Delivery Order W912BV11D0012-0002
Award Date 9/8/14
Potential Completion Date 1/16/18
Potential Value $3.4M
Funding Federal Agency
Contracting Federal Agency
Awardee
Ultimate Awardee
Not listed NAICS Category
Set-Aside Type
8(a) Sole Source
Federal Contract Vehicle
Extent Competed
Not Available for Competition
Major Defense Program
Not listed Pricing Type
Firm Fixed Price
Place of Performance
Keota, OK 74941, USA
Solicitation Procedures
Only One Source
Number Of Offers Received
1
Legislative Mandate
Davis Bacon Act
National Interest Action
Not listed Research Type
Not listed Primary Consortia Member
Not listed Similar Awards
- This is a $2,247,212.00 firm fixed price contract awarded by the U.S. Army Corps of Engineers (USACE) to Knight Const. & Supply, Inc. (doing business as Knight Construction & Supply) for the installation of new digital governor programmable logic controllers (PLCs) at the Dardanelle Powerhouse in Arkansas. The contract has a total small business set-aside designation. The original solicitation was a sources sought notice seeking information to replace and commission the existing...
- The U.S. Army Corps of Engineers, Little Rock District, awarded a $217,120 firm fixed-price purchase order to Reivax North America Inc. for modernization of the station service governor system at Bull Shoals Powerhouse in Lakeview, Arkansas. The contract, awarded September 24, 2024, requires replacement of two digital governors and associated hydraulic and feedback devices within one calendar year, with a completion date of September 23, 2025. The modernization effort incorporates clause...
- This is a firm fixed-price delivery order contract awarded by the Department of the Army Corps of Engineers to American Governor Company, a subsidiary of Emerson Electric Co.'s White-Rodgers Division. The $828,580.21 contract is for digital governors at the Ft. Randall Powerhouse in Pickstown, South Dakota. The contract has no set-aside designation and was awarded on November 14, 2019 with a completion date of November 30, 2021. American Governor Company is a manufacturer of governors and...
- Olsson Industrial Electric, Inc. received a $48.2 million firm fixed-price definitive contract from the U.S. Army Corps of Engineers on March 9, 2021, to upgrade governors, exciters, and powerhouse controls at the McNary Dam hydroelectric facility in Umatilla, Oregon. The work, scheduled for completion by April 28, 2026, encompasses modernizing digital governors and static exciters across all fourteen main generator units, replacing legacy governor and exciter control systems with modernized...
- This firm-fixed-price delivery order, valued at $165,996.31, was awarded by the U.S. Army Corps of Engineers to the American Governor Company, a manufacturer of governors and related equipment for power generation facilities. The contract provides for digital governor commissioning services for Units 1-6 at the LGA facility. The award was not set aside for any specific business type. American Governor Company has previously supported federal agencies such as the Department of Energy, Bureau of...
- The Department of the Interior, Bureau of Indian Affairs Western Region awarded a $340,945 firm fixed-price purchase order to Siemens Industry, Inc. on May 30, 2024, for the replacement and retrofit of hydroelectric governor controllers at dams operated by the Colorado River Agency. The contract, which is not set-aside designated, calls for Siemens to assess existing infrastructure, develop an implementation plan, and install and configure Siemens programmable logic controller (PLC) governors on...
- This is a $113,128.15 firm fixed price delivery order awarded by the U.S. Army Corps of Engineers to the American Governor Company, a subsidiary of Emerson Electric Co. White-Rodgers Division. The contract is for digital governor commissioning services at the Lower Monumental facility in Kahlotus, Washington, with a completion date of July 31, 2019. While this contract does not have a set-aside designation, American Governor Company has been awarded other federal contracts, both as a prime and...
- The U.S. Army Corps of Engineers Engineering District Tulsa awarded Eaton Corporation a $43,230 firm fixed price delivery order for circuit breakers refurbishment/rebuilding at Fort Gibson Powerhouse and Broken Bow Powerhouse in Oklahoma. As the prime contractor, Eaton Corporation will perform the requested services to refurbish and rebuild circuit breakers at the two powerhouse locations. The delivery order was awarded on September 12, 2019 under the Corps of Engineers' operations and...
- This is a Delivery Order contract awarded by the U.S. Army Corps of Engineers (USACE) to American Governor Company, a subsidiary of Emerson Electric Co. White-Rodgers Division, for the provision of Pelton Retrofit Equipment for the Big Bend Project. The contract has a Firm Fixed Price of $830,628.75 and a completion date of June 20, 2017. The contract was not set aside for any specific business type. American Governor Company has a history of providing governor equipment, commissioning services,...
- The U.S. Army Corps of Engineers, Tulsa District, awarded a $60,672 firm fixed-price purchase order to Ruhrpumpen, Inc. for pump refurbishment work at Fort Gibson Powerhouse in Oklahoma. This contract modification de-obligates funds from a previous contract (W912BV24P0059) and represents a Total Small Business set-aside. The work involves altering and refurbishing pump shafts critical to the powerhouse operations, with performance scheduled for completion by July 31, 2024, and work to be...
- Army POCA Construction Services 2011-2016Master IDIQ
- W912BV11D0012Indefinite Delivery Contract
- W912BV11D0012-0002Delivery Order
. DIGITAL GOVERNORS UPGRADES AT ROBERT S KERR, TENKILLER, EUFAULA & DENISON POWERHOUSES
Posted 9/13/14
Mod # | Description | ReasonForModification | Federal Obligation | Date |
|---|---|---|---|---|
| 1A | Change Order | ($10k) | 10/7/16 | |
| 1 | Exercise an Option | $841.2k | 9/30/14 | |
| Not listed | Not listed | $2.4m | 9/13/14 |