Double v hull do 300- nonrecurring engineering and long lead materials

Ended Awarded Last action

Contract number
0300
Awardee
Awarding agency
Obligated
$227,033,707

Award facts

Contract value 100% obligated
$227,033,707.00 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Funding agency
TACOM Life Cycle Management Command Army Materiel Command, Department of Defense
NAICS code
336992 Military Armored Vehicle, Tank, and Tank Component Manufacturing
PSC
2350 Combat, Assault, And Tactical Vehicles, Tracked
Set-aside
No set-aside
Competition
Not Competed Only One Source
Pricing
Cost Plus Fixed Fee
Place of performance
Sterling Heights, MI 48310, USA
Defense program
Stryker Family of Vehicles
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope 29 · Double v hull $48,855
Funding Only Action 28 · DE-obligation of funds -$35,684
Other Administrative Action 27 · Revision of cdrl V011 which deletes the delivery of a demil video update. $0
Supplemental Agreement for work within scope 26 · This bilateral modification 26 is being issued to settle the contractor's request for equitable adjustment under proposal w-0082-R9/CCP 1236 for DVH… -$1,171,079
Funding Only Action 23 · Deobligation of excess funds for DVH stryker production NRE tooling and fixtures. -$4,933,056
Other Administrative Action 24 · MOD to revise addressee on cdrl V004- geometric three dimensional drawings $0
Funding Only Action 22 · MOD to fund cost overrun on clin 0004AA- apmi $13,357
Supplemental Agreement for work within scope 20 · Remove full text of statement of work and only cite by paragraphs as full text is incorporated into the base requirements contract. $0
Funding Only Action 21 · Administrative fund swap $0
Change Order 19 · Change order to fund additional production tooling/production non-recurring engineering for the stryker double-v hull as a result of a specification change. $1,326,574
Definitize Change Order 18 · Settlement of contractors equitable adjustment for stryker double-v hull development and prototypes $28,320,615
Supplemental Agreement for work within scope 17 · Revise the not to exceed price to include advanced precision mortar initiative (apmi) efforts. The value of NTE price did not change. -$285,636
Supplemental Agreement for work within scope 16 · Revise not to exceed price for design, development and prototypes of stryker double-v hull (DVH) vehicles. $40,000,000
Change Order 15 · Revise clin name, scope of work for production NRE/tooling and revise delivery locations for DVH prototypes $0
Change Order 14 · Revise DVH SOW for C4ISR kit development, apmi kit delivery schedule, add government test PLA by reference and add a DVH vehicles as GFE. $0
Change Order 13 · Design a-kit for accelerated precision mortar initiative (apmi) to allow for installation on DVH design, integrate kit into drawings and develop 2 prototypes. $285,636
Other Administrative Action 12 · Update attachement 0002 to revise the mortar carrier vehicle that will be provided as a government furnished vehicle. $0
Change Order 11 · Incremental funding for the non-recurring engineering for DVH, remove 2 cdrls and revise prototype delivery date $19,566,620
Change Order 10 · Stryker double-v hull (DVH). Fund procurement of 4 set of kits to support operational testing and clarify number and configurations of prototypes. $154,828
Change Order 9 · Revise SOW and prototype delivery locations and incremental funding for stryker DVH. $24,000,000
Funding Only Action 8 · Incremental funding $120,000
Change Order 7 · Incremental funding for stryker double-v hull and administrative changes to revise cdrls $3,020,675
Change Order 6 · Administrative fund swap, incremental funding and SOW revision of stryker double-v hull development effort $23,700,000
Change Order 5 · Administrative fund swap, deobligate funds and move to delivery orders 0036 & 0046, update prototype delivery schedules and revise period of performance for… -$28,749,945
Change Order 4 · Add 14 prototype deliverables and incremental funding $52,445,520
Funding Only Action 3 · Incremental funding for non-recurring enginerring of stryker double-v hull. $10,950,000
Funding Only Action 2 · Administrative fund swap: clin 0002AA and 0002AB $0
Other Administrative Action 1 · Administrative modification to revise performance start date. $0
Original award $58,256,427
Show all 29

Quick answers

Who was awarded contract 0300?

0300 was awarded to GM Gdls Defense Group, L.L.C. by ACC Warren (Army Contracting Command) on April 7, 2010.

How much is contract 0300 worth?

The government has obligated $227,033,707 on 0300.

Which agency awarded contract 0300?

ACC Warren (Army Contracting Command) awarded 0300, with funding from TACOM Life Cycle Management Command (Army Materiel Command).

Is contract 0300 an order under another contract?

Yes. 0300 is a delivery order under W56HZV07DM112, an indefinite delivery contract.

Was contract 0300 competed?

The extent of competition for 0300 was not competed.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award