1. This performance-based task order KY09 entitled, "support for the trojan nexgen family of systems" is issued on a cost plus fixed fee (with cost, no fee clins) basis in accordance with the terms…

Ended Awarded Last action

Contract number
KY09
Awardee
Awarding agency
Obligated
$46,638,009

Award facts

Contract value 53% obligated
$87,956,157.03 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Funding agency
Research Development and Engineering Command Army Materiel Command, Department of Defense
NAICS code
541330 Engineering Services
Set-aside
No set-aside
Competition
Full and Open Competition · 1 offer Multiple Award, Fair Opportunity
Pricing
Cost Plus Fixed Fee
Place of performance
Aberdeen Proving Ground, MD 21005, USA
Legislative mandates

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Funding Only Action 44 · This task order is for engineering services, technology insertion and integration, software and hardware engineering, systems integration support, test and… -$65,092
Funding Only Action 43 -$200,722
Funding Only Action 42 · The purpose of this modification is to DE-obligate excess funds. -$103,237
Funding Only Action 41 · The purpose of this modification is to RE-obligate funding $536
Funding Only Action 40 · The purpose of this modification is to DE-obligate and RE-obligate funding -$93,624
Funding Only Action 39 · The purpose of this modification is to DE-obligate excess funds -$37,219
Funding Only Action 38 · Modification 38 removes excess funding. -$15,159
Funding Only Action 37 · Modification 37 DE-obligates excess funds -$10,168
Funding Only Action 36 · Modification 36 deobligates excess funds from all three periods of performance. -$36,552
Other Administrative Action 1A -$648,135
Funding Only Action 35 · Modification 35 deobligates 8,645,844.74 in funding from option two. -$8,645,845
Other Administrative Action 34 · Modification 34 provides $107,000.00 in incremental funding and incorporates a QRC eula. $107,000
Funding Only Action 33 · Modification 33 provides $777,775.43 in incremental funding to option two. $777,775
Other Administrative Action 32 · Modification 32 provides incremental funding and incorporates the cisco eula dated may 2017. $285,750
Funding Only Action 31 · Modification 31 provides incremental funding, realigns funds and adjusts funding to align with the original purpose. $7,994,200
Funding Only Action 30 · Modification 30 is to provide $110,032.00 in incremental funding for option two. $110,032
Funding Only Action 29 · Modification 29 obligates $5,177,496.00 in funding for option two and realigns $253,000.00 in option one funding to option two. $5,177,496
Funding Only Action 28 · Modification [28] is to provide incremental funding in the amount of $228,000.00, DE-obligate incorrectly applied $4M in funding and reply the $4M with the… $228,000
Funding Only Action 27 · Modification 27 provides incremental funding to option two. $4,000,000
Funding Only Action 26 · Modification 26 is to provide incremental funding, realign funds from option one to option two and incorporate the chesapeake technology data assertion table in… $592,622
Other Administrative Action 25 · Modification 25 is to incorporate the espy commercial eula. $0
Other Administrative Action 24 · Modification 24 is to incorporate the schneider electronics (pcns & pcbe) end user agreements. $0
Other Administrative Action 23 · Modification 23 obligates $409,855.35 in funding to option two, realigns $158,000.00 from option one to option two and incorporates several eulas as section j… $409,855
Exercise an Option 22 · Modification 22 is to exercise option period 2, provide $4,443,878.00 in funding to option two and extend the period of performance of slins 1006AC, 1006AG,… $4,443,878
Other Administrative Action 21 · Modification 21 is to incorporate end user agreements (a) APC software license agreement: attachment 0013 and (b) dell enterprise license agreement (including… $0
Exercise an Option 20 · Modification 20 is to provide 364,874.32 in funding to option one, exercise option two and provide $1,916,231.99 in funding and incorporate the pure storage end… $2,280,106
Funding Only Action 19 · Modification 19 is to provide $6,671,776.80 in material and labor funding to option one. $6,671,777
Other Administrative Action 18 · Modification 18 is to incorporate the QRC eula and riders. $0
Other Administrative Action 17 · Modification 17 provides 4,135,745.00 in option year funding and incorporates four eulas. $4,135,745
Other Administrative Action 16 · Modification 16 is to incorporate two cisco eulas and narrative for the use of eulas. $0
Funding Only Action 15 · Modification 15 is to provide $2,304,514.48 in funding to option period one. $2,304,514
Funding Only Action 14 · Modification 14 is to provide 727,669.17 in funding for option period one. $727,669
Funding Only Action 13 · The purpose of modification is to realign 2,128,278.77 from the base to the option period and obligate a total 4,106,081.89 to the option period. $4,106,082
Exercise an Option 12 · Modification 12 is to exercise option period one and provide $500,196.66 in funding to the option. $500,197
Funding Only Action 11 · Modification 11 is to provide $281,557.14 in funding to the base period. $281,557
Funding Only Action 10 · The purpose of modification 10 is to provide $493,169.66 in funding in support of performance work statement 3.1,3.2, 4.0 and 7.0 for trojan nexgen… $493,170
Funding Only Action 9 · The purpose of modification 09 is to provide $2,631,480.94 in funding to support the base period in accordance with performance work statement paragraphs… $2,631,481
Funding Only Action 8 · The purpose of this modification [08] is to provide incremental funding in the amount of $575,000.00 $575,000
Other Administrative Action 7 · The purpose of this modification [07] is to correct a slin numbering error in modification 06, section b. Slin 0008AD has been RE-numbered to 0008AC. $0
Funding Only Action 6 · The purpose of this modification [06] is to obligate funding in the amount of $1,797,891.11 $1,797,891
Funding Only Action 5 · The purpose of this modification [05] is to provide funding in the amount of $387,000.00. $387,000
Funding Only Action 4 · The purpose of this modification [04] is to provide funding in the amount of $2,500,000.00. The funds are hereby obligated to the task order in accordance… $2,500,000
Funding Only Action 3 · The purpose of this modification [03] is for the following: 1. Provide funding in the amount of $152,857.14 is hereby obligated to the task order in… $152,857
Funding Only Action 2 · The purpose of this modification [02] is to obligate additional funding to the task order and to revise the material purchase approval tthreshold in the PWS. 1.… $611,628
Funding Only Action 1 · Funding MOD $255,018
Original award $1,954,925
Show all 46

