Safety upgrades at radford army ammunition plant including: a. Air scrubber replacement at 4TH rolled powder blender operation B. High speed fire suppression system replacement in 4TH rolled powder…
Ended Awarded Last action
- Contract number
- 0050
- Awardee
-
BAE Systems Ordnance Systems Inc. UEI PFGVR4NPLNB2
- Awarding agency
-
Joint Munitions Command
Army Materiel Command, Department of Defense
- Obligated
- $1,365,662
Award facts
- Opportunity
-
- Operation of ammunition facilities Award Notice · Posted Dec 31, 2015
- Contract value 100% obligated
- $1,365,661.53 Current and potential, with all options
- Completion date 100% complete
- Current and potential, with all options
- Funding agency
- PEO Ammunition Acquisition Support Center, Department of Defense
- NAICS code
- 561210 Facilities Support Services
- PSC
- M1EA Operation Of Ammunition Facilities
- Set-aside
- No set-aside
- Competition
- Full and Open Competition · 1 offer Negotiated Proposal / Quote
- Pricing
- Firm Fixed Price
- Place of performance
- Radford, VA, USA
- Legislative mandates
-
- Walsh-Healey Public Contracts Act FAR subpart 22.6
- Service Contract Act FAR subpart 22.10
- Davis-Bacon Act FAR subpart 22.4
Award details come from SAM.gov/FPDS.
Transactions
| Action | Obligated | Date |
|---|---|---|
| Other Administrative Action | $0 | |
| Supplemental Agreement for work within scope | $0 | |
| Original award | $1,365,662 |
About this award
This firm fixed-price delivery order contract was awarded by the Department of the Army's Program Executive Office for Ammunition to BAE Systems Ordnance Systems Inc. for $1,365,661.53 to perform safety upgrades at the Radford Army Ammunition Plant in Virginia. The work includes replacing the air scrubber at the 4th Rolled Powder Blender operation, replacing the high-speed fire suppression system in the 4th Rolled Powder area, and installing a new retaining wall to replace a collapsed wall barrier in the MK 90 Press 3 operation. This contract does not have a set-aside designation. BAE Systems Ordnance Systems Inc. is the prime contractor and operates the Radford Army Ammunition Plant, which produces propellants, explosives, and pyrotechnic items to support U.S. military operations.
Description
Safety upgrades at radford army ammunition plant including: a. Air scrubber replacement at 4TH rolled powder blender operation B. High speed fire suppression system replacement in 4TH rolled powder area C. Retaining wall installation to replace collapsed wall barrier in MK 90 press 3 operation
Quick answers
Who was awarded contract 0050?
0050 was awarded to BAE Systems Ordnance Systems Inc. by Joint Munitions Command (Army Materiel Command) on December 31, 2015.
How much is contract 0050 worth?
The government has obligated $1,365,662 on 0050.
Which agency awarded contract 0050?
Joint Munitions Command (Army Materiel Command) awarded 0050, with funding from PEO Ammunition (Acquisition Support Center).
Is contract 0050 an order under another contract?
Yes. 0050 is a delivery order under W52P1J11G0002, a basic ordering agreement.
Was contract 0050 competed?
The extent of competition for 0050 was full and open competition. The government received 1 offer.
On GovTribe
See this award's full record
- Every transaction and funding action
- The awardee's other awards and teaming partners
- Similar awards and recompete opportunities
- Ask GovTribe AI about this award