Repair miner road sheridan to burrill, fort sill, OK

Ended Awarded Last action

Contract number
0003
Awardee
Awarding agency
Obligated
$6,573,805

Award facts

Contract value 63% obligated
  • $6,573,804.94 Current, with exercised options
  • $10,396,981.02 Potential, with all options
Completion date 100% complete
Current and potential, with all options
Set-aside
Total Small Business
Competition
Full and Open Competition after exclusion of sources · 2 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Lawton, OK 73501, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Other Administrative Action 1M · TE016 - weather time extension APR 18 - JUN 18 $0
Other Administrative Action 1L · TE014 - 1L - weather time extension JAN 18 - MAR 18 $0
Other Administrative Action 1K · TE012 - QA deficiency 002 -$11,399
Other Administrative Action 1J · TE013 - phase 4 sub-base failure $126,117
Other Administrative Action 1H · TE009 - phase 5 sub-base failure minor road $46,565
Supplemental Agreement for work within scope 1G · TE008 thompson hill north pad -$6,774
Supplemental Agreement for work within scope 1F · TE010 - weather time extension SEP 17 - NOV 17 $0
Other Administrative Action 1E · TE007 weather time extension SEP 16 - JUL 17 $0
Supplemental Agreement for work within scope 1D · TE006 phase 3 - subbase failure, miner road $25,164
Change Order 1C · Phase 1 /city of lawton $34,331
Other Administrative Action 1B · Phase 1 and 2 minor road $192,345
Other Administrative Action 2 · Repair roads and ranges at fort sill. Admin MOD to incorporate wage rates from time of contract award. $0
Other Administrative Action 1 · Administrative MOD to correct period of performance at no additional cost. Repair miner road sheridan to burrill. $0
Supplemental Agreement for work within scope 1A · MOD 1A TE001 electric fires range parking $0
Original award $6,167,456
Show all 15

About this award

The U.S. Army Corps of Engineers awarded a $10,396,981.02 firm fixed-price delivery order contract to Southwind Construction Services, LLC, a woman-owned small business, for the repair of Miner Road from Sheridan to Burrill at Fort Sill in Lawton, Oklahoma. The contract, which has a completion date of July 20, 2018, was set aside for total small business participation.

Southwind Construction Services is a tribally owned, minority-owned, and Native American-owned limited liability company based in Edmond, Oklahoma. The company provides a range of construction services to federal agencies, including the Department of Defense and Department of Transportation, and holds several significant indefinite delivery/indefinite quantity (IDIQ) contracts with the U.S. Army Corps of Engineers and the U.S. Air Force for civil works, design-build, and roof replacement projects across the Midwest region.

Quick answers

Who was awarded contract 0003?

0003 was awarded to Southwind Construction Services, LLC by ENDIST Tulsa (US Army Corps of Engineers) on September 30, 2015.

How much is contract 0003 worth?

The government has obligated $6,573,805 on 0003. Its potential value, with all options, is $10,396,981.

Is contract 0003 an order under another contract?

Yes. 0003 is a delivery order under W912BV15D0024, an indefinite delivery contract.

Was contract 0003 competed?

The extent of competition for 0003 was full and open competition after exclusion of sources. The government received 2 offers. It was set aside: Total Small Business.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award