Magnolia relief well collector system, magnolia levee, magnolia, OH

Ended Awarded Last action

Contract number
0018
Awardee
Awarding agency
Obligated
$939,221

Award facts

Opportunity
Contract value 100% obligated
$939,220.86 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
NAICS code
237990 Other Heavy and Civil Engineering Construction
PSC
Y1PZ Construction Of Other Non-Building Facilities
Set-aside
HUBZone
Competition
Full and Open Competition after exclusion of sources · 6 offers Multiple Award, Fair Opportunity
Pricing
Firm Fixed Price
Place of performance
Magnolia, OH 44643, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope 11 · Project, magnolia relief well collector system, modification finalizes contract quantities. -$6,461
Other Administrative Action 10 · Administrative modification to update issuing office information. $0
Other Administrative Action 9 · Magnolia levee relief well collector system, contractor defaulted, surety completing work. $0
Supplemental Agreement for work within scope 7 · Project: magnolia relief well collector system¿ modification incorporates pump test specification changes. -$6,474
Supplemental Agreement for work within scope 8 · Project: magnolia relief well collector system¿ modification definitizes modification 05 for additional well development costs. -$3,407
Supplemental Agreement for work within scope 6 $6,404
Change Order 5 · Project: magnolia relief well collector system¿ modification incorporates additional well development into the contract. $40,000
Other Administrative Action 1A · Administrative change to update the task order delivery date to 30 SEP 13. $0
Supplemental Agreement for work within scope 4 · Project: magnolia relief well collector system¿ modification extends the contract completion date. $0
Supplemental Agreement for work within scope 3 · Project: magnolia relief well collector system modification settles all portions of undefinitized modification 02. $1,016
Change Order 2 · Project: magnolia relief well collector system¿ modification directs repairs to 48 inch drain pipe to facilitate other contract work. $8,000
Change Order 1 · Project: magnolia relief well collector system - modification changes installation details for the manhole relief well ladders required under the contract. $5,769
Original award $894,375
Show all 13

Quick answers

Who was awarded contract 0018?

0018 was awarded to Tab Construction Company, Inc. by ENDIST Huntington (US Army Corps of Engineers) on September 27, 2012.

How much is contract 0018 worth?

The government has obligated $939,221 on 0018.

Is contract 0018 an order under another contract?

Yes. 0018 is a delivery order under W9123710D0014, an indefinite delivery contract.

Was contract 0018 competed?

The extent of competition for 0018 was full and open competition after exclusion of sources. The government received 6 offers. It was set aside: HUBZone.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award