple Award, Fair Opportunity
Pricing
Cost Plus Fixed Fee
Place of performance
Clayton, MO 63105, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope 25 · This is a modification to definitize WVN's 17 - 19 for the ST. Louis fusrap north county sites. $494,239
Supplemental Agreement for work within scope 24 · The purpose of this modification is to: a. Definitize WVN¿s 14 - 16. B. Increase the negotiated ceiling and obligates previously negotiated funding, in… $781,661
Funding Only Action 23 · This modification funds previously negotiated capacity that was incorporated in modification 20 for the ST. Louis fusrap north county sites (norco). $862,141
Funding Only Action 22 · This modification funds previously negotiated capacity negotiated under modification 20, dated 14 april 2014. All work performed under this modification shall… $1,000,000
Funding Only Action 21 · This modification obligates previously negotiated capacity in the amount of $600,000.00. This work was negotiated under modification 20. $600,000
Supplemental Agreement for work within scope 20 · The purpose of this modification is to definitize WVN¿s 06¿ 13, increase the negotiated ceiling, and fund previously negotiated capacity for the ST. Louis… $3,630,000
Other Administrative Action 19 · The purpose of this modification is to recognize the transfer of assets between shaw environmental & infrastructure, INC. And chicago bridge & iron federal… $0
Funding Only Action 18 $1,350,000
Funding Only Action 17 · This modification obligates previously negotiated capacity for the ST. Louis fusrap north county site (norco) in accordance with authority to proceed 019. $1,291,000
Funding Only Action 16 · This modification incorporates previously funded capacity in accordance with ATP 18 $62,000
Funding Only Action 15 · This modification obligates previously negotiated capacity for the ST. Louis fusrap north county site (norco) in accordance with authority to proceed 017. $350,000
Funding Only Action 14 · This modification is to obligate previously negotiated work for the ST. Louis fusrap north county site (norco), in accordance with ATP 016. $779,000
Funding Only Action 13 · This modification is to obligate previously negotiated capacity for the ST. Louis fusrap north county site (norco), located in ST. Louis, missouri in order to… $1,250,000
Funding Only Action 12 · This modification obligates previously negotiated capacity in the amount of $1,000,000.00, for the ST. Louis fusrap north county sites (norco) in accordance WIT… $1,000,000
Funding Only Action 11 · This modification is to partially obligate funds to fund the FY13 general conditinos for the ST. Louis fusrap north county site. The work includes the removal… $1,000,000
Funding Only Action 10 · Modification to increase obligated funds against previously negotiated capacity on cpff to 0001, IAW ATP011, dated 16 july 2012 $400,000
Supplemental Agreement for work within scope 9 · Fusrap norco (ST. Louis north county) increase in negotiated capacity, reference authority to proceed (ATP) #010, dated 29 FEB 12 $0
Funding Only Action 8 · Obligation of previously negotiated capacity for work and services for the fusrap ST. Louis north county (norco) site, located in ST. Louis county, missouri, in… $3,483,733
Funding Only Action 7 · FY10-STL norco fusrap-52K6B3-ATP008 $275,000
Funding Only Action 6 · FY10-STL norco fusrap-increased obligated amount against previously negotiated task order capacity, IAW ATP 007 $1,716,000
Supplemental Agreement for work within scope 5 · This modification is to increase negotiated capacity and obligate previously negotiated capacity on task order 0001, for the ST. Louis norco project, located in… $2,000,000
Funding Only Action 4 · This modification is to obligate previously negotiated capacity to the ST. Louis norco project for the latty AVE. Fusrap, in accordance with ATP #005. $1,030,200
Funding Only Action 3 · FY11-STL norco fusrap-52K6B3 ATP 004 funding of previously negotiated capcity; administrative changes in PD2 made decreases in the PD2 system itself and does… $2,509,000
Change Order 2 · ATP #3, increased negotiated cost; zero funding. $0
Change Order 1 · ATP #2, additional negotiated cost and funding. $4,205,000
Original award $78,855
Show all 26

Quick answers

Who was awarded contract 0001?

0001 was awarded to Aptim Federal Services, LLC by ENDIST Kansas City (US Army Corps of Engineers) on June 28, 2010.

How much is contract 0001 worth?

The government has obligated $30,147,829 on 0001.

Is contract 0001 an order under another contract?

Yes. 0001 is a delivery order under W912DQ10D3007, an indefinite delivery contract.

Was contract 0001 competed?

The extent of competition for 0001 was full and open competition. The government received 4 offers.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award