Statement of work to upgrade a 5.56MM scamp primer safe pack unloader (SPU) system located in building 1 of lake city army ammunition plant. Also includes driver upgrade and wall removal.

Active Awarded Last action

Contract number
W52P1J20F0207
Awardee
Awarding agency
Obligated
$274,497,383

Award facts

Opportunity
Contract value 99% obligated
$276,379,289.29 Current and potential, with all options
Completion date 87% complete
Current and potential, with all options
Funding agency
PEO Ammunition Acquisition Support Center, Department of Defense
Set-aside
No set-aside
Competition
Full and Open Competition after exclusion of sources Negotiated Proposal / Quote
Pricing
Firm Fixed Price
Place of performance
Independence, MO 64056, USA

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Supplemental Agreement for work within scope P00051 · Lcaap - M1158 cartridge lrip stage II SOW 6 overrun $20,348,677
Supplemental Agreement for work within scope P00050 · M1158 POP extension and cdrl update $0
Supplemental Agreement for work within scope P00049 · Ngsw interim capability phase II cost overrun $2,600,000
Funding Only Action P00048 · POP extension for clin 1217AA. $1,547,140
Supplemental Agreement for work within scope P00047 · 7.62MM ALT slug EPR. $758,254
Supplemental Agreement for work within scope P00046 · Clin 1212AB ngsw interim capability PH II POP extension $0
Change Order P00045 · Race year 3. $3,008,290
Supplemental Agreement for work within scope P00044 · M1158 SOW5 bullet reclaim service addition and additional QTY update QTY for clin 1208AA $97,141,319
Supplemental Agreement for work within scope P00043 · Race year 2 POP extension $0
Funding Only Action P00042 · Clin 1209AE DE-OB. -$50,000
Supplemental Agreement for work within scope P00041 · M1158 SOW 5 dispersion testing $2,774,423
Supplemental Agreement for work within scope P00040 · Ngsw-a race year 2 funding $2,539,714
Change Order P00039 · M1158 lrip stage II SOW 6 and SOW 5 update $24,272,535
Funding Only Action P00038 · Correction of MOD P00036. $0
Supplemental Agreement for work within scope P00037 · Ngsw interim capability phase III $8,332,834
Supplemental Agreement for work within scope P00036 · Update attachment 0012 statement of work and DE-obligate amount of descoped work. -$142,068
Change Order P00035 · Updating of attachment 0008 OW statement of work (SOW) 7.62MM, M1158 cartridge manufacturing development $0
Other Administrative Action P00034 · Update NSN and REF CD for clins 1208AA and 1208AD. $0
Supplemental Agreement for work within scope P00033 · Ngsw-a facility design VE change order $1,408,083
Change Order P00032 · Update shipping location and corrected quantity for 1208AA. Updated shipping location for 1208AD. Updated POP of 1209AA. $0
Funding Only Action P00031 · Transfer of existing funds to 1208AA from 1208AD, removal of 1208AD. $1,000,000
Supplemental Agreement for work within scope P00030 · Lcaap GYM $247,727
Supplemental Agreement for work within scope P00029 · Administrative MOD $0
Supplemental Agreement for work within scope P00028 · M1158 SOW 5 $10,884,637
Supplemental Agreement for work within scope P00027 · Extend period of performance for 3 months for race at lcaap. $1,046,371
Supplemental Agreement for work within scope P00026 · Ngsw wetlands credit and essp primer testing change requests at lcaap $642,461
Supplemental Agreement for work within scope P00025 · Ngsw interim capability phase II UCO definitization $9,140,793
Supplemental Agreement for work within scope P00024 · Lcaap ngsw-a 100% clouding change request $281,535
Supplemental Agreement for work within scope P00023 · Ngsw-a manufacturing facility design value engineering change request $1,939,312
Supplemental Agreement for work within scope P00022 · Lcaap award for ngsw interim capability phase II facilitization and case option 2-3. $12,827,257
Supplemental Agreement for work within scope P00021 · The purpose of this modification is to award the ngsw-a facility design - change order for essp phase II explosive safety equipment in support of lcaap. $196,346
Change Order P00020 · The purpose of this modification is to award the ngsw design change order in support of lcaap. $1,078,609
Supplemental Agreement for work within scope P00019 · The purpose of this modification is to award the M1158 bullet manufacturing change order statement of work (SOW) in support of the lake city army ammunition… $22,025
Supplemental Agreement for work within scope P00018 · Revise ngsw interim capability phase II UCO definitization schedule $0
Supplemental Agreement for work within scope P00017 · Award undefinitized change order for the ngsw interim capability phase II effort. $20,479,700
Supplemental Agreement for work within scope P00016 · Establishing program level planning and integration activities to support the facility design, facility construction, establishment of an interim and enduring… $2,013,744
Change Order P00015 · POP extension for clin 1203AA $0
Supplemental Agreement for work within scope P00014 · Modification to design, build, install and test an improved 7.62MM ammunition can INK/print head system for the M548, M19A1 and M2A2 ammunition containers. $1,041,055
Change Order P00013 · Ngsw-a manufacturing facility design, definitize UCO for designer of record $14,718,814
Funding Only Action P00012 · The purpose of this modification is to incrementally fund clin 1208AC in support of the M1158 bullet manufacturing effort. $211,752
Supplemental Agreement for work within scope P00011 · UCO for ngsw designer of record $706,000
Supplemental Agreement for work within scope P00010 · The purpose of this modification is to award the M1158 bullet manufacturing SOW. $12,997,337
Change Order P00009 · To definitize the unpriced change order (UCO) implemented at modification P00006 of delivery order W52P1J20F0207 and update exhibit a to incorporate the… $1,035,860
Supplemental Agreement for work within scope P00008 · 7.62MM cartridge loading system effort at lcaap $2,692,775
Supplemental Agreement for work within scope P00007 · B81 neutralization upgrade-commissioning effort at lcaap $722,333
Supplemental Agreement for work within scope P00006 · The purpose of this modification is to award an unfinitized change order for the ngsw requirements analysis. $1,500,000
Supplemental Agreement for work within scope P00005 · The purpose of this modification is to award the trace manufacturing modernization phase IIB project. $231,673
Other Administrative Action P00004 · This modification revises exhibit a cdrls and the 6.8MM ngws SOW $0
Supplemental Agreement for work within scope P00003 · The purpose of this modification is to procure the 6.8MM ngsw ammunition at cold heading bullet equipment prototyping $5,048,325
Funding Only Action P00002 · This modification incorporates far 52.232-32 to allow for disbursement of performance based payments for specific efforts utilizing this type of financing. $0
Show 40 more