About this award

This is a cost-plus-fixed-fee task order awarded by the U.S. Army Research, Development and Engineering Command (RDECOM) to CACI Technologies, LLC, a subsidiary of CACI International Inc. The task order, titled "Support for the Trojan NEXGEN Family of Systems," has a twelve-month base period with two twelve-month options, for a total potential period of performance of 36 months and a total potential value of $87,970,779.74. The task order was issued under the Rapid Response Third Generation (R2-3G) Indefinite Delivery Vehicle (IDV) contract. CACI Technologies, LLC will provide services in accordance with the performance work statement for the Trojan NEXGEN Family of Systems. No small business set-aside designation was used for this award.

Description

1. This performance-based task order KY09 entitled, "support for the trojan nexgen family of systems" is issued on a cost plus fixed fee (with cost, no fee clins) basis in accordance with the terms and conditions of contract W15P7T-10-d-D413 and modifications thereto. The R23G order number associated with this task is R23G-0808. 2. Services shall be performed in accordance with the performance work statement (PWS) entitled, support for the trojan nexgen family of systems dated 11 may 2015 as found in section c and attachment 0001 of this task order. 3. Task order KY09 has a twelve (12) month base period and two (2) twelve (12) month options. The total possible task order period of performance is for 36 months. 4. The total cost for this task order is $85,701,996.06 and the total fixed fee for this task order is $2,268,783.68 (9.25% on labor only). The total cost plus fixed fee for this task order is $87,970,779.74.

Quick answers

Who was awarded contract KY09?

KY09 was awarded to Caci Technologies, LLC by ACC Aberdeen Proving Ground (Army Contracting Command) on August 28, 2015.

How much is contract KY09 worth?

The government has obligated $46,638,009 on KY09. Its current value, with exercised options, is $87,956,157.

Which agency awarded contract KY09?

ACC Aberdeen Proving Ground (Army Contracting Command) awarded KY09, with funding from Research Development and Engineering Command (Army Materiel Command).

Is contract KY09 an order under another contract?

Yes. KY09 is a delivery order under W15P7T10DD413, an indefinite delivery contract, on Rapid Response Third Generation (R2-3G).

Was contract KY09 competed?

The extent of competition for KY09 was full and open competition. The government received 1 offer.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award