Managing observatory line-of-sight pointing jitter: a design and development process overview tutorial the primary purpose of the task is for the contractor to collect and document the industry best…

Ended Awarded Last action

Contract number
80LARC18F0142
Awardee
Awarding agency
Obligated
$50,761

Award facts

Contract value 80% obligated
$63,566.31 Current and potential, with all options
Completion date 100% complete
Current and potential, with all options
Contracting staff
NAICS code
541330 Engineering Services
Set-aside
No set-aside
Competition
Not Competed Only One Source
Pricing
Cost Plus Fixed Fee
Place of performance
El Segundo, CA, USA

Award details come from SAM.gov/FPDS.

Transactions

Action Obligated Date
Funding Only Action P00003 -$1,462
Other Administrative Action P00002 -$12,805
Supplemental Agreement for work within scope P00001 · Managing observatory line-of-sight pointing jitter-the primary purpose of the task is for the contractor to collect and document the industry best practices and… $0
Original award $65,028

About this award

This is a $63,566.31 cost-plus-fixed-fee delivery order awarded by the Langley Research Center, a civilian agency, to The Aerospace Corporation, a federally funded research and development center (FFRDC). The purpose of this task order is for The Aerospace Corporation to document industry best practices and lessons learned for predicting and managing space observatory line-of-sight jitter and micro-vibrations caused by onboard disturbance sources. The end-product will be a tutorial presentation detailing the preferred process and practices for observatory jitter/micro-vibration analysis, modeling, simulation, ground testing, and in-flight testing. This delivery order is not set aside and is part of a larger $709 million indefinite delivery, indefinite quantity (IDIQ) contract that enables The Aerospace Corporation to provide specialized engineering, evaluation, and test services across NASA's human spaceflight, science, and technology initiatives.

Description

Managing observatory line-of-sight pointing jitter: a design and development process overview tutorial the primary purpose of the task is for the contractor to collect and document the industry best practices and lessons learned over the years for predicting and managing space observatory (i.e., spacecraft bus plus instrument payload) line-of-sight jitter/rmicro-vibrations due to on-board internal disturbance sources. The end-product of this study will be a tutorial type presentation documenting and describing the preferred process and practices for observatory jitter/micro-vibration analysis, modeling, simulation, ground testing, and in-flight testing.

Quick answers

Who was awarded contract 80LARC18F0142?

80LARC18F0142 was awarded to The Aerospace Corporation by Langley Research Center (National Aeronautics and Space Administration) on July 12, 2018.

How much is contract 80LARC18F0142 worth?

The government has obligated $50,761 on 80LARC18F0142. Its current value, with exercised options, is $63,566.

Is contract 80LARC18F0142 an order under another contract?

Yes. 80LARC18F0142 is a delivery order under NNL11AA01B, an indefinite delivery contract.

Was contract 80LARC18F0142 competed?

The extent of competition for 80LARC18F0142 was not competed.

On GovTribe

See this award's full record

  • Every transaction and funding action
  • The awardee's other awards and teaming partners
  • Similar awards and recompete opportunities
  • Ask GovTribe AI about this award