Latest 50 listed here. See the rest on GovTribe.

About this award

The Program Executive Office for Ammunition issued a delivery order to Olin Winchester LLC on August 3, 2020, for upgrade of a 5.56mm SCAMP Primer Safe Pack Unloader system at Lake City Army Ammunition Plant, including driver upgrade and wall removal, under a parent indefinite delivery contract with a ceiling value of $274,497,382.61.

Place of performance is Independence, Missouri. Ultimate completion date is September 30, 2027. The order is priced on a firm fixed price basis with no set-aside applied.

Quick answers

Who was awarded contract W52P1J20F0207?

W52P1J20F0207 was awarded to Olin Winchester LLC by Department of the Army (Department of Defense) on August 3, 2020.

How much is contract W52P1J20F0207 worth?

The government has obligated $274,497,383 on W52P1J20F0207. Its current value, with exercised options, is $276,379,289.

Which agency awarded contract W52P1J20F0207?

Department of the Army (Department of Defense) awarded W52P1J20F0207, with funding from PEO Ammunition (Acquisition Support Center).

Is contract W52P1J20F0207 an order under another contract?

Yes. W52P1J20F0207 is a delivery order under W52P1J19D0085, an indefinite delivery contract.

Was contract W52P1J20F0207 competed?

The extent of competition for W52P1J20F0207 was full and open competition after exclusion of sources.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